The Law of Construction Delay Claims
Elements of a Delay Claim: The Basics
In federal construction projects, the Federal Circuit has established three elements that a contractor must prove to succeed on a claim for an equitable adjustment to the contract for federal government-caused delays: “liability, causation, and resultant injury.” The contractor has the burden to prove “the extent of the delay, that the delay was proximately caused by government action, and that the delay harmed the contractor.” More specifically, the contractor has the burden of proving that the federal government’s actions “affected activities on the critical path of the contractor’s performance of the contract.”
Contractual Terms Regarding the Delay Claims
Federal Construction Contracts
In federal government construction contracts, Sections 48 C.F.R. 52.233-1 and 48 C.F.R. 52.243-1 et seq. of the Federal Acquisition Regulations (FAR) prescribe contract requirements that must be incorporated into federal government contracts. Those regulations govern the resolution of disputes between contractors and the federal government. Under Sections 52.233-1 and 52.243-1 et seq., a contractor must initiate a request for a time extension or delay damages by making either a Request for Equitable Adjustment (REA) to the federal government’s contracting officer or a “Claim” under the Contract Disputes Act. A Claim is a more formal procedure, establishing a deadline for the contracting officer’s formal response, while there is no set date for the federal government’s response to an REA. An REA seeks an informal negotiation with the federal government’s contracting officer in an effort to reach a mutually agreeable settlement while better maintaining the working relationship between the contractor and the federal government. In either case, the contractor may seek monetary compensation and an extension of time before liquidated damages begin to accrue.
Contractors will often submit an REA before filing a formal Claim under the Contract Disputes Act. A contractor must notify the federal government’s contracting officer of a Claim before receiving final payment, as a release of all claims is required except for those Claims the contractor has specifically excepted from the release. If the contractor does not reach an agreement with the federal government and is not satisfied with the contracting officer’s decision on a Claim, the contractor has a right to appeal or to ask the Board of Contract Appeals or Court of Federal Claims to issue a final decision in the contractor’s favor. Detailed requirements apply to these procedures. The contractor (or its attorney) will need to review the contract and the applicable regulations to ensure that these procedures are followed.
Only the contractor may pursue these Claims. Federal anti-assignment statutes prevent a surety, assignee, or subrogee from asserting Claims for changes to the contract against the federal government except where the federal government consents to the assignment. Only when the surety is itself the “contractor” under a takeover agreement may the surety assert an REA or Claim, and then only for delays occurring during performance of the takeover agreement.
Accordingly, for the surety to recover on the contractor’s Claim for delay damages from the federal government, the surety will need to first have the contractor pursue its Claim to settlement or judgment. Once the delay damages have been added to the construction contract in response to the contractor’s own Claim or REA, the surety can step in and assert its right to those funds under the Tucker Act. The Court of Federal Claims has jurisdiction under the Tucker Act over a surety’s claim based on equitable subrogation “when the surety takes over contract performance or when it finances completion of the defaulted contractor.” A payment bond surety may also sue in equitable subrogation under a federal contract. This option requires caution and is most likely to succeed if the surety has an agreement with the bond principal while the Claim is in process because the surety must both (1) wait until the delay damages have been added to the contract price based on the bond principal’s successful Claim or REA, and (2) then assert its right to those funds before the federal government disburses them to that successful bond principal. Such arrangements may involve, for example, a financing agreement or settlement of the bond principal’s indemnity obligation by which repayment to the surety will depend in part on the outcome of the Claim or REA. If the Claim or REA appears to be well founded, the surety may agree to pay the bond principal’s attorney fees to pursue the Claim.
State and Local Public Works Contracts
State and local public works contracts may also be governed by state statutory procedures, local ordinances, and contract terms. These requirements may include written notice to the project owner within a specified number of days after a delay occurs, submission of a formal claim before suit is filed, mediation, or non-binding arbitration if the claim is below a specified dollar amount. The contract’s dispute resolution procedures and state law will need to be reviewed. In some cases, these procedural requirements may simply be contract terms that are waived if neither party requests them (e.g., a contract requirement for mediation). In other cases, they may be conditions precedent to the contractor’s right to recovery, which will defeat the contractor’s entire claim if not effected in a timely manner.
State and local projects occasionally contain more than one set of contract provisions governing remedies for delays. State public works projects may be funded by one or more federal government agencies. When that occurs, the contract may include the federal agency’s required contract terms and conditions in the form of special conditions. Where a project is funded by more than one federal agency, it may contain multiple sets of special conditions that are not entirely consistent with each other. A project architect, design engineer, or construction manager may also add their own standard contract terms to the state or local public entity’s contract form. When that occurs, it is important to review the various components of the contract for applicable requirements, rather than assume that the first relevant provision found is the only one that applies.
In addition, the surety’s right to pursue the bond principal’s claims varies by state law. Generally, the surety’s claim may be based on equitable subrogation to the bond principal’s rights, a security interest in contract funds under the indemnity agreement’s assignment provisions, and/or provisions of the indemnity agreement requiring the contract funds to be held in trust for payments to subcontractors. If only the surety’s equitable subrogation rights entitle the surety to assert the contractor’s claims for extras, including delay damages, the surety will need to follow all applicable requirements of state law to pursue its subrogation rights, including notice requirements, government claim requirements, and contractual claim requirements.
While public entities usually have their own contract form, ConsensusDocs 210 provides a standard agreement and general conditions form between owner and constructor for a public works project for use by public entities. ConsensusDocs 210, Section 6.3 through 6.5, govern delays, time extensions, and liquidated damages. No particular type of schedule analysis is required. Section 2.4.22 provides: “The ‘Schedule of the Work’ is the document prepared by Constructor that specifies the dates on which Constructor plans to begin and complete various parts of the Work, including dates on which information and approvals are required from Owner.” Section 6.2.1 requires the contractor to submit a Schedule of the Work before the first payment application. The schedule must be updated monthly “or at appropriate intervals as required by the conditions of the Work and the Project.”
Additionally, Section 6.4 requires the contractor to provide “prompt” written notice if the contractor “requests an equitable extension of the Contract Time or an equitable adjustment in the Contract Price as a result of a delay.” Notice must be provided under Section 8.4. If the contractor causes delay in completion, Section 6.4 provides that the owner “shall be entitled to recover its additional costs subject to Section 6.6.” Section 6.6 mutually waives consequential damages. Section 8.4 requires notice of a claim “within fourteen (14) Days after the occurrence giving rise to the claim or within fourteen (14) Days after Constructor first recognizes the condition giving rise to the claim, whichever is later.” Thereafter, the contractor “shall submit written documentation of its claim, including appropriate supporting documentation, within twenty-one (21) Days after giving notice, unless the Parties mutually agree upon a longer period of time.”
Section 3.13.5 allows the contractor to recover an equitable adjustment in both contract price and time if the contractor “incurs additional costs or is delayed due to the presence or remediation of Hazardous Material.”
Private Construction Contracts
In private construction projects, the contractor’s rights may be governed by detailed contract provisions in a standard form, or they may be governed by unique terms and conditions of a contract form drafted by the project owner. This section provides a survey of well-known standard form private contract provisions related to delay claims.
American Institute of Architects (AIA) Document A201
Section 3.10 of AIA Document A201-2017 General Conditions governs the contractor’s construction schedules for the project. Subsection 3.10.1 provides that the contractor “promptly after being awarded the Contract, shall prepare and submit for the Owner’s and Architect’s information a Contractor’s construction schedule for the Work.” No particular type of schedule or software is specified. Article 8 of the AIA Document A201-2017, General Conditions, governs delays and time extensions. It does not prescribe a specific type of schedule analysis for time extension requests.
Section 8.3.2 provides that “Claims related to time shall be made in accordance with applicable provisions of Article 15,” the “Claims and Disputes” provision. Section 8.3.3 provides that Section 8.3 “does not preclude recovery of damages for delay by either party under other provisions of the Contract Documents.”
Article 15 of the AIA A201-2017 applies to delay claims. Section 15.1.3.1 requires written notice to the owner and initial decision maker “within 21 days after occurrence of the event giving rise to such Claim or within 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later.” This notice provision may be difficult to apply in that it turns on when the contractor “recognizes” the condition causing the delay. Different personnel may “recognize” a problem at different points in time, making it difficult to pinpoint when the contractor recognized it would have a delay claim.
Section 15.1.6.1 provides that claims for additional time require written notice and shall include “an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.” Section 15.1.6.2 provides that claims for “adverse weather conditions” must be “documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.” Section 15.1.7 waives claims for consequential damages including “loss of management or employee productivity” among other damages for both the Owner and the Contractor.
Section 15.2 provides for the architect to be the initial decision maker unless otherwise indicated in the agreement and shall decide in writing following specified procedures. Mediation, arbitration, or (if the parties choose not to arbitrate) court action can proceed thereafter.
Standard forms still require scrutiny. Any contract may include special or supplementary conditions that alter the contractor’s right to delay damages or time extensions. Supplementary conditions may be unique to the individual contract. Parties also may modify portions of the standard form provisions by inserting additional terms or conditions or by striking out portions of the standard provisions.
EJCDC Documents C-700 and C-800
The Engineers Joint Contract Documents Committee (EJCDC) revised its Construction Series Documents in 2018. The revised Section 4.05 of its EJCDC C-700 Standard General Conditions of the Construction Contract clarifies the contractor’s right to relief for delays. While no particular type of schedule analysis is required, the new provisions specifically refer to the requirement of showing the delay’s effect on the critical path. New Section 4.05.E provides that the project owner or engineer may require “a revised progress schedule indicating all the activities affected by the delay, disruption, or interference, and an explanation of the effect of the delay, disruption, or interference on the critical path to completion of the Work.”
Section 2.03 requires the contractor to provide, within ten days after the effective date of the contract, a “preliminary progress schedule” indicating times for starting and completing various stages of the work. Section 2.05.A.1 provides: “The Progress Schedule will be acceptable to Engineer if it provides an orderly progression of the Work to completion within the Contract Times.” Thus, while the contract does not require a CPM schedule, in the event of a delay claim, the contractor must be prepared to provide a revised schedule with an explanation of the effect of the delay on all affected activities.
Under Section 4.05.A, “If Owner, Engineer, or anyone for whom Owner is responsible, delays, disrupts, or interferes with the performance or progress of the Work, then Contractor shall be entitled to an equitable adjustment in Contract Price or Contract Times.” The 2018 revision omits a sentence in the 2013 document that conditioned the adjustment “on such adjustment being essential to Contractor’s ability to complete the Work within the Contract Times.”
Section 4.05.C contains detailed provisions regarding equitable adjustments in contract times, but not monetary awards, for specified unanticipated causes not attributable to either the contractor or the owner (force majeure), such as “abnormal weather conditions” and certain natural catastrophes. EJCDC Document C-800 includes a proposed Supplemental Condition that allows the parties to further detail which weather conditions will be “abnormal” by objective factors, such as a specific amount of precipitation and specific temperatures measured and recorded at a designated weather station.
Newly revised Section 4.05.D and new Section 4.05.E condition the adjustment on the delay, disruption or interference “adversely affecting an activity on the critical path to completion of the Work, as of the time of the delay, disruption, or interference” and contain requirements for change proposals based on delay, disruption, or interference. Such change proposals must be “supplemented by supporting data,” including specific categories of information listed in the contract. The new Section 4.05.E concludes:
Contractor shall also furnish such additional supporting documentation as Owner or Engineer may require including, where appropriate, a revised progress schedule indicating all the activities affected by the delay, disruption, or interference, and an explanation of the effect of the delay, disruption, or interference on the critical path to completion of the Work.
ConsensusDocs Documents 200 and 230
Unlike ConsensusDocs 210, Public Works Projects, discussed above, ConsensusDocs 200, Lump Sum, and 230, Cost Plus, expressly require a critical path project schedule. Both contract forms include Section 6.2.1, which provides:
Except as otherwise agreed, the Schedule of the Work shall be formatted in a detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work, and (b) identifies dates that are critical to ensure timely and orderly completion of the Work. Constructor shall update the Schedule of the Work on a monthly basis or as mutually agreed by the Parties.
The ConsensusDocs’ change order provisions do not require any particular type of schedule analysis to support a request for an equitable adjustment of contract time or price. However, since the contract requires the contractor to perform monthly CPM schedule updates, a CPM analysis will undoubtedly be required under the provisions requiring “appropriate supporting documentation” for the claim.
Section 6.3 of both forms contains a detailed provision for an equitable extension of contract time for “causes beyond the control of Constructor” including “acts or omissions of Owner, Design Professional, or Others” and “changes in the Work or the sequencing of the Work ordered by Owner, or arising from decisions of Owner that impact the time of performance of the Work,” as well as “adverse weather conditions” and other items on a detailed list of possible causes of delays. For only four of the thirteen causes of delays, Section 6.3.2 also allows the contractor to request an equitable adjustment in the contract price. For delays caused by the owner, design professional, or others, hazardous materials, unknown conditions, and other items among those four causes, the contractor’s claim for delay damages and time extension is made under the contract’s changes provision.
Section 6.4 provides that if the contractor seeks an equitable time extension or an equitable adjustment to contract price for delay, “Constructor shall give Owner written notice of the claim in accordance with” the provision requiring notice of changes.
Section 8.4 of Document 200 provides for notice “within fourteen days after the occurrence giving rise to the claim or within fourteen days after Constructor first recognizes the condition giving rise to the claim, whichever is later.” Thereafter, “Constructor shall submit written documentation of its claim, including appropriate supporting documentation, within twenty-one days after giving notice, unless the Parties mutually agree upon a longer period of time.” Paragraph 9.4 of Document 230 requires notice of the claim within twenty-one days, rather than within fourteen days. As for Document 200, the contractor must provide “written documentation of its claim, including appropriate supporting documentation” within twenty-one days after giving notice.
Cases Concerning the General Requirements for a CPM Schedule Analysis
While CPM schedules (usually through Primavera P6 software) are not always legally necessary, they may be required by contract or regulation, and they are widely recognized by courts as an established way of proving the cause and amount of time associated with a delay. This section canvases how various courts have treated delay claims brought with or without the aid CPM schedules.
In PCL Construction Services, Inc. v. United States, the court stated: “One established way to document delay is through the use of CPM schedules and an analysis of the effects, if any, of government-caused events upon the critical path of the project.” The Civilian Board of Contract Appeals quoted PCL in Yates-Desbuild Joint Venture v. Department of State, adding: “In fact, in situations, as here, where the contractor utilized Primavera scheduling software to create schedules throughout the life of the project, it would be folly to utilize some other method of critical path analysis.”
Similarly, in Morrison Knudsen Corp. v. Fireman’s Fund Ins. Co., the court stated:
Courts often use CPM to resolve disputes over excusable-delay claims. See Cibinic Nash, supra, at 584. CPM provides a useful, well-developed nomenclature and analytic framework for expert testimony. While CPM has generated a technical terminology, the legal requirement that it is used to analyze is general and commonsensical: a contractor must prove that a delay affected not just an isolated part of a project, but its overall completion.
Though not legally required, failing to use a systemic schedule analysis tool like a CPM schedule may prove fatal to a delay claim. In 1-A Construction & Fire, LLP v. Department of Agriculture, the board found that a defaulted contractor had failed to meet its burden of proving excusable delays under the contract’s default provision by failing to “demonstrate how the delay, or delays, affected activities on the contract’s critical path and impacted the contractor’s ability to finish the contract on time.” Specifically, the board held:
To show how the critical path of contract performance evolved over the life of the contract and how excusable delays impacted that path, a contractor, at a minimum, needs a reasonable “as planned” schedule and an “as built” schedule, which it can incorporate into an analysis to show “the interdependence of any one or more of the work items with any other work items” as the project progressed.
The contractor never used an “as planned” schedule on the project, and, therefore, the Board concluded that the contractor “[could not] show that any excusable delay actually impacted its ultimate contract completion.” The board thus sustained the contract termination and dismissed the contractor’s request for damages.
In CEMS, Inc. v. United States, the court denied recovery to the contractor, finding that while the contractor argued that its schedules were CPM schedules, they did not “provide the court with the ability to determine whether the alleged delays claimed by the plaintiff were on the critical path” and had not shown its claims to have been based on much more than its superintendent’s own “estimates and speculation.”
The Second Circuit Court of Appeals has held that while the contractor must show a delay on the critical path, it may satisfy that burden through evidence and testimony that accomplish the same objective as a CPM schedule.
State law is generally to the same effect. For example, California courts have held that a contractor may recover its extended overhead loss due to delay “especially when . . . the contractor has prepared a critical path schedule, for any delay along the critical path results in the delay of the overall project.” However, in Howard Contracting, Inc. v. G.A. MacDonald Construction Co., a California appellate court held that a contractor is not required to use a CPM schedule to establish critical path delays where a bar chart schedule is based on a critical path method analysis.
Applying Texas law in United States ex rel. CMC Steel Fabricators v. Harrop Construction Co., the court carefully considered the opinions of two scheduling experts and then modified the one it thought best, based on the testimony of a percipient witness:
The Court weighs heavily McCullough’s estimate. Using the critical path methodology, Mr. McCullough provided a tighter analysis and did a better job tying and analyzing relationships between job occurrences and job events, providing a tighter and more conservative approach to the flow of events and therefore delays. The CPM is an accepted and even favored methodology for such analysis . . . . Of the experts, the Court credits McCullough and Popescu but believes following their model too closely disregards the testimony of the contractor’s supervising employees such as Jack Mount and Judy Jones. The Court’s own review convinces it that Mr. McCullough’s total project costs are low by approximately $300,000.
As with federal law, though not legally required under state law, failure to systemically track schedule impacts through a method such as CPM may present issues when seeking delay damages. In Sheraton Operating Corp. v. Castillo Grand, LLC, a New York trial court held, applying Florida law: “One way, but not necessarily the exclusive way, to demonstrate that the defendant delayed the project is by use of ‘critical path’ analysis . . . . Thus, in assessing the issue of responsibility for delay in completion of an entire project, the focus is on delays along the critical path.”
In Plato General Construction Corp. v. Dormitory Authority of the State of New York, a New York trial court declined to dismiss affirmative defenses related to change orders, noting a lack of proof of causation of delays. The defendant public entity was responsible for creating and maintaining a CPM with the input from each of the trades in a multi-prime construction project. Having delayed in awarding an HVAC contract, the public entity was unable to provide a valid CPM. Nonetheless, the plaintiff-general contractor had the burden of proof on the causation of delays. The court concluded that “[i]f there is no connection between the damages and whatever [the particular reason for the delay], including the failure to provide a critical path method schedule, . . . there will still be no recovery . . . . [Y]ou have that burden.” Because the public entity’s actions left the contractor without a valid CPM schedule, the contractor’s ability to prove its damages was hampered; yet the court would not allow the contractor to prevail without finding some other way to prove the cause of the delay. At trial, the lack of a CPM schedule left the plaintiff “unable to provide the proof of plaintiff’s degree of responsibility for any particular failing.” Nonetheless, the court found clearly delays associated with specific scopes of work, noting that “[d]efendant’s attempt to attribute to plaintiff delay in the excavation and erection of the superstructure of the new addition is unavailing. It is clear, even by Turner’s own admissions, that substantial delay at the beginning of the Project was attributable to defendant.” Ultimately, the court found sufficient evidence to allocate fault and awarded judgment to the plaintiff for its delay damages in a net amount of $10,106,698.00.
Courts often evaluate the need for CPM evidence and the importance given to it on a case-by-case basis, considering how persuasive the presentation is in the context of the facts of a particular case. The cases discussed above are examples of how trial court judges and appellate court judges view that evidence; what they do when they find the underlying facts insufficient to support the conclusions; and what they do when the evidence they wish they had simply is not there due to no fault of the contractor who suffered a loss. In preparing a delay claim for trial, whether in the Claims Court or a state, or federal trial court, it is essential to consider how persuasive the evidence will be taken together in the context of the facts of the case as a whole.
The availability of a sophisticated and accurate CPM analysis will usually be an important and persuasive part of that evidence in a delay damages case.
Demonstrating the Schedule’s Reliability
For the schedule analysis to be persuasive, the initial data must be accurate and supported by the evidence. A scheduling expert’s analysis cannot compensate for insufficient admissible evidence of the underlying facts. The following are examples of cases that have addressed schedule reliability issues.
In Mega Construction Co. v. United States, the Court of Federal Claims found that the contractor’s expert’s bar chart analysis was “unsubstantiated and incomplete,” drawing from documents that were not identified in the record or were successfully refuted by the defendant. The analysis drew from the plaintiff’s construction logs, which the court considered “highly suspect.”
In 1-A Construction, relying on Mega Construction Co., the Board of Contract Appeals held that the contractor, at a minimum, needed a reasonable “as planned” schedule and an “as built” schedule to show whether delays were on the critical path, which the contractor did not have. The lack of a complete schedule at the beginning of the project was also discussed in Edwin J. Dobson Jr., Inc. v. Rutgers, State University, where the contractor did not have a complete “as planned” schedule until the third update, and only then had sufficient information to measure a delay.
The board in Yates-Desbuild provided an insightful comment concerning the issue of schedule reliability:
Nevertheless, the existence of contemporaneous schedules does not permit a tribunal to ignore, or fail to consider, logic errors in those schedules. A CPM schedule, even if maintained contemporaneously with events occurring during contract performance, is only as good as the logic and information upon which it is based. CPM is not a ‘magic wand,’ and not every schedule presented will or should be automatically accepted merely because CPM technique is employed.
In Hoffman Construction Co. v. United States, the court found that the plaintiff “has not presented any specific, persuasive evidence or analysis demonstrating how any government action . . . caused [the contractor’s] overruns. A contractor must present more than general, unsubstantiated pronouncements from its own witnesses that various acts of the government caused labor overruns.”
In Transtechnology Corp., Space Ordinance Division. v. United States, an inefficiency claim failed where the court found:
There is no testimony of a single specific interruption or slowdown, and therefore nothing concrete in terms of length of interruption, what happened on the production line, who made decisions about whether to keep workers in place, whether other tasks could be performed, or how often interruptions occurred.
Additionally, in Appeal of Santa Fe, Inc., the Veterans Administration Board of Contract Appeals discussed the importance of updates to the CPM where the contractor was responsible for the accurate and timely submission of all CPM data necessary to produce monthly computer reports while the project was ongoing. The board rejected the contractor’s proposed revisions to a November CPM offered in the course of litigating the claim: “We give little weight here to the Contractor’s proposed revisions to the November CPM. That is not to say that we would never allow such revisions. We are simply not persuaded that suggested revisions are correct and that the CPM was wrong at the time it was created.” However, the board would not totally disregard the October CPM as the federal government suggested: “There is a rebuttable presumption of correctness attached to CPM’s upon which the parties have previously mutually agreed. [I]n the absence of compelling evidence of actual errors in the CPM’s, we will let the parties ‘live or die’ by the CPM applicable to the relevant time frames.”
It is important to both consider available technology and expertise, as well as to ensure that the expert has available as much supporting evidence as possible, and preferably accurate CPM schedule information prepared in the course of the project.
Acceleration Claims
“Acceleration” refers to a contractor’s losses due to increasing the amount of labor provided to a project to make up for a delay and comply with the project owner’s insistence that the contractor work faster. The owner’s directive may be either (1) a directive due to the contractor’s own delays, which plainly are not compensable; (2) an express directive due to the owner’s desire to complete construction in a shorter amount of time than provided by contract; or (3) an implied directive to complete construction in a shorter time than provided by contract, such as where the project owner refuses to grant a time extension to which the contractor is legally entitled.
The court in Fraser Construction Co. v. United States, provided an excellent explanation of acceleration claims:
A claim of acceleration is a claim for the increased costs that result when the government requires the contractor to complete its performance in less time than was permitted under the contract. The claim arises under the changes clause of a contract; the basis for the claim is that the government has modified the contract by shortening the time for performance, either expressly (in the case of actual acceleration) or implicitly through its conduct (in the case of constructive acceleration), and that under the changes clause the government is required to compensate the contractor for the additional costs incurred in effecting the change.
The elements of a claim for constructive acceleration are the following:
(1) that the contractor encountered a delay that is excusable under the contract; (2) that the contractor made a timely and sufficient request for an extension of the contract schedule; (3) that the government denied the contractor’s request for an extension or failed to act on it within a reasonable time; (4) that the government insisted on completion of the contract within a period shorter than the period to which the contractor would be entitled by taking into account the period of excusable delay, after which the contractor notified the government that it regarded the alleged order to accelerate as a constructive change in the contract; and (5) that the contractor was required to expend extra resources to compensate for the lost time and remain on schedule.
Acceleration claims often occur together with claims for other forms of delay damages. When the owner disputes the cause of a delay, it is common for the owner to expressly or impliedly demand that the contractor work faster to finish the project more quickly. Counsel, parties, and schedule consultants should keep the concept of acceleration in mind as they consider the facts, the analysis, and the resulting loss.
Concurrent Delays
The court in George Sollitt Construction, explained the analysis of concurrent delays as follows:
The exact definition of concurrent delay is not readily apparent from its use in contract law, although it is a term which has both temporal and causation aspects. Concurrent delays affect the same “delay period.” See Tyger Constr. Co. v. United States, 31 Fed. Cl. 177, 259 (1994) (“In cases of concurrent delay, where both parties contributed significantly to the delay period by separate and distinct actions, justice requires that the cost of the delay be allocated between the two parties proportionally.”). A concurrent delay is also independently sufficient to cause the delay days attributed to that source of delay. See Beauchamp Constr. Co. v. United States, 14 Cl. Ct. 430, 437 (1988) (noting that a concurrent action “would have independently generated the delay during the same time period even if it does not predominate over the government’s action as the cause of the delay” (citations omitted)).
The court provided for an apportionment of delays and, thus, a proportionate recovery of damages only where “clear apportionment” of the delay attributable to each party has been established. Unless the claimant contractor can meet its burden of proof of “clear apportionment,” the general rule bars recovery for government-caused delays where a concurrent delay is caused by the contractor. Except where clear apportionment can be shown, the general rule prevents recovery of delay damages in the event of concurrent delays. Accordingly, in Weaver-Bailey Contractors, Inc. v. United States the court held: “Only if the delay was caused solely by the government will the contractor be entitled to both an extension of time within which to perform, and recovery of excess costs associated with the delay.”
Several cases likewise have allowed apportionment of liquidated damages where clear apportionment can be shown. In courts that follow the traditional rule against apportionment, where the federal government has caused part of the delay to project completion, the rule against apportionment prevents government recovery of liquidated damages, thus allowing the contractor a time extension but no delay damages. In courts that allow apportionment, the federal government’s liquidated damages claim is barred if the causes are intertwined, and apportioned where the government can show a clear apportionment of the delay attributable to the contractor.
Outside of the context of federal construction contracts, the provisions of the contract and state law may provide for (1) the traditional rule of no recovery to either party in the event of concurrent delays or (2) apportionment of damages. The EJCDC C-700 Standard General Conditions of the Construction Contract §4.05(D)(2), for example, provides:
Contractor shall not be entitled to an adjustment in Contract Price for any delay, disruption, or interference if such delay is concurrent with a delay, disruption, or interference caused by or within the control of Contractor. Such a concurrent delay by Contractor shall not preclude an adjustment of Contract Times to which Contractor is otherwise entitled.
Where the contract establishes the contractor’s right (or lack of right) to delay damages, or the owner’s right (or lack of right) to recover liquidated damages in the event of concurrent delays, most courts will enforce the parties’ agreement.
Conclusion
The four forensic scheduling methodologies discussed in this paper are commonly deployed to claim both excusable and compensable delays on construction projects by contractors, while owners use these same methodologies to rebut affirmative claims and to establish that asserted delay claims are non-excusable or non-compensable. Depending on the quality and availability of scheduling information, project participants should make an informed decision about which scheduling method to use. In addition, understanding the project schedule is a critical skill for successful claims handling. The schedule is often the source of conflict and later the source of relief. Working with owners and claimants to understand their scheduling concerns goes a long way towards reaching a favorable result. When this is not possible, the construction professional needs to have a keen understanding of the basic principles of delay claims, any contractual requirements regarding notice and presentation of same, and how the courts have ruled when confronted with varying schedule analysis methodologies.