C. Compensable v. Non-Compensable Delays
If an excusable delay exists, one must further determine if it is a non-compensable or compensable delay. One place to start such an analysis is the contract between the parties, as it will likely govern whether a delay is compensable or non-compensable.
1. Non-Compensable Delays.
Non-compensable delays, commonly referred to as excusable and non-compensable, are delays for which the contractor is entitled to a time extension but not entitled to additional monetary compensation. When a non-compensable delay exists, neither party is responsible for the other party’s damages. In such cases, both parties absorb their own additional costs arising out of the delay. For example, the contractor absorbs its delay costs for being on the project longer, and the owner absorbs its costs associated with the delay. In this case, the owner would grant an excusable/non-compensable time extension to complete the contracted work. These delays are typically addressed in the context of force majeure events and encompass such things as strikes, acts of God, and other delays that are not reasonably foreseeable.
a. Application of a Force Majeure Clause
A force majeure clause’s primary purpose is to relieve a party from certain duties when performance was prevented by some force beyond its control or when the purpose of the contract was frustrated. Force majeure clauses are typically construed in strict accordance with their terms and usually only excuse a party’s performance if the event causing the delay or nonperformance is identified in the clause. Courts typically interpret force majeure clauses in strict accordance with their terms, or at the very least, in strict accordance with what the courts determine to be the intent of the parties in drafting such clauses.
“To determine whether a certain event excuses performance, a court should look to the language that the parties specifically bargained for in the contract to determine the parties’ intent, rather than resorting to any traditional definition of the term.” “In other words, when the parties have themselves defined the contours of force majeure in their agreement, those contours dictate the application, effect, and scope of force majeure.”
Courts also generally consider the parties’ reasonable expectations and whether those expectations and the overall contract performance have been frustrated by a circumstance beyond either party’s control. In the construction context, courts specifically consider whether the contractor contributed to or caused the delay or non-performance. If the force majeure clause may be invoked, courts then look to that clause to determine the appropriate relief to be awarded to the parties.
b. COVID-19
Since 2020, courts have been forced to determine whether and to what extent the COVID-19 Pandemic and other epidemics/pandemics may qualify as a force majeure event. Many courts interpreting force majeure clauses including the words “pandemic,” “epidemic,” or “natural disaster” have recognized that the COVID-19 Pandemic constituted a force majeure event as an unanticipated “act of God” that was clearly not caused by anyone working on the jobsite and could not have been reasonably anticipated. These courts reasoned that the contractors that were unable to perform their work as a direct result of the pandemic were entitled to excusable and oftentimes compensable delays.
However, some courts concluded that claims of delay resulting from the hardships brought on by the COVID-19 Pandemic could not be relied upon to excuse performance under the parties’ contract.
Merely because an event is unforeseeable or is a triggering event listed in or reasonably contemplated by a force majeure provision does not automatically excuse a party from performing. Rather, the party seeking to excuse its performance based on force majeure must prove that the unanticipated triggering event was the direct cause of the parties’ inability to complete their contractual obligations. Some courts require proof that the triggering event rendered performance impossible, not just financially difficult or a hardship. Similarly, some courts have held that when a contract can be performed in either of two alternative ways, the impracticability of one alternative does not excuse the promisor of performance if the other alternative is still practicable.
In the future, delays caused by the COVID-19 Pandemic and other pandemics/epidemics may be deemed excusable but could be deemed non-compensable given that all contractors arguably should now anticipate that the emergence of another virus or similar force majeure event could delay a project. Contractors might have better results in focusing their arguments on changes in the law or other governmental action, such as temporary orders to stop all work for extended periods of time to slow the spread, that make the entirety of their work impossible in seeking to excuse their performance.
c. Weather Events
Weather related delays are also typically excusable but not compensable. To obtain compensation for weather related delays, the contractor must generally prove the weather was unusually severe and delayed the critical path. Unusually severe weather is typically demonstrated through historical weather data that shows the contractor could not have reasonably foreseen the nature and extent of the weather event at issue.
Nonetheless, the occurrence of unusually severe weather will not necessarily warrant a time extension. Indeed, even if the weather is proven to be severe, unusual, and/or unforeseeable, the contractor will likely not be entitled to compensation for weather related delays if it cannot prove the event delayed the critical path. For example, if the building is enclosed and the unusually severe weather had no effect on the contractor’s ability to perform its interior work, then there would be no critical path delay and a time extension would not be warranted.
Some federal agencies, particularly the United States Army Corps of Engineers, have contractually specified the precipitation that is anticipated in a particular area. Like most commercial construction contracts, the Corps of Engineers’ contracts will identify the number of days a specified amount of rain is expected each month for each year in that part of the country. The contractor is expected to account for the “expected” number of rain days in its project schedule. Oftentimes, the excusable/compensable days of delay are limited to only the number of rain days that occur over and beyond the contractually agreed upon number of rain days. For example, the Corps of Engineers will consider unusually severe weather only if the contractor can prove that the amount of rain over a certain number of days exceeded the amount of rain and the number of days specified in the contract. However, a careful reading of the contract is required to ensure what is exactly specified concerning weather and if the contractor could be entitled to compensation.
In short, even if the contractor can successfully prove that it was delayed by an unanticipated, unforeseeable, or uncontrollable event such as a flood, weather, or a strike, the delay may warrant a time extension but typically the contractor is not entitled to compensation for the delay; but neither is the owner. Concurrent delays, discussed in detail below, are another example of excusable/non-compensable delays.
2. Compensable Delays
Compensable delays are unforeseeable delays to the critical path that are beyond the contractor’s control or fault and entitle the contractor to both a time extension and additional compensation. Determination of the critical path is necessary for determining if a delay is compensable because only work on the critical path has an impact upon the time in which the project is to be completed.
Courts have held that a critical path delay is compensable if it was entirely caused by events within the other party’s control. However, if a contractor is unable to prove that the owner was responsible for the event(s) that caused the delay, then the delay is excusable but non-compensable. Normally, a compensable delay is caused by the owner or its agent, but one could also be caused by “no fault” events such as acts of God and the like. Common causes of compensable delays include: material changes in the design or the contract terms; suspensions of work; the owner’s refusal or inability to provide site access; untimely review of submittals, shop drawings, or responses to requests for information by the owner’s design team; delayed issuance of the notice to proceed; defective plans and specifications; and differing site conditions.
There are many instances where various courts have found that certain actions of a party, such as that of an owner, have resulted in compensable delays. Examples include: (1) directing the contractor to perform its operations in sequences that differ from those set forth in the contract documents; (2) requiring the contractor to meet stricter tolerances than those set forth in the specifications; (3) providing a contractor with defective plans and specifications; and (4) failing to timely issue written change orders for changes or additional work.
A contractor may also seek compensation for delays from downstream subcontractors resulting from late delivery of materials, lack of labor, and other issues arising from the subcontractors’ failures to timely commence or complete their own work. In such cases, courts have required the contractor to prove that its subcontractor was the sole or primary cause for the delay period for which the contractor seeks damages.
D. Concurrent Delays.
In analyzing delays, it is also important to determine whether a concurrent delay exists. In general, a concurrent delay refers to the situation when the critical path of a construction project is delayed by two or more events at the same time, for only one of which the contractor bears responsibility. Usually, the two or more independent delay events may overlap and delay the critical path for a similar or the same period of time. This results in concurrent or sequential delays to the project’s critical path. Concurrent delays occur “where both parties are responsible for the same period of delay.” Concurrent delays have been defined by some courts as delays to the critical path caused concurrently by multiple events not exclusively within the “control of one party.” When concurrent delays exist, neither party may benefit monetarily from the delay. Thus, concurrent delays are typically excusable/non-compensable delays from the contractor’s perspective.
To establish concurrency, the delay must be involuntary and the delayed work must be substantial and not readily curable. The party claiming concurrency must also establish two major functional requirements relating to the relationship between the delays: (1) the delays occurred during or impacted the same time analysis period; and (2) each event/condition would have independently delayed the critical path absent the other event/condition.
Project schedules, which are typically presented in some form of network, are intended to identify both project activities and their interdependencies. A project network functions as a basis and an essential input to the process of assessing concurrent delays. For example, a concurrent delay can arise from the concurrence of both a non-excusable and excusable delay or a compensable and non-excusable delay. Generally, a concurrent delay is treated as an “excusable delay” entitling a contractor to an extension of contract time, but not entitling the contractor to additional costs or exposing the contractor to liability for liquidated damages or the owner’s delay damages. Thus, an owner’s compensable delay that concurs with a contractor’s inexcusable delay would offset each other; neither party would be entitled to monetary compensation, and the only remedy available would be an extension of the contract time.