chevron-down Created with Sketch Beta.

ARTICLE

Oil Pipelines Fall 2019 Report

Daniel J Poynor, Steven Adducci, Steven H Brose, Eugene Richard Elrod, and Erica Rancilio

Summary

  • The Pipeline and Hazardous Materials Safety Administration’s regulations allow any interested person to file a petition for reconsideration of the final rules within 30 days of publication in the Federal Register.
  • On December 21, 2018, MPLX Ozark Pipe Line LLC filed an application for authorization to charge market-based rates for the transportation of crude oil on its pipeline system from Cushing, Oklahoma, to Wood River, Illinois.
  • Quality Bank’s valuation of the Trans Alaska Pipeline System crude streams has been the subject of extensive litigation at the Federal Energy Regulatory Commission, the Regulatory Commission of Alaska (and predecessor agencies), and the U. S. Court of Appeals for the D.C. Circuit since the late 1980s.
Oil Pipelines Fall 2019 Report
alacatr

A. Introduction

The following report highlights the most significant developments with respect to oil pipeline regulation since our 2019 Spring Report. With respect to oil pipeline regulation by the Federal Energy Regulatory Commission (“FERC” or “Commission”), one of the most noteworthy developments since our 2019 Spring Report involved petitions for declaratory orders where approval of various committed rate structures are sought in support of new pipeline projects and expansions. In recent orders on petitions for declaratory orders, the Commission has rejected requests for waiver of initial rate regulations and made some orders contingent on compliance with 18 C.F.R. § 342.2, which requires a supporting affidavit or cost data to establish initial committed rates. This and other matters of interest are summarized below.

B. Pipeline Safety Developments

1. Reauthorization

The U.S. Congress is in the process of considering legislation to reauthorize the Pipeline Safety Act. The current authorization, enacted in the Protecting our Infrastructure of Pipelines and Enhancing Safety Act of 2016 (“PIPES Act”), expires on September 30, 2019. Congress had held several hearings on reauthorization and introduced competing bills in the U.S. House of Representatives and U.S. Senate. The U.S. Department of Transportation (“DOT”) has also released a legislative proposal that reflects the current administration’s priorities, such as encouraging the use of new technologies in a pilot program, expediting the review of the technical standards that are incorporated by reference into PHMSA’s regulations, and imposing additional criminal sanctions for pipeline vandalism.

2. Rulemaking

a. Upcoming Final Rules

i. Safety of Hazardous Liquid Pipelines and Emergency Order Authority Rulemakings

On September 24, 2019, U.S. Secretary of Transportation Elaine Chao announced that two final rules from the Pipeline and Hazardous Materials Safety Administration (“PHMSA”) had been sent to the Office of Federal Register for publication. The first final rule will amend various provisions in the federal safety standards for hazardous liquid pipelines (49 C.F.R. Part 195). The second final rule will modify the interim procedural requirements for issuing emergency orders to address imminent hazards (49 C.F.R. § 190.236). Both final rules are expected to publish in the Federal Register on or about October 1, 2019.

The Part 195 final rule is expected to extend new reporting requirements to gravity lines and certain unregulated rural gathering lines; require inspections of pipelines in areas affected by extreme weather, natural disasters, and other similar events; require periodic assessments of pipelines that are not currently regulated under the integrity management (“IM”) program requirements; modify the requirements for leak detection systems; and expand the use of inline inspection tools for pipelines covered under the IM requirements. Two mandates from the PIPES Act involving the submission of safety data sheets after pipeline releases and the performance of integrity assessments for certain underwater pipeline facilities are also expected to be addressed in the final rule. The emergency order final rule is expected to amend the interim regulations that went into effect on October 14, 2016, pursuant to the authority provided in the PIPES Act.

PHMSA’s regulations allow any interested person to file a petition for reconsideration of these final rules within 30 days of publication in the Federal Register. The Pipeline Safety Act also provides for judicial review if a petition for review is filed in the U.S. Courts of Appeal within 89 days of the final rule’s publication.

b. Upcoming Notice of Proposed Rulemakings

i. Amendments to Part 195 to Require Valve Installation and Minimum Rupture Detection Standards

PHMSA is proposing to revise the hazardous liquid pipeline safety regulations to establish new performance requirements with the purpose of improving rupture mitigation and shortening pipeline segment isolation times in HCAs and certain non-HCA areas. PHMSA will be proposing valve maintenance and inspection requirements and 911 notification requirements. PHMSA anticipates publishing this notice of proposed rulemaking before the end of 2019.

ii. Repair Criteria

PHMSA will be initiating a regulatory reform rulemaking to amend the repair criteria in the IM regulations for pipelines in high consequence areas (“HCAs”) and establish new criteria for pipelines outside of HCAs. PHMSA anticipates publishing a notice of proposed rulemaking in this proceeding sometime in 2020.

3. Enforcement

PHMSA has initiated 136 enforcement actions so far in 2019, including 2 corrective action orders, 40 notices of probable violation, 39 notices of amendment, 54 warning letters, and 1 notice of proposed safety order. PHMSA has proposed approximately $2.9 million in total civil penalties this year, an amount that is significantly lower than the approximately $7.1 million in total civil penalties proposed in 2018.

4. Litigation

a. Plains All American Pipeline, L.P.

On September 7, 2018, the Santa Barbara Superior Court found Plains All American Pipeline, L.P. (“Plains”) guilty on nine counts in relation to an oil spill in 2015 that released 140,000 gallons of crude oil into the Pacific Ocean. The Court found that Plains was guilty for failing to properly maintain its pipeline, failing to call emergency response in a timely fashion, killing marine mammals, protected sea birds, other sea life, and “discharging oil onto land or water, in violation of county ordinances.” In April 2019, the Court issued its sentence in the case, imposing a $3.3 million fine.

b. WildEarth Guardians v. Chao

On August 14, 2018, WildEarth Guardians filed a complaint in the United States District Court for the District of Montana, alleging that DOT and PHMSA violated the Mineral Leasing Act (“MLA”) by failing to annually examine and inspect oil and gas pipelines and associated facilities on Federal lands. The plaintiffs are seeking declarative and injunctive relief for violations of the Administrative Procedures Act, 5 U.S.C. § 706, and the MLA, 30 U.S.C. § 185(w)(3).

The MLA requires that “[p]eriodically, but at least once a year, the Secretary of the Department of Transportation shall cause the examination of all pipelines and associated facilities on Federal lands and shall cause the prompt reporting of any potential leaks or safety problems.” Plaintiffs argue that PHMSA has not met that obligation, and that its regulations do not provide methods for carrying out the required annual inspections. Plaintiffs also argue that PHMSA has violated the MLA by providing exceptions in its regulations for flow lines and certain gathering lines that are not recognized in the MLA. Specific to oil pipelines, plaintiffs contend that PHMSA violates the MLA regarding flow lines, unregulated gathering lines, and regulated gathering and transmission lines that do not affect an HCA.

In May 2019, the court denied DOT’s motion to dismiss the case, concluding that WildEarth Guardians had standing to pursue their claims under the MLA and Administrative Procedure Act. The administrative record was filed with the court in September 2019.

c. National Wildlife Federation v. Dep’t of Transportation, No. 19-1609 (6th Circuit)

In 2017, the National Wildlife Federation (NWF) filed a complaint in the U.S. District Court for the Eastern District of Michigan challenging PHMSA’s approval of Enbridge Energy, L.P. (Enbridge) facility response plans for its “Line 5” oil pipeline. NWF alleged PHMSA violated the Clean Water Act (CWA) and failed to consider the National Environmental Policy Act (NEPA) and the Endangered Species Act (ESA) in issuing the approval.

On March 29, 2019, the District Court granted partial summary judgment to NWF, concluding that PHMSA’s approvals of Enbridge’s response plans were arbitrary and capricious under the Administrative Procedure Act because the Agency failed to adequately explain its conclusions that the plans met the CWA requirements. The District Court also concluded that the CWA directs PHMSA to consider environmental concerns before approving response plans; therefore, the Agency’s approvals were arbitrary and capricious because PHMSA did not take into account ESA and NEPA concerns before approving the response plans.

PHMSA and Enbridge both appealed the District Court’s decision to the U.S. Court of Appeals for the Sixth Circuit. PHMSA filed its opening brief on August 30, 2019, arguing that the District Court erred in two respects in granting NWF partial summary judgment. First, PHMSA argued that ESA consultation is not required under the U.S. Supreme Court’s decision in National of Association of Home Builders v. Defenders of Wildlife, 551 U.S. 644 (2007), because PHMSA is required to approve an oil spill response plan if certain enumerated criteria are met. Second, PHMSA argued that a NEPA analysis is not required under the rule of reason established by the U.S. Supreme Court in DOT v. Public Citizen, 541 U.S. 752 (2004), because PHMSA has no authority to prevent any environmental impacts that might result from approving an oil spill response plan. Accordingly, PHMSA asked the Sixth Court to reverse the District Court’s decision.

C. FERC Rulemaking Proceedings

1. Advance Notice of Proposed Rulemaking Regarding Revisions to Indexing Policies and Page 700 of FERC Form No. 6 (Docket No. RM17-1)

As reported in the 2017 Reports, on October 20, 2016, the Commission issued an Advance Notice of Proposed Rulemaking (“ANOPR”) in Docket No. RM17-1 regarding Revisions to Indexing Policies and Page 700 of FERC Form No. 6. In the ANOPR, the Commission proposed to require pipelines to file supplemental FERC Form No. 6 Page 700 reports showing the cost and revenue data for their: (1) crude oil and refined products systems; (2) “non-contiguous systems that use geographically separate assets;” and (3) “major pipeline systems that extend at least 250 miles and serve fundamentally different markets,” or systems “established by a final Commission order in a litigated case.”

The Commission also proposed to require pipelines to: (1) submit cost allocation and direct assignment data related to the supplemental Page 700 reports; (2) separately state certain rate base amounts for each Page 700; and (3) separately report revenue, barrel, and barrel-mile data for cost-based rates, non-cost-based rates, and other jurisdictional revenues on each Page 700.

Regarding the Commission’s indexing policies, the Commission sought comments on a proposal to deny a pipeline’s indexing rate increase if: (1) the pipeline’s total Page 700 revenues exceeded its total Page 700 cost of service by at least 15 percent for the 2 previous years; or (2) the sum of the rate increase and the cost decrease reflected on the pipeline’s most recent Page 700 exceeds 5 percent. The Commission stated that it is also considering whether to require all oil pipelines to file their annual ceiling level adjustments, which the Commission may use to deny a pipeline’s ceiling level increase if it meets either of the proposed tests for denying an indexing rate increase. Industry participants filed initial comments on the ANOPR on January 19, 2017, and reply comments were filed on March 17, 2017. The Commission has not taken any further action on this docket.

2. Petition of the Liquids Shippers Group for Expedited Action Addressing the Impact of Federal Income Tax Changes on Indexed Rate Increases for Oil Pipelines (Docket No. OR18-16)

As noted in the Fall 2018 Report, on February 28, 2018, the Liquids Shippers Group filed a Petition for Expedited Action Addressing the Impact of Federal Income Tax Changes on Indexed Rate Increases for Oil Pipelines (“Petition”). The Petition asked the Commission to: (1) require pipelines that planned to file an indexing rate increase in 2018 to also submit a revised 2017 FERC Form No. 6 Page 700 that adjusts the income tax component downwards, to reflect the new effective tax rates associated with the Tax Cuts and Jobs Act of 2017; (2) permit shippers to use the revised 2017 Page 700 data, including the lower tax costs, to challenge an oil pipeline’s 2018 indexing rate increase; and (3) establish a general policy, whereby the Commission will investigate an oil pipeline’s indexing rate increase filing, after a protest or a complaint, when that pipeline’s Page 700 revenues exceed its Page 700 cost of service by 5 percent or more. On April 12, 2018, industry participants filed initial comments on the Petition, and reply comments were filed on April 27, 2018. The Commission has not taken any further action on this docket.

3. Petition for Rulemaking(s) to Restore Integrity of Controlling Acts and Court Decisions Pertaining to Oil Pipelines (Docket No. OR18-25)

As noted in the Fall 2018 Report, on May 11, 2018, R. Gordon Gooch filed a Petition for Rulemaking(s) to Restore Integrity of Controlling Acts and Court Decisions Pertaining to Oil Pipelines (“Petition”). The Petition asked the Commission to: (1) adopt a rulemaking proceeding to decrease oil pipelines’ rates to just and reasonable levels that do not produce revenues in excess of their cost of service; (2) deny indexing rate increases when an oil pipeline’s revenues exceed its costs, or when its cost of service decreases; (3) find that pipelines cannot charge negotiated rates or offer different services to shippers who take service between the same origin and destination points; (4) repeal and replace the Commission’s Opinion No. 154-B method of deferring the inflation component of an oil pipeline’s return and allowing the pipeline to accrue capital costs on that deferred return; and (5) replace the Commission’s discounted cash flow method of calculating an equity return for Master Limited Partnerships (“MLP”) with a method that reflects the fact that an MLP’s cash distributions are not income. The Petition also requests the Commission to use criminal penalties to enforce the Interstate Commerce Act. Industry participants filed comments on the Petition on July 10, 2018. The Commission has not taken any further action on this docket.

4. Petition for Rulemaking of Airlines for America and National Propane Gas Association for Adoption of Affiliate Standards of Conduct (Docket No. RM18-10-000)

As noted in the last report, on February 1, 2018, Airlines for America and the National Propane Gas Association (“Joint Petitioners”) filed a Petition for Rulemaking for Adoption of Affiliate Standards of Conduct (“Petition”) applicable to crude oil, petroleum product, and natural gas liquid (“NGL”) pipelines governed by the Interstate Commerce Act (“ICA”). The Petition requests the Commission to issue a Notice of Proposed Rulemaking to apply its existing affiliate Standards of Conduct for Transmission Providers under 18 C.F.R. § 358 (2017) (“Standards of Conduct”) (which currently only apply to the electric and natural gas industries) to these ICA-governed carriers. The Joint Petitioners state that application of the Standards of Conduct to these entities is required due to the recent increase in domestic oil and natural gas production and related restructuring of these pipeline companies’ businesses.

Joint Petitioners contend that this restructuring has resulted, in part, in these pipeline entities participating in the marketing of crude oil, NGLs, and petroleum products through affiliated entities. The Joint Petitioners identify multiple alleged examples where crude oil, NGL, and petroleum product pipelines have, in their opinion, engaged in the sharing of sensitive information with an affiliate thereby providing an undue preference to such affiliate, including potential rebates, or where the sharing of such sensitive information with an affiliate has worked to the competitive disadvantage of non-affiliated shippers on the subject pipeline. Application of the Standards of Conduct to these entities, the Joint Petitioners state, is designed to prevent (i) the misuse of sensitive transmission function information generated by transmission providers in ways that unduly discriminate against non-affiliated transmission customers, or (ii) the undue preference to such pipeline-affiliated marketers.

On February 12, 2018, the Commission issued a Notice Inviting Comments in response to the Petition. On March 14, 2018, various parties filed inventions and comments and/or protests, with most commenters being opposed to the Petition. Most opposing parties are members of the Association of Oil Pipelines (“AOPL”) which also intervened and filed a protest on March 14. That protest challenged the petition on the grounds that (i) adopting the affiliate standards applied to other industries is inappropriate given the more relaxed regulatory regime governing liquid pipelines, (ii) the current statutory provisions are adequate to police alleged abuses, and (iii) Petitioners had not provided adequate material evidence of abuses. AOPL also alleged the proposed rules would expand FERC’s jurisdiction beyond the terms of the ICA.

On May 11, 2018, Petitioners filed reply comments. These comments responded to the arguments raised by AOPL and other parties and provided additional alleged examples of market abuse and accompanying exhibits. Petitioners also asserted on reply that proof of abuse is not needed to justify the rules. On June 4, 2018, AOPL filed a Motion to Reject Petitioner Reply Comments or, Alternatively, For Leave to File Reply Comments and Reply Comments. These comments faulted Petitioners’ Reply as repetitive of the Petition and claimed that the current methods of enforcement are adequate, the rules would unreasonably increase the jurisdiction of the Commission, and that meaningful evidence of abuse was lacking. As of the publication of this report, the Commission has taken no further action in this matter.

D. Ratemaking Proceedings

1. Market-Based Rate Applications

a. Buckeye Pipe Line Company, L.P., Guttman Complaint (Docket No. OR14-4)

As noted in prior reports, on October 15, 2013, Guttman Energy, Inc. and PBF Holding Company, LLC (“Complainants”) filed a complaint against Buckeye Pipe Line Company, L.P. (“Buckeye”) and its subsidiary Laurel Pipe Line Company, L.P., challenging Buckeye’s market-based rates in Pennsylvania as well as the carrier’s jurisdictional treatment of certain of its shipments (i.e., Buckeye had allegedly classified certain shipments as interstate subject to interstate tariff rates versus being considered intrastate and thereby subject to lower intrastate tariff rates). The Commission issued its order on complaint on May 2, 2014, finding that Complainants had provided sufficient evidence of substantial changes in competitive circumstances to warrant a hearing regarding Buckeye’s market power in the areas of Harrisburg, Pittsburgh, (i.e., the destination markets) and Chelsea Junction (i.e., the origin market), Pennsylvania.

The order specified that the framework set out in Order No. 572 would govern the determination of market power. The Commission dismissed Complainants’ jurisdictional claims. However, in conjunction with a request for rehearing filed by Complainants, the Commission reconsidered its original rejection of Complainants’ jurisdictional claims and set for hearing, in addition to the market power issues, “whether the Complainants’ shipments should be considered interstate or intrastate transportation.” Following multiple rounds of testimony, a hearing was conducted by Presiding Judge Whang between September 29, 2015 and October, 10, 2015.

An Initial Decision was issued on April 19, 2016, finding that the Complainants did not meet their burden of proof that Buckeye can exercise market power in the Chelsea Junction origin market and Pittsburgh destination market, but that Complainants and Commission Trial Staff did meet their burden of proof that Buckeye can exercise market power in the Harrisburg destination market. For the Harrisburg destination market, the Presiding Judge “agree[d] with Complainants and Trial Staff that the [Herfindahl-Hirschman Index (“HHI”)] calculation supports a finding that the Harrisburg destination market is highly concentrated and that there are no other relevant pro-competitive factors.” Because the Presiding Judge did not believe she had been directed to determine whether Buckeye’s market-based rate authority should be revoked, she stopped short of revoking Buckeye’s authority, but rather made the recommendation that Buckeye’s market-based rate authority for the Harrisburg destination market be revoked.

With respect to the issue of whether Complainants’ subject shipments were interstate or intrastate, the Presiding Judge found that Complainants did not meet their burden of proof in challenging Buckeye’s jurisdictional treatment of its shipments; rather, the Presiding Judge found that the movement at issue was properly characterized as interstate transportation. The parties filed briefs on exceptions on May 19, 2016 and briefs opposing exceptions on June 13, 2016.

The Commission issued its Order on Initial Decision (Opinion No. 558) on November 16, 2017. First, along with a sweeping overview of its jurisdictional analysis, the Commission affirmed the Presiding Judge’s finding that the movements at issue in the case were interstate and, therefore, subject to interstate tariff rates. The Commission also ruled on numerous exceptions to the Initial Decision and affirmed the Presiding Judge on all but a few issues. Most importantly, the Commission determined that the Initial Decision utilized an erroneous HHI calculation in determining market concentration for the Pittsburgh destination market. The Commission then stated that its properly revised HHI “provides a sufficiently reliable indicator that the [Pittsburgh] market is concentrated.” As a result, the Commission reversed the Initial Decision with regard to its finding regarding market concentration for the Pittsburgh destination market and, as a result, revoked Buckeye’s market-based ratemaking authority for both the Harrisburg and Pittsburgh destination markets.

On December 18, 2017, Buckeye filed a Request for Rehearing challenging the Commission’s factual findings and revocation of its market-based ratemaking authority for the referenced markets. On January 16, 2018, the Commission granted the request solely for the purpose of affording additional time for consideration of the matters raised. On July 19, 2018, the Commission issued its Order on Rehearing (Opinion No. 558-A), denying Buckeye’s request in full. On September 17, 2018, Buckeye filed a Petition for Review of Opinion No. 588-A with the Court of Appeals for the D.C. Circuit. On November 19, Buckeye filed an unopposed Motion to Suspend the Briefing Schedule in light of a purported forthcoming settlement in Docket Nos. IS18-228-000, et al., discussed below. This motion was granted on November 21, 2018. On February 19, 2019, Buckeye reported to the Court that the parties had reached an agreement in principle.

Preceding the above referenced settlement discussions, on March 16, 2018, Buckeye submitted several tariff filings in response to the ruling in Opinion No. 558. In Docket No. IS18-229-000, Buckeye filed FERC Tariff No. 442.13.0 reflecting rate decreases for certain movements from all origins to the Harrisburg and Pittsburg, Pennsylvania destinations. Buckeye also identified that it was implementing retroactive indexing rate increases for various of the unchallenged rates. In Docket No. IS18-228-000, Buckeye filed FERC Tariff No. 443.17.0, reflecting rate decreases for transportation from Midland, Pennsylvania to Coraopolis, Neville Island, and Tioga Junction, Pennsylvania. This filing also took a similar approach to that described above, retroactively indexing unchallenged rates. In Docket No. IS18-230-000, Buckeye filed FERC Tariff Nos. 444.12.0 and 446.21.0 which similarly retroactively indexed unchallenged origin and destination pairs on the Eastern Products System and the Midwest Products System. Finally, Buckeye claimed that its indexed rates on the Midwest Products System to Pittsburgh destinations would result in revenues 36.7 percent below its costs and therefore sought cost-based-rates.

On April 2, 2018, PBF Holding Company LLC, Lucknow-Highspire Terminals, LLC, Sheetz, Inc., and C.H.R. Corp., (collectively “Joint Protestors”) filed a Motion to Intervene and Protest in response to Buckeye’s Tariff filings, requesting that the Tariffs be suspended for the minimum statutory period, subject to refund, and set for hearing. Joint Protestors argued that the Commission never ruled on the reasonableness of the rates Buckeye sought to index and that carriers are not permitted to retroactively make indexed rate increases. Joint Protestors also claim the new rates would produce an over-recovery. By removing the income tax allowance pursuant to recent policy, Joint Protestors calculated a 23 percent system-wide over-recovery and a 58 percent over-recovery on the Eastern Products System. Joint Protestors also questioned Buckeye’s treatment of certain costs, in particular, a 2016 Broadway expansion, leading to an estimated 41 percent over-recovery of costs for deliveries to Pittsburgh area destinations.

On April 9, 2018, Buckeye filed three separately docketed answers to Joint Protestors—opposing consolidation in each. Buckeye defended its effort to retroactively index its market based rates on the grounds that indexing is the primary mechanism to adjust rates, drawing analogies to those rates grandfathered by the Energy Policy Act of 1992. Buckeye also asserted comparisons of cost-of-service and market-based rates are irrelevant. Buckeye claimed removal of an income tax allowance is inappropriate because the rates were market-based not based on cost of service. Buckeye also took issue with Joint Protestors’ characterization of the Broadway expansion and challenged certain parties’ standing because they were not current shippers on the challenged routes.

On April 30, 2018, the Commission issued its Order Accepting and Suspending Tariffs Subject To Refund, Establishing Hearing and Settlement Judge Procedures, and Consolidating Proceedings. The Commission found “that the Protest raises material issues regarding the proposed rates sufficient to warrant further investigation at hearing.” While stating that Buckeye may use any lawful method to justify its rates, the Commission clarified that “Buckeye’s proposal to retroactively index its October 2011 market-based rates is not consistent with Commission policy.” The Commission also stated that all the Joint Protestors have standing as all ship on Buckeye’ system to some of the markets at issue and that this proceeding was the first of its kind. The Commission also consolidated the three filings. The tariffs were accepted, subject to refund and further order of the Commission, to be effective May 1, 2018. The Commission directed that an evidentiary hearing be established following an effort to determine if a settlement could be reached.

On May 30, 2018, Buckeye filed a Request for Clarification, or in the Alternative Rehearing. Buckeye argued that the April 30 Order is inconsistent with existing Commission policy because FERC nominally allows any method to justify its rates but in reality, apparently only cost-based-rates could satisfy the purported policy. Buckeye also asserts that the April 30 Order was inconsistent with Opinion No. 558 because Buckeye must now defend its rates on the basis of cost even though Opinion No. 558 did not find them unjust or unreasonable. In the alternative, Buckeye requests rehearing on the theory that the approach outlined in the April 30 Order narrows the “zone” of reasonableness to a cost based “point.”

On June 14, 2018, Joint Protestors submitted their Answer to Buckeye’s Rehearing Request, arguing that the April 30 Order was clear, internally consistent, and consistent with Opinion No. 558 and other Commission precedent. On June 27, 2018, the Commission granted Buckeye’s rehearing request for the limited purpose of further consideration.

On June 29, 2018, Buckeye submitted a petition for review to the Court of Appeals for the D.C. Circuit. On August 17, 2018, FERC submitted its unopposed motion to dismiss the petition without prejudice as premature. On September 26, 2018, the D.C. Circuit granted the motion and dismissed the petition in an unpublished Per Curiam opinion.

Settlement negotiations continued and on October 2, 2018, the Chief Administrative Law Judge designated herself as the Settlement Judge. On December 14, 2018, Buckeye filed a motion to stay consideration of its Request for Clarification or Rehearing. An Offer of Settlement was filed on December 17, 2018 by Buckeye and the Joint Protestors. The settlement was designed to resolve all issues in Docket Nos. IS18-228-000, et al. and require Buckeye to withdraw its Rehearing Request at the Commission and Petition to the D.C. Circuit. The settlement rates include lower rates for shipments from the Chelsea Origin and an incentive rate from Linden, New Jersey to Eldorado, Pennsylvania. Further, Buckeye will tender settlement payments to the Protestors.

Commission Trial Staff filed late comments on the Offer of Settlement on January 7, 2019. Trial Staff did not oppose the certification of the settlement, but stated it would not support the proposed rates at a trial. Staff expressed concern that many of the rates were unchanged from the retroactively indexed rates previously rejected by the Commission. Trial Staff also noted that many of the settlement rates on the Midwest Products System are identical to the proposed cost-based rates and have not been corrected to remove the income tax allowance. Buckeye filed reply comments on January 16, 2019. Buckeye noted that no party opposed the settlement. Buckeye emphasized that the lawfulness of the rates rejected by the Commission was not yet resolved and Buckeye was foregoing its rights of appeal in the settlement. Buckeye also argued that its rates do not need to be “corrected” to remove an income tax allowance because the Commission policy regarding income taxes is not self-executing in rates and does not apply to “black box” settlements where the parties disclaim any cost-of-service principles.

On February 19, 2019, the Settlement Judge certified the settlement to the Commission, including Trial Staff’s comments noting concern with aspects of the agreement and particular rates to be litigated. The Commission accepted the settlement and terminated the dockets by Letter Order on April 18, 2019. On April 29, 2019, the D.C. Circuit granted Buckeye’s unopposed motion to dismiss its petition for review of Opinion No. 588-A.

b. MPLX Ozark Pipe Line LLC (Docket No. OR19-14)

On December 21, 2018, MPLX Ozark Pipe Line LLC (“MPLX Ozark”) filed an application for authorization to charge market-based rates for the transportation of crude oil on its pipeline system from Cushing, Oklahoma, to Wood River, Illinois. In its application, MPLX Ozark stated that the relevant product market for the origin market is the supply of all types of crude oil, and the relevant product market for the destination market is the absorption, either through transportation receipts or local consumption, of all types of crude oil. MPLX Ozark asserted that the proper origin market consists of the entire State of Oklahoma, and that the proper destination market consists of the counties located in BEA No. 160 (the St. Louis Destination Market).

MPLX Ozark asserted that it lacks market power in either the origin or destination markets and that both markets are workably competitive. It provided market power analyses that it says demonstrate that MPLX Ozark cannot exercise market power in the origin market or the destination market, as the markets are characterized by low HHIs, significant competition, and excess capacity. Further, MPLX Ozark asserted that its market shares in the origin market and the destination market are below the levels the Commission has stated would warrant concern, even when paired with higher HHIs.

Husky Marketing & Supply Company (“Husky”) and Phillips 66 filed a motion to intervene and a protest in response to the MPLX Ozark application. Husky and Phillips 66 challenged the merits of the application by alleging that it does not demonstrate a lack of market power, and that in particular it uses an overly broad destination geographic market and an overly broad product market.

On June 25, 2019, the Commission issued an order establishing a hearing to determine whether MPLX Ozark has the ability to exercise market power in the challenged destination market. The Chief Judge appointed a Settlement Judge, and the parties engaged in a settlement conference on July 9, 2019. On August 19, 2019, the Chief Judge terminated settlement procedures on the recommendation of the Settlement Judge. Commission Staff, MPLX Ozark, Husky, and Phillips 66 have all requested the issuance of numerous subpoenas for documents and responses. In accordance with the Track III schedule adopted in an order from the Presiding Administrative Law Judge on July 16, 2019, MPLX Ozark submitted direct testimony on September 13, 2019. The deadline for Husky and Phillips 66 to file answering testimony is November 8, 2019. An initial decision in the proceeding is not expected until September 9, 2020.

c. West Texas LPG Pipeline Limited Partnership (Docket No. OR17-19)

On August 4, 2017, West Texas LPG Pipeline Limited Partnership (“WTXP”) filed an application for authority to charge market-based rates for the transportation of natural gas liquids (“NGLs”) over its pipeline that extends from the Permian Basin and the Barnett Shale production basins to Mont Belvieu, Texas. In the application, WTXP stated that the relevant product market is defined as the supply or absorption of all NGLs that it transports or could transport, including ethane, propane, normal butane, isobutene, natural gasoline, and Demethanized Mix. WTXP asserted that the proper origin markets are the Permian Basin and the Barnett Shale production basins, and the proper destination market is the counties and parishes within a 100-mile radius of Mont Belvieu, Texas.

WTXP asserted that it lacks significant market power in both the origin and destination markets. In the Permian Basin origin market, WTXP stated that it faces competition from nine firms operating pipelines and fractionation facilities. In the Barnett Shale origin market, WTXP asserted that there are eight firms operating pipelines and fractionation facilities. In the Mont Belvieu destination market, WTXP stated that there are 17 firms operating pipelines and gas processing plants that compete to supply NGLs. WTXP further claimed that market power statistics demonstrate that it lacks market power in the origin and destination markets. To reinforce its claim that it will not exercise market power in the origin and destination markets, WTXP noted the existence of potential competition in the form of trucking from external supply sources, expansion of trucking, rail, and waterborne transportation options, ethane injection, and the expansion, conversion, and construction of pipelines. WTXP also cited the existence of committed rate agreements and the ability to engage in exchanges as factors demonstrating that it lacks significant market power in the origin and destination markets.

Several parties filed responses to the WTXP application. XTO Energy Inc., Anadarko Energy Services Company, Occidental Energy Marketing, Inc., Devon Gas Services, L.P., Chevron Products Company, EOG Resources, Inc., Pioneer Natural Resources USA, Inc., and ConocoPhillips Company all filed motions to intervene. Targa Liquids Marketing and Trade, Indicated Shippers, and EnLink NGL Marketing, LP each filed protests challenging the merits of the application and alleging that WTXP has failed properly to demonstrate that it lacks market power.

The Commission issued an order establishing hearing procedures on March 19, 2018. WTXP filed an Offer of Settlement on November 29, 2018, and the presiding Administrative Law Judge (“ALJ”) issued an order certifying the Offer of Settlement on January 7, 2019. The ALJ summarized the terms of the settlement, noted that the settlement was uncontested, concluded that the settlement “is fair, reasonable, and in the public interest,” and recommended approval by the Commission. The Commission issued an order approving the settlement and granting the application on March 27, 2019.

d. White Cliff Pipeline, L.L.C. (Docket No. OR18-9)

On December 21, 2017, White Cliff Pipeline, L.L.C. (“White Cliffs”) filed an Application for Authorization to Charge Market-Based Rates. White Cliffs sought authorization to charge market-based rates for the transportation of all crude oil from White Cliffs’ origin market consisting of the counties that encompass the geography of the Niobrara Shale Region as defined by the Energy Information Administration, and the transportation of crude oil to White Cliffs’ destination market, consisting of the counties located in BEA No. 170 (Tulsa-Bartlesville, Oklahoma). White Cliffs stated that its application demonstrates that it lacks market power in the origin market and the destination market, both of which are workably competitive. On February 20, 2018, the Liquids Shippers Group protested White Cliffs’ application and requested that the Commission either summarily deny White Cliffs’ application for market-based rate authority or set the application for a full evidentiary hearing before an administrative law judge. On March 22, 2018, White Cliffs filed and answer to the protest by the Liquids Shippers Group, and on April 6, 2018, the Liquids Shippers Group filed an answer to White Cliffs’ answer.

On May 17, 2018, the Commission granted White Cliffs’ application for market based rate authority in the destination market, but set for hearing the issue of whether White Cliffs lacks market power in the origin market. On May 22, 2018, the Chief Judge designated a presiding judge for the hearing and set the proceeding for a Track III procedural schedule. However, on December 13, 2018, the Chief Judge extended the Track III procedural schedule, such that the Initial Decision was due by August 13, 2019. On January 3, 2019, the Presiding Judge adopted a revised procedural schedule, maintaining the same date for the initial decision, but modifying intervening procedural dates.

On July 30, 2018, White Cliffs filed supplemental direct testimony, and on September 27, 2018, the Liquids Shippers Group filed answering testimony. On November 20, 2018, Commission Trial Staff filed direct and answering testimony. On December 18, 2018, the Liquids Shippers Group filed cross-answering testimony. On January 22, 2019, Commission Trial Staff and White Cliffs submitted their respective rebuttal testimony. On February 19, 2019, the participants to the proceeding submitted joint statements of stipulated and contested facts, joint witness list, and a joint statement of issues. Prehearing briefs were filed on February 26, 2019. The hearing began on March 19, 2019 and concluded on March 28, 2019.

On April 26, 2019, White Cliffs, Liquid Shippers Group, and Trial Staff each filed initial posthearing briefs. Each also filed posthearing reply briefs on June 4, 2019. On August 12, the Chief Administrative Law Judge extended the deadline for issuance of the initial decision from August 13, 2019 to September 13, 2019.

On September 12, 2019, the Presiding Judge granted White Cliff’s Application, concluding that White Cliffs lacks market power in the origin market as well as the destination market. First, the Initial Decision defined the relevant product market for which White Cliffs sought market-based rate authority as the transportation of light crude oil. Second, the Initial Decision adopted Trial Staff’s definition of DJ Basin Origin Market as the appropriate geographic origin market, contending that it includes both the producing field for the majority of White Cliffs’ shipping as well as competitive alternatives that could provide market discipline to White Cliffs. Third, the Presiding Judge relied on White Cliffs’ and Trial Staff’s proposals to compile a list of competitive alternatives to White Cliffs in the geographic origin market, finding thirteen such alternatives. Finally, the Presiding Judge used the HHI and White Cliffs’ market share to assess the market power of White Cliffs, determining that the pipeline does not have the ability to exercise market power in the geographic origin market.

2. Rate Issues

a. Notice of Inquiry to Address Income Tax Allowance Policy Following Decision in United Airlines v. FERC (Docket No. PL17-1-000 & related SFPP Docket No. IS08-390)

The chronicles of the evolving nature of FERC’s income tax allowance policy and the intertwined SFPP, L.P. (“SFPP”) rate cases continues. As addressed in previous reports, SFPP’s Docket No. IS08-390 proceeding involved the development of cost of service rates on the carrier’s West Line between Los Angeles, California and Phoenix, Arizona. This proceeding has been the subject of an ALJ Initial Decision and Commission orders addressing the reasonableness of the Initial Decision as well as rehearing requests and related SFPP compliance filings as reflected in the Commission’s Opinion Nos. 511, 511-A, and 511-B. On April 22, 2015, the D.C. Circuit Court of Appeals consolidated all of the various petitions for review filed in connection with the Commission’s Opinion Nos. 511, 511-A, and 511-B under the lead Case No. 11-1479.

On appeal, Shipper Petitioners contended that the Commission erred in permitting SFPP, a pipeline organized as a partnership, to include in its cost of service an allowance for income taxes borne by its partners/investors, given that the cost of service already includes a return on equity (“ROE”) component that allows for the recovery of the partner/investors’ income tax liability and to permit both in the cost of service causes a double recovery of investor tax liability and thus unjust and unreasonable rates. Petitioner SFPP argued that the Commission failed to engage in reasoned decision-making in adopting an equity ROE and inflation factor without determining that they meet the Commission’s own requirement that the equity rate of return and inflation factor represent a reasonable forecast of the pipeline’s future cost of service. SFPP also challenged the Commission’s decision to prohibit the carrier from applying the full amount of the 2009 index adjustment in calculating rates, and associated refunds, for the period July 1, 2009 through June 30, 2010 on the grounds that such a decision fails to properly comport with Commission precedent and regulations.

In response to Petitioners’ arguments, the Commission argued that it (i) reasonably approved, consistent with its own policy and court precedent, SFPP’s proposal to include an income tax allowance in its cost of service, (ii) reasonably affirmed the Presiding Judge’s use of test period financial data to calculate SFPP’s ROE instead of the more recent financial data presented by the carrier which encompassed a unique economic period in American history that had not existed for quite some time and was unlikely to exist for the foreseeable future, and (iii) reasonably disallowed SFPP’s request to use a full index adjustment for the industry-wide cost increases in 2008 given that SFPP had already adjusted its rates for its own 2008 costs for the first three quarters of 2008 (i.e., SFPP was permitted to take one-quarter of the 2009 index amount).

The D.C. Circuit issued its opinion on July 1, 2016 granting in part and denying in part SFPP’s petition and granting the Shippers’ petition for review. As it respects the Shipper Petitioners’ income tax allowance issue, the Court acknowledged that it had previously approved FERC’s granting of an income tax allowance to partnership pipelines, but determined that “FERC has not provided sufficient justification for its conclusion that there is no double recovery of taxes for partnership pipelines receiving a tax allowance in addition to the discounted cash flow return on equity.” The Court stated that “[t]hese facts support the conclusion that granting a tax allowance to partnership pipelines results in inequitable returns for partners in those pipelines as compared to shareholders in corporate pipelines.” The Court remanded the case for FERC to consider “mechanisms for which the Commission can demonstrate that there is no double recovery.”

The Court upheld FERC’s refusal to adopt SFPP’s proposal to rely on post-test-period ROE calculation updates because these figures were drawn from time periods during which abnormal financial conditions prevailed. However, the Court agreed with SFPP that FERC “provided no reasoned explanation” for setting the ROE on the basis of end-of-test-year data because the “evidence does not show that the real return on equity for that time period was representative of SFPP's costs.” The Court remanded to FERC and explained that “while we are particularly deferential to the Commission's expertise with respect to ratemaking issues, FERC cannot rely in conclusory fashion on its knowledge and expertise without adequate support in the record.”

Finally, the Court denied SFPP’s petition claiming that FERC engaged in arbitrary or capricious decision-making when it declined to apply the full amount of the 2009 rate index adjustment in calculating SFPP’s rates and refunds for the period from July 1, 2009 through June 30, 2010.

In comments to the Commission following the Court’s remand and mandate issuance, Shippers contended that FERC could eliminate the double recovery simply by denying an income tax allowance for partnership pipelines owned by Master Limited Partnerships (“MLPs”) such as SFPP and leaving undisturbed the Commission’s long-established market-based DCF ROE methodology. SFPP has contended in comments following the remand that it believes the Court was mistaken in finding that a double recovery arises when the Commission grants partnership pipelines owned by MLPs an income tax allowance and a DCF-based ROE. Additionally, SFPP urged FERC to re-open the record on the issue, permit the parties to supplement the record, and consider various arguments that it believes refute the Court’s double recovery conclusion. Shippers opposed SFPP’s proposition, asserting that the existing record was sufficient for the Commission to resolve the matter and challenging the factual and procedural validity of SFPP’s income tax allowance recommendations.

On December 15, 2016, the Commission issued, in response to the remand in the United Airlines case, a Notice of Inquiry Regarding the Commission’s Policy for Recovery of Income Tax Costs (“NOI”). The NOI sought comments regarding (i) “any proposed methods to adjust the income tax allowance policy or current ROE policies to resolve any double recovery of investor-level tax costs for partnerships or similar pass-through entities” and “how any adjustment to the Commission’s tax allowance and/or ROE policies should be specifically implemented.” In this connection, the NOI called for commenters to explain “how any adjustment to the Commission’s tax allowance and/or ROE policies should be specifically implemented” and “how the proposed approach would (a) resolve any double recovery of investor-level income tax costs for partnership entities, and (b) allow regulated entities to earn a sufficient return consistent with the capital attraction standard in Hope. Finally, the NOI called for commenters to address “how these proposals apply to publically [sic] traded pass-through entities, such as MLPs and real estate investment trusts (REITS), as well [as] other pass through entities, including closely held partnerships and joint ventures” with attention to the “practical application” of the proposals made. Initial comments regarding the NOI were filed on March 8, 2017 and reply comments were filed April 7, 2017.

In addition to the initial and reply comments filed by SFPP and the pipeline community and the shipper community, including the interested SFPP shippers, a number of other shipper and pipeline interests have weighed in on the NOI issue. In general, the shipper community provided comments asserting that, based on the discussion and findings in the United Airlines decision, as well as the underlying record, the Commission should eliminate income tax allowances for MLP-owned pass-through pipelines in deriving cost of service rates. On the other side, the groups and entities representing the pipeline industry interests filed comments in support of the concept that the Commission need not change its income tax allowance policy in the wake of the United Airlines decision and that MLP-owned pipelines should be allowed to continue to include an income tax allowance in computing cost-of-service rates.

On March 15, 2018, the Commission issued its Revised Income Tax Allowance Policy Statement that the Commission will generally not permit MLP pipelines like SFPP to recover an income tax allowance in their cost of service. The Commission found granting an MLP pipeline both an income tax allowance and a DCF ROE created an impermissible double recovery of investors’ tax costs. In addition, also on March 15, 2018, the Commission issued its Opinion No. 511-C which applied the Revised Income Tax Allowance Policy to SFPP and the record in Docket No. IS08-390 and the carrier’s West Line rates.

Numerous parties requested rehearing and/or clarification of the Commission’s Revised Income Tax Allowance Policy Statement. For instance, the Association of Oil Pipe Lines challenged the ruling as inconsistent with Hope and invalid because the Commission did not adequately explain its departure from past policy or gather new empirical evidence. Many of the other commenters were members of AOPL and that organization’s arguments can be considered fairly representative of the industry. On April 27, 2018, the Commission granted the rehearing requests for the limited purpose of further consideration.

Notably, on July 18, 2018, the Commission issued an Order on Rehearing concerning the Revised Income Tax Policy Statement. The Commission dismissed the rehearing requests, and while it declined to reconsider the Revised Policy Statement, it allowed for an MLP pipeline to make legal and factual arguments in the future as to why they should be entitled to an income tax allowance. Further, citing inquiries made in the ADIT NOI (further discussed below), the Commission provided guidance that “an MLP pipeline (or other pass-through entity) no longer recovering an income tax allowance pursuant to the Commission's post-United Airlines policy may also eliminate previously-accumulated sums in ADIT for cost of service purposes instead of flowing these previously-accumulated ADIT balances to ratepayers.” The Commission justified this policy as consistent with Internal Revenue Service regulations, precedent that shippers do not have an ownership interest in ADIT, and a D.C. Circuit case suggesting (in the Commission’s opinion) that a different result would be retroactive ratemaking. The Commission cautioned that this pronouncement was only guidance and not binding. Commissioners LaFleur and Glick authored a concurrence expressing frustration with the guidance on grounds of shipper equity but expressing concerns with the issue of retroactive ratemaking to the extent a different outcome was reached and emphasizing that the Rehearing Order was non-binding.

On September 14, 2018, Enable Gas Transmission, LLC filed a Petition for Review with the Court of Appeals for the D.C. Circuit challenging the Revised Income Tax Allowance Policy Statement and the Rehearing Order. On September 24, 2018, SFPP, L.P. did the same. The Court consolidated the two cases on September 19, 2018, and accepted various motions to intervene on November 2, 2018.

On October 17, 2018, SFPP submitted a motion to hold the proceeding in abeyance until the Commission “has a chance to complete its pending proceedings regarding the application of the Revised Policy Statement to SFPP in FERC Docket No. IS08-390.” On October 26, 2018, Joint Intervenors Filed an Answer to the Motion arguing the Court should defer ruling on abeyance until it rules on a pending motion to dismiss. Enable filed an Answer to the Motion to Hold in Abeyance on October 29, 2018, arguing that the motion should be denied or limited to SFPP’s case because FERC had applied the policy statement to Enable as if it was a binding rule in a case under the Natural Gas Act. On November 2, 2018, Enable filed a Reply to Joint Intervenors’ Answer emphasizing that its situation was distinct from SFPP’s. On November 2, 2018 SFPP filed a Reply to Joint Intervenors’ Answer to its Motion to Hold in Abeyance, arguing that abeyance was appropriate here because SFPP would be prejudiced if a court could not review the records of both docket PL17-1 and docket IS08-390 in the same proceeding. On November 5, 2018, SFPP Filed a Reply to Enable’s October 29 Response, arguing that Enable’s concerns of delay are outweighed by concerns of judicial economy and a complete record.

On October 24, 2018, FERC submitted a Motion to Dismiss, arguing the orders were statements of policy not ripe for review. On November 5, 2018, Joint Intervenors filed an Answer in Support of FERC’s Motion. And Enable filed an Answer arguing that the Motion should be denied or limited to SFPP’s petition because the Policy Statement had been applied to Enable as a substantive rule. On November 5, 2018, SFPP filed a Response in Opposition to the Motion to Dismiss. SFPP argued that fairness requires that the Court be able to review the factual record of PL17-1 when SFPP challenges a final order in IS08-390 because FERC declined to reopen the record in that proceeding and therefore the PL17-1 record is the only avenue to review FERC’s reasoning in applying the United Airlines holding to SFPP in IS08-390. On November 12, 2018, Enable filed a reply to Joint Intervenors’ November 5, 2018 Answer, again emphasizing its different posture from SFPP. On November 12, 2018, SFPP filed a Reply to Joint Intervenors’ November 5, 2018 Answer, saying review of docket PL17-1 is necessary to avoid prejudice because the factual record in Docket IS08-390 was developed under a different legal theory. On November 13, 2018, FERC filed a reply in favor of dismissal.

On November 16, 2018, the Association of Oil Pipe Lines filed a Notice of Intervention with a non-binding statement of issues to be raised.

On January 31, 2019, the Court issued a Per Curiam Order dismissing the motion to hold in abeyance and referring the Motion to Dismiss to the merits panel. On March 4, 2019, Petitioners SFPP and Enable and Respondent FERC filed a proposed briefing schedule in this matter seeking to delay the beginning of briefing until mid-July 2019 to accommodate potential pleadings and petitions for review of FERC’s Opinion No. 511-D in SFPP’s West Line rate proceeding. Shipper intervenors in the matter filed comments opposing any delay in the briefing schedule. Specifically, the shipper intervenors noted that the Court previously denied SFPP’s request to hold this proceeding in abeyance where SFPP had claimed it was necessary pending a FERC order on it request for rehearing of Opinion No. 511-C. Shipper intervenors explained that FERC had now acted by issuing Opinion No. 511-D and thus there should be no delay in the scheduling and filing of briefs. On April 18, 2019, the Court issued a Per Curiam Order setting the briefing schedule.

On July 12, 2019 Petitioners Enable and SFPP filed their Joint Brief. The Petitioners argued that FERC misinterpreted the United Airlines decision as dictating one particular result and therefore the agency failed to conduct an adequate, independent evaluation of the record. Relatedly, Petitioners argued that FERC failed to consider the impact of the decision on regulated pipelines. Petitioners also argued that the Revised Policy Statement treated owners of partnership and corporate pipelines disparately. On July 29, 2019, Intervenor AOPL filed its Brief in Support of Petitioners. AOPL argued that FERC failed to conduct an independent evaluation and assumed that the United Airlines decision commanded a particular result. AOPL also argued that FERC ignored evidence that MLP pipeline returns are not higher than those owned by corporations and evidence regarding the financial impact the policy statement would have on MLP pipelines.

On September 10, 2019, Respondent FERC filed its Brief. FERC asserted that the Court lacked jurisdiction because the Revised Policy Statement was a non-reviewable statement of policy without legal effect. Respondent also stated that Petitioners lacked standing because, as the Revised Policy Statement and Order on Rehearing had no legal effect, they did not cause the Petitioners any injury-in-fact. The Commission also argued that the substantive issues raised should be adjudicated elsewhere, such as the appeal of Opinion No. 511-D. On the merits, FERC defended its decision to disallow an income tax allowance for pass-through entities, arguing it was a reasonable solution to the issue of double-recovery. The Joint Brief of the shipper intervenors is due September 25, 2019.

March 9, 2019 SFPP filed a petition for review of Opinion No. 511-D. This Petition was followed by petitions for review from several of SFPP’s shippers (“Shipper Petitioners”) that were consolidated by the Court. On April 11, 2019, AOPL filed a Motion for Leave to Intervene. On April 19, 2019, the Shipper Petitioners filed a Response opposing AOPL’s intervention on the ground that it lacked standing. In their Response, Shipper Petitioners argued that AOPL’s participation was not required and that the harms AOPL asserted were either harms to SFPP, which was already a participant, or were merely precedential harms that cannot support standing. On April 26, 2019, AOPL filed its Reply arguing that it had standing to intervene on behalf of its members, who were harmed by the application of FERC’s new rule. On June 4, 2019, the Court issued an unpublished Per Curiam order granting AOPL’s Motion to Intervene.

On July 3, 2019, SFPP filed a Motion for Concurrent Oral Argument in Case No. 19-1067, et al. (consolidated) and Case Nos. 18-1254 and 18-1252 (consolidated) (the Revised Policy Statement Appeal). SFPP noted that the two cases involve a similar background and will involve similar issues. Thus, SFPP argued, holding oral argument on the same day before the same panel will advance judicial economy. On July 11, 2019, the Shipper Petitioners filed their Response to SFPP’s Motion. The Shipper Petitioners stated that they were not opposed to holding oral argument on the same day before the same panel. Shipper Petitioners stressed, though, that the two cases involved different legal arguments that deserve the Court’s full consideration. For instance, finality and standing are at issue in the review of the Revised Policy Statement, and issues of retroactive ratemaking are implicated in the review of Opinion No. 511-D. The Shipper Petitioners also noted that the administrative records in each case are different and requested that concurrent argument not impact the time and consideration given to the distinct issues in each case.

On August 8, 2019, the Court granted SFPP’s Motion. The Court, in the same Per Curiam order, set the briefing schedule for Case No. 19-1067, et al. (consolidated). Petitioner Briefs are due October 11, 2019. Petitioner-Intervenor Briefs are due October 28, 2019. The Respondent’s Brief is due December 20, 2019. Briefs of Respondent Intervenors are due January 6, 2020, and Reply Briefs are due February 5, 2020. The date for the concurrent oral argument has not yet been set.

b. Inquiry Regarding the Effect of the Tax Cuts & Jobs Act on Commission-Jurisdictional Rates (Docket No. RM18-12)

On March 15, 2018, the Commission issued a Notice of Inquiry soliciting industry-wide comment on the effect of the Tax Cuts and Jobs Act on Commission-jurisdictional rates. Of particular note, the Commission sought comment on whether, and if so how, the Commission should address changes related to Accumulated Deferred Income Tax (“ADIT”) and bonus depreciation in Commission-jurisdictional rates. The Commission also sought comment “regarding the treatment of ADIT to the extent the income tax allowance is eliminated” for MLPs and other pass-through entities following the United Airlines holding and the Revised Income Tax Allowance Policy Statement.

Between May 18 and May 22, 2018, various entities responded to the Commission’s inquiry representing carrier, shipper, utility, and consumer interests. On May 21, 2018, the United Airlines Shipper Petitioners and Aligned Shippers filed their Initial Comments which were generally representative of the overall liquid pipeline ratepayer positions. Specifically, these comments generally asserted that ADIT amounts represent dollars for an anticipated future expense that no longer will occur as a result of the United Airlines decision and the Revised Income Tax Policy Statement and that Commission precedent and equity require that the now overfunded ADIT balances be amortized back to shippers expeditiously in rates.

On May 21, 2018, the Association of Oil Pipe Lines (“AOPL”), among others, submitted its comments in response to the Commission’s inquiry. These comments generally reflect the overall position of the liquid pipeline carriers and contend that no Commission action is needed regarding oil pipelines because existing policies already adequately respond to changes in cost of service such as the reduction in tax rates. Further, regarding pipelines owned by MLPs or other pass-through entities, AOPL argued that there was no reason for those pipelines owned by MLPs to include ADIT in their cost of service or to adjust ADIT in response to tax rates because those pipelines are no longer understood to pay taxes nor entitled to an income tax allowance. Of note, also on May 21, 2018, TransCanada Corporation submitted its comments which raised, in addition to those of AOPL, the claimed legal theory that amortizing back to ratepayers excess ADIT balances would constitute impermissible retroactive ratemaking.

Between June 5 and June 20 multiple parties filed motions for leave to answer and answers to the initial comments received by the Commission. These comments generally represented carrier interests and argued that ADIT funds collected should and could not be returned to shippers. To date, although the Commission has addressed ADIT in other dockets as addressed in certain of the other case summaries herein, the Commission has not issued a formal order in this rulemaking/notice of inquiry proceeding.

For example, on November 15, 2018, in Docket No. PL19-2, the Commission issued a Policy Statement regarding (i) the treatment of ADIT for accounting and ratemaking purposes in light of the reduced tax rate and (ii) the accounting and ratemaking treatment of ADIT following the sale or retirement of an asset. For oil pipeline rates, the Commission articulated that “the current regulatory treatment of excess and/or deficient ADIT amounts is to . . . amortize them by removing the annual amortization amount from the cost of service in the process of determining an income tax allowance.” The Commission clarified it will “continue the practice of amortizing and removing the excess and or deficiency by reducing the allowed return before it is grossed up for income taxes.” Regarding the sale or retirement of an asset, the Commission expressed that, although sale or retirement is usually found to extinguish an ADIT balance, the “excess or deficient ADIT associated with post-December 31, 2017, asset dispositions and retirements should be treated differently for ratemaking purposes.” The Commission reasoned that excess ADIT balances beyond what is owed in the event of a sale is “more reflective of a regulatory liability or asset, and no longer reflects deferred taxes that are still to be settled with the IRS and [therefore] need not be extinguished.” In regards to oil pipelines, the Commission directed carriers to “continue maintaining excess and/or deficient ADIT within the appropriate ADIT accounts for ratemaking purposes.” And cautioned that “[w]hen jurisdictional assets are retired or sold the oil pipeline should continue to amortize any excess and/or deficient amounts associated with those assets as part of the process of determining an income tax allowance within the rate making process, or seek prior Commission approval to do otherwise.”

As noted elsewhere in this report, the Commission has also issued decisions in the Docket Nos. PL17-1 and IS08-390 proceedings regarding how MLPs and other pass-through entities should handle their existing ADIT balances. In particular, as referenced in other parts of this report, the Commission issued an Order on Rehearing associated with the Revised Income Tax Allowance Policy Statement in which it announced that “an MLP pipeline (or other pass-through entity) no longer recovering an income tax allowance pursuant to the Commission’s post-United Airlines policy may also eliminate previously-accumulated sums in ADIT from cost of service instead of flowing these previously-accumulated ADIT balances to ratepayers.” According to the Commission, to require excess ADIT to be amortized or otherwise flowed back to shippers would constitute unlawful retroactive ratemaking in this context.

c. SFPP 2008 West Line (Docket No. IS08-390)

As discussed in previous reports and above, the D.C. Circuit’s United Airlines decision remanded FERC’s Opinion Nos. 511, 511-A and 511-B addressing SFPP, L.P.’s (“SFPP”) 2008 West Line cost-of-service rate case, Docket No. IS08-390. On March 15, 2018, the Commission issued its Order on Remand and Compliance Filing, Opinion No. 511-C. This ruling, consistent with the Revised Income Tax Allowance Policy Statement, concluded that granting SFPP an income tax allowance resulted in an impermissible double recovery of the carriers income liabilities and that removing the allowance restores parity between corporate and MLP pipelines. Regarding the calculation of real ROE, the Commission allowed a real ROE of 10.24 percent with a 12.63 percent nominal ROE and a 2.39 percent inflationary component. The Commission declined to reopen the record on the issues. The Commission directed SFPP to make a compliance filing within 60 days, with Comments due within 75 days and replies within 90 days.

On April 16, 2018 SFPP filed a Request for Rehearing and Motion to Hold in Abeyance. This filing challenged Opinion No. 511-C as arbitrary and capricious because it relied on the Revised Income Tax Allowance Policy Statement without reaching its own conclusions. SFPP also requested that Opinion No. 511-C be held in abeyance pending its rehearing request and the rehearing requests in Docket No. PL17-1 dealing with the Revised Income Tax Allowance Policy Statement so that it need not make a compliance filing within 60 days of Opinion No. 511-C’s issuance.

On May 1, 2018, Joint Shippers filed their Answer to the April 16 Motion to Hold in Abeyance. Joint Shippers asserted that abeyance was not justified, that delaying the effectiveness of Opinion No. 511-C would more properly be characterized as a stay of an order, and that the higher burden for issuance of a stay had not been met. On May 9, 2018, SFPP filed its Motion for Leave to Answer and Answer which asserted abeyance was justified, citing continued argument of the income tax allowance issue in other dockets.

On May 14, 2018, SFPP submitted its Compliance Filing Implementing Opinion No. 511-C. Also on May 14, 2018, the Commission granted SFPP’s prior rehearing request for the limited purpose of further consideration.

On June 8, 2018, Joint Shippers filed their Comments and Protests on the Compliance Filing. Also on June 8, 2018, Tesoro Refining and Marketing (“Tesoro”) filed a Motion to Intervene, Protest and Comments. Joint Shippers and Tesoro took issue with SFPP’s proposal and methodology to recover Overpaid Refund/Under-Collected Revenues (“ORR”) associated with its restored 2011 index-based rate increase in Docket No. IS11-444 and litigation expenses in future rates. Much of the discussion in the protests involved SFPP’s removal of Accumulated Deferred Income Taxes (“ADIT”) from consideration with respect to the development of rates and/or refunds, with shippers arguing that, due to the removal of any income tax allowance from rates, the ADIT amount previously accumulated from prior rates should be considered entirely overfunded and thus should properly be returned to ratepayers in rates to prevent a windfall to the carrier.

On July 11, 2018, SFPP filed Reply Comments to the June 8, 2018 Comments and/or Protests. SFPP responded to shippers’ allegations regarding its proposals associated with ORR and litigation expenses and also defended its treatment of ADIT. In particular, SFPP argued that removal of ADIT for ratemaking purposes and rejecting the concept of returning any overfunded ADIT amounts to ratepayers is consistent with Commission policy and requiring SFPP to do otherwise would violate the rule against retroactive ratemaking. SFPP also alleged that returning ADIT to shippers was allegedly foreclosed by a Commission-approved settlement.

On August 17, 2018, Joint Shippers submitted their Motion to File Surreply Comments and Surreply Comments in response to the carrier’s July 11, 2018 Reply Comments. These comments denied that refunding ADIT is against Commission policy or otherwise retroactive ratemaking. Specifically, in these comments, the shippers took issue with SFPP’s assertions arguing that (i) the carrier’s justification for retaining its existing excess ADIT balance is contrary to both fact and law, (ii) the rule against retroactive ratemaking is inapplicable to SFPP’s situation, and (iii) no prior settlement precludes prospective rate adjustments to remedy SFPP’s overfunded ADIT balance. In addition, the shippers took the opportunity to address and rebut the tentative ADIT observations made by the Commission in its Order on Rehearing (discussed above) asserting that the Commission’s proposed tentative ADIT treatment allowing carriers to retain such over-funded amounts directly conflicts with established precedent and tax normalization principles.

On February 21, 2019, the Commission issued its Order on Rehearing and Compliance filing. In that order the Commission denied SFPP’s requests for rehearing and to reopen the record on income tax allowance issues. The Order accepted SFPP’s compliance filing but rejected SFPP’s proposal to create an ORR reserve.

The Commission denied rehearing of “the findings in Opinion No. 511-C that a double recovery results from granting SFPP an income tax allowance and a DCF ROE,” as it found the Commission had adequately addressed SFPP’s comments. The Commission rejected SFPP’s Motion to Reopen the Record on the grounds that SFPP has already fully litigated the issue of whether including an ITA in its cost of service results in a double recovery and none of the offered evidence refutes the Commission’s conclusion that it does. The Commission also rejected SFPP’s argument that it should receive a partial ITA. Procedurally, Commission found the argument to be untimely raised on rehearing. Further, the Commission rejected the substance of the proposal because the issue of double recovery would still be present. On the issue of MLP incentive distributions and their interaction with evaluating the reasonableness of an income tax allowance, the Commission reversed its prior determinations finding, among other things, that allowing incentive distributions to influence the derivation of an income tax allowance would be contrary to the Commission’s stand-alone tax policy and, in addition, allowing an ITA to be based on incentive distributions in a partnership agreement would lead to nonsensical results and is not needed to attract capital.

Regarding ADIT, the Commission found that it was appropriate for SFPP to eliminate its ADIT balance from its cost of service because (i) the ITA had been removed, (ii) shippers had no alleged right to the accumulated ADIT balance, and (iii) amortizing excess ADIT in rates back to shippers would be prohibited retroactive ratemaking pursuant to the D.C. Circuit’s decision in Public Utilities Commission California v. FERC. The Commission allowed SFPP to update its litigation surcharge to account for costs incurred since the 511-B Compliance filing and found a three-year recovery period to be appropriate. However, the Commission rejected SFPP’s assertion that it reserved the right to recover litigations costs it is unable to recover in IS11-444-002 as beyond the scope of the proceeding. As noted, the Commission rejected SFPP’s proposed ORR reserve mechanism as unjustified and contrary to the general policy that shippers should not bear the costs of other shippers’ debts.

On March 8, 2019, the Joint Shippers filed a motion for clarification requesting that the Commission clarify that Opinion No. 511-D obligated SFPP to pay refunds to all shippers within 30 days. The Commission granted this Motion on March 21, 2019.

This decision is currently being reviewed by the D.C. Circuit in Case No. 19-1067, et al. (consolidated) as described above.

d. SFPP 2009 and 2010 East Line (Docket Nos. IS09-437 and IS10-572)

Closely related to the Docket No. IS08-390 proceeding is the dispute regarding SFPP’s 2009 and 2010 East Line rate increase proceedings, Docket Nos. IS09-437 and IS10-572. As described in prior reports, on July 31, 2009, SFPP filed FERC Tariff No. 182, to be effective September 1, 2009 (“East Line Tariff Filing”) and on May 28, 2010, SFPP filed FERC Tariff No. 187 (“2010 Index Filing”), pursuant to the Commission’s annual rate indexing methodology for oil pipelines. SFPP’s 2009 rate increase proceeding was protested by shippers and went to a hearing which resulted in an Initial Decision issued February 10, 2011. On September 20, 2012, the Commission issued its determination concerning the Initial Decision (i.e., Opinion No. 522). On February 19, 2015, the Commission partially granted rehearing in Opinion No. 522-A. On March 23, 2015, SFPP sought rehearing of Opinion No. 522-A. On April 6, 2015, SFPP submitted its Compliance Filing Pursuant to Opinion No. 522-A. On April 20, 2015, Joint Shippers filed a Protest of the April 5, 2015 Compliance Filing. On May 5, 2015 SFPP filed Reply Comments.

On March 15, 2018 the Commission issued Opinion No. 522-B. This opinion reverses Opinion No. 522-A insofar as it allowed SFPP to apply index increases different from what the carrier actually sought in the subject years in indexing-forward its rates for deriving refunds and going-forward rates. The Commission also directed SFPP to remove any income tax allowance in the development of its cost-based rates and related refunds, “consistent with United Airlines, the Remand Order in Docket No. IS08-390 and the Revised Policy Statement on Treatment of Income Taxes in Docket No. PL17-1.” The decision also rejected SFPP’s prior rehearing request as moot given that SFPP was not entitled to incorporate a 2011 index increase in its compliance filing. SFPP filed its Opinion No. 522-B Compliance Filing on May 14, 2018 and shippers filed their protests related thereto on June 8, 2018.

The subsequent pleadings mirrored in timing, form, and substance those in SFPP’s West Line rate case (Docket No. IS08-390) discussed above.

On March 26, 2019, Joint Shippers filed a Motion to Lodge the Commission’s Order on Clarification issued in Docket No. IS08-390 (the West Line docket) which directed SFPP to pay refunds. Joint Shippers argued that the nearly identical procedural posture of the West Line Case should impose the same obligation regarding the East Line proceeding. On April 10, 2019, SFPP filed an Answer to Joint Shippers’ Motion arguing that the two dockets were different and that establishing global settlement procedures would be more judicially efficient. On April 19, 2019, Joint Shippers filed a response and argued that further delay as to refunds was not justified.

As of publication of this Report, the Commission has not yet acted on SFPP’s Opinion No. 522-B Compliance Filing, the related protests, or the Motion to Lodge.

e. Chevron Products Company, et al. v. SFPP, L.P. (Docket No. OR16-6)

As noted in previous reports, on December 4, 2015, Chevron Products Company, HollyFrontier Refining & Marketing LLC, US Airways, Inc., Valero Marketing and Supply Company, and Western Refining Company, L.P. (“Joint Complainants”) filed a joint complaint in Docket No. OR16-6 against SFPP, L.P. (“SFPP”) challenging the lawfulness of the existing transportation rates and charges for services on the carrier’s “East Line” facilities originating in El Paso, Texas and delivering to Lordsburg, New Mexico; Tucson, Arizona; Phoenix, Arizona; and various military destinations. The Joint Complainants alleged that Page 700 data from SFPP’s Form No. 6 report for 2014 and data from SFPP’s Opinion 522-A Compliance Filing demonstrated that SFPP’s East Line rates were not just and reasonable as they were substantially over-recovering the carrier’s applicable costs. The joint complaint requested reparations for past payments and the establishment of just and reasonable rates going forward.

SFPP filed an answer to the joint complaint arguing that the data upon which the Joint Complainants relied is subject to change based on the result of several ongoing rate and complaint proceedings. Therefore, SFPP asked the Commission to hold the joint complaint in abeyance until the pending dockets reach a final outcome. Joint Complainants responded, laying out their arguments for why the joint complaint should not be held in abeyance. On March 23, 2016, the Commission issued an order stating that the Joint Complainants had presented a prima facie case to support their rate challenge and set the complaint for a hearing.

On June 24, 2016, Joint Complainants filed their direct testimony estimating that Joint Complainants had overpaid for shipments on the East Line by approximately $44.5 million between December 2013 and May 2016. SFPP filed its answering testimony on August 12, 2016 challenging Joint Complainants’ positions. However, SFPP’s own testimony demonstrated rate reductions on the East Line were in order. Commission Trial Staff filed direct and answering testimony on September 14, 2016 which, based on the cost-of-service elements and principles addressed, advocated East Line rate reductions in excess of Joint Complainants. On October 18, 2016, SFPP filed testimony responding to Commission Trial Staff and challenging Staff’s economic analysis.

Joint Complainants and Commission Trial Staff filed their respective rebuttal testimonies on November 23, 2016. Notably, Joint Complainants updated their overpayment calculations for the period December 1, 2013 through September 30, 2016 based on updated cost information and their interpretation of the United Airlines, Inc., et al. v. FERC, 827 F.3d 122 (D.C. Cir. 2016) decision and asserted that aggregate overpayments to SFPP totaled approximately $70 million. A hearing was held from January 24 to February 7, 2017.

In the Initial Decision, filed on July 21, 2017, the Presiding Judge found that the Joint Complainants are due reparations from SFPP (with interest) equal to the difference between what SFPP collected for East Line service and the amount to be established by the Commission as just and reasonable based on the cost-of-service and throughput rulings set forth in the Initial Decision.

The Initial Decision addressed the following rate design and development issues: (i) the determination of an appropriate base and test period for deriving going-forward rates and computing reparations; (ii) the appropriate throughput level for deriving reasonable rates and whether actual throughput for the base and test period should be adjusted for any particular shipper or refinery events; (iii) the appropriate cost of capital, capital structure, and proxy group to rely on for deriving rates; (iv) the appropriate level of operating expenses, including right-of-way, environmental remediation, regulatory litigation, and oil losses and shortages, and whether such test period costs should be updated as of the end of the test period; (v) depreciation expenses; and (vi) the appropriate treatment of SFPP’s request for an income tax allowance now that it is ultimately owned by a corporation versus its prior ownership by a master limited partnership which situation was addressed in the D.C. Circuit’s United Airlines decision.

The Initial Decision found in favor of Commission Trial Staff’s and Joint Complainant’s positions in multiple instances indicating that reparations will need to be paid. However, the ultimate just and reasonable rates for SFPP’s East Line service will be established after the Commission addresses the briefs on and opposing exceptions associated with the Initial Decision and any related SFPP compliance filing(s) associated with implementing the Commission’s related cost and throughput decisions. Briefs on exception to the Initial Decision were filed September 20, 2017 and briefs opposing exceptions were filed on October 17, 2017.

In addition, on September 20, 2017, SFPP filed a Motion to Reopen the Record, or, in the Alternative, for the Commission to Take Administrative Notice. SFPP’s motion stated that a long-running dispute with Union Pacific Railroad Company (“UPRR”) regarding the rental expenses for, among others, the East Line right-of-way paid by SFPP to UPRR during the test period was resolved after the close of evidence in the docket. SFPP contended that this settlement affects SFPP’s overall cost-of-service calculation and therefore moved to re-open the record so the settlement figure could be incorporated into the cost-of-service analysis as it respects the Commission’s review of the Initial Decision. Alternatively, SFPP requested the Commission to take administrative notice of the court record showing that the dispute between SFPP and UPRR regarding the rental expenses had been resolved and terminated.

Joint Complainants and Trial Staff both filed answers to SFPP’s motion on October 5, 2017. Trial Staff stated that it did not oppose reopening the record to admit the new right-of-way cost figures so long as an adequate supplemental record could be established through limited testimony and procedures. However, Trial Staff opposed the Commission taking administrative notice of these facts. Joint Complainants’ opposed both reopening the record and the Commission taking administrative notice. Joint Complainants argued that the UPRR rental expense is one discrete and minor cost item among many others and therefore does not meet the Commission’s high bar for evidence worthy of submission after the record is closed. Moreover, Joint Complainants argued that SFPP is not able to add this new cost item into its test period cost-of-service calculation because such would amount to improper retroactive ratemaking and that Commission policy and precedent precludes spot adjustments to costs of service following the close of the record. Joint Complainants further argued that to the extent the carrier desired to recover its alleged increased cost, it should file a rate case where all costs and revenues could be evaluated to determine whether any cost increases were offset by cost decreases and/or increased revenues.

On December 12, 2018, SFPP filed another Motion to Reopen the Record. SFPP requested a paper hearing to discuss applying in that proceeding a new rate of return methodology (the Composite Method) which SFPP alleged was announced by the Commission in another proceeding under the Federal Power Act. SFPP argued that reopening the record was justified because this new policy amounts to an extraordinary circumstance, the policy was not announced before the close of the record in Docket No. OR16-6, and reopening the record at this stage would promote administrative efficiency. On December 27, 2018, Commission Trial Staff filed an Answer to SFPP’s Motion, taking the position that reopening of the record may be justified as the Commission had appeared to articulate a new policy. In its Answer, Staff also emphasized the high burden to reopen the record and requested any reopening be narrowly defined. Joint Complainants answered the motion on December 27, 2018, arguing that the burden had not been met to reopen a proceeding that had already taken so long, and that a new policy articulated under the FPA was not applicable to proceedings under the Interstate Commerce Act. On January 10, 2019, SFPP answered Joint Complainants Answer asserting that the Coakley Briefing Order was an extraordinary change in circumstance, a re-opened proceeding would be limited, and reopening was consistent with precedent.

On January 18, 2019, Joint Complainants filed a Motion to Supplement Answer and Supplement of Answer. Joint Complainants sought leave to supplement their answer because the Commission issued a subsequent order on January 7, 2019 clarifying that the Coakley Briefing Order had neither rejected the DCF methodology used in the present proceeding or adopted the Composite Methodology. In particular, the Commission stated, “the Commission did not reach any final conclusions or make any final determinations with respect to the new ROE methodology in the Briefing Order,” and that the “Commission also did not reach any final conclusions or make any final determination in the Briefing Order with respect to the use of the DCF in determining the ROE or whether DCF alone has ceased to be sufficient to estimate investors’ expectations for a return on equity.” On January 25, 2019, Commission Trial Staff filed an Answer to Joint Complainants Motion to Supplement, urging the Commission to accept the Joint Complainants’ supplemental answer and reject SFPP’s Motion to Reopen in light of the Commission’s pronouncements. On February 11, 2019, SFPP filed an Answer to Joint Complainants Motion, arguing that the language cited by Joint Complainants and Staff in the January 7 Coakley Order spoke to the finality of that order, and did not undermine the policy articulated in the Coakley Briefing Order which allowed parties to brief the issue of whether the DCF methodology or the Composite Method was more appropriate.

As of this report, the Commission has not yet ruled on the Initial Decision and the exceptions taken with respect thereto or on SFPP’s motions to reopen the record.

f. 2011 West Line Index (Docket No. IS11-444)

As described in past reports, on May 27, 2011, SFPP submitted a company-wide index rate increase of 6.88 percent. This was protested by various shippers and SFPP ultimately chose only to defend the West Line index-based rate increase as part of this proceeding. On March 12, 2012, the Presiding Judge granted summary judgment against SFPP on the grounds that SFPP was over-recovering its West Line costs by 1.16 percent for the relevant review period and thus was not entitled to any index-based rate increase associated with this line.

On exceptions, the Commission issued two orders. On July 12, 2012, the Commission denied SFPP’s motion to reopen the record to incorporate 2011 data into the evaluation of the reasonableness of the proposed 2011 index increase on the grounds that calendar-year 2011 data was irrelevant and that the relevant analysis is focused on cost changes between 2009 and 2010. On June 6, 2013, the Commission also issued Opinion No. 527, which upheld the Presiding Judge’s granting of summary judgment. Opinion No. 527 did not look at the difference between 2010 revenues and 2010 costs, stating “comparing costs to revenues in a single year is irrelevant.” Opinion No. 527 also refused to remove surcharged litigation costs and revenues from its analysis, because “there is no distinction between so-called ‘surcharged’ and ‘nonsurcharged’ litigation expenses for purposes of the percentage comparison test of the prior two years’ Form No. 6 data.” Accordingly, the Commission directed that SFPP refund to West Line shippers the index-based rate increase previously put into effect.

On July 8, 2013, SFPP filed a Request for Rehearing and Clarification and for Expedited Consideration. The Rehearing Request claimed that Opinion No. 527 was internally inconsistent. The Rehearing Request further asserted that the rejection of the index increase in Opinion No. 527 was inconsistent with the Commission’s practice of allowing pipelines to take an increase up to a 10 percent threshold. SFPP also sought clarification on Opinion No. 527’s declaration that comparing “costs to revenues in a single year is irrelevant.” On July 23, 2013 Shippers responded arguing that SFPP’s arguments were misplaced and that it was unlikely to prevail at trial and that the 10 percent rule was a screening tool not applicable at a trial type hearing.

On March 15, 2018, the Commission issued its Order on Rehearing and Establishing Further Hearing and Settlement Judge Procedures (Opinion No. 527-A), which partially granted SFPP’s rehearing request. The Commission affirmed the use of West-Line only data (versus total company data) to evaluate the proposed index rate increase, and clarified that Opinion No. 527’s emphasis regarding Form No. 6, Page 700 total company cost data did not change this determination. The Commission also upheld the July 2012 Order’s refusal to consider 2011 end-of-year cost and revenue data to evaluate the reasonableness of the proposed 2011 index-based rate increase.

However, the Commission found that the previous determination to reject the carrier’s index-based West Line rate increase in its entirety was unjustified based on the current record. Regarding the 10-percent threshold used at the screening stage of index protests proceedings, the Commission acknowledged that parties can advocate a different standard at hearing, but found that “the present record would not justify Opinion No. 527’s rejection of the index increase.” The Commission also found that “Opinion No. 527 improperly rejected SFPP’s West Line index increase based upon data that includes revenues and costs associated with SFPP’s litigation surcharge.” However, the Commission clarified that “if a pipeline’s revenues already significantly exceed its costs, then this pre-existing disparity will magnify the effect of any difference between an indexed rate change and the pipeline’s cost changes” and, as such, “[s]o long as the consideration of revenues is tied to the language of the regulation and indexing’s policy objectives, then the parties may consider revenues at hearing.” In sum, the Commission found that the current record was insufficient to accept the index increase and therefore directed that a new hearing be held and that settlement procedures be explored.

Opinion No. 527-A provided three pieces of guidance for the future hearing. First, because the Commission’s percentage comparison test is a screening mechanism, at hearing parties may advance other methods which “fully explain why the percentage comparison test and the 10-percent threshold do not justify accepting or rejecting SFPP’s 2011 West Line index” The Commission also clarified that “Opinion No. 527’s statement that ‘comparing costs to revenues in a single year is irrelevant’” was “overly broad.” Finally, the Commission emphasized that the hearing must revolve around indexing policy objectives of simplified rate regulation and rewarding efficient pipeline operation.

On May 3, 2019, SFPP, L.P. filed an Offer of Settlement. On May 23, 2019, Staff filed comments in support of the Settlement stating that the Settlement is fair, reasonable, and in the public interest. On June 12, 2019, the Settlement Judge issued a Certification of Uncontested Settlement. On August 7, 2019, the Commission issued a Letter Order Approving the Settlement.

g. ConocoPhillips Company v. SFPP, L.P., (Docket No. OR11-13); Chevron Products Company, (Docket No. OR11-16); and Tesoro Refining and Marketing Company, (Docket No. OR11-18)

As briefly discussed in past reports, on June 13, 2011, ConocoPhillips Company (“ConocoPhillips”) and Chevron Products Company (“Chevron”) filed similar complaints (Docket Nos. OR11-13 and OR11-16, respectively) challenging the justness and reasonableness of the interstate rates on SFPP, L.P.’s (“SFPP”) pipeline system, including the portions grandfathered by the Energy Policy Act of 1992 (“EPAct 1992”). These complaints were followed on July 20, 2011 by a similar complaint instituted by Tesoro Refining and Marketing Company (“Tesoro”) (Docket No. OR11-18). SFPP filed a Joint Answer to Chevron’s and ConocoPhillips’s Complaints on July 5, 2011, and an Answer to Tesoro’s Complaint on August 9, 2011.

On October 3, 2011, the Commission issued its Order on Complaints and Establishing Further Procedures. This order found that notwithstanding SFPP’s reported over-recovery of costs, because SFPP reported its 2010 revenue and cost-of-service data on a consolidated system-wide basis, the record was insufficient to determine whether complainants had made an appropriate showing that the carrier’s rates on its individual pipeline systems warranted investigation as potentially being unjust and unreasonable. The Commission ordered that the complaints be held in abeyance and directed SFPP to provide segmented or system-specific revenue and cost-of-service data after appropriate progress had been made in connection with SFPP’s ongoing rate proceeding in Docket No. IS08-390 as this case dealt with “issues that have a very large economic impact on rates, most notably the income tax allowance and overhead cost allocation issues.” The Commission identified that once SFPP did ultimately provide the referenced segmented cost and revenue data, the complainants would have a reasonable period of time to submit amended complaints.

On March 15, 2018, the Commission issued an Order Establishing Further Procedures in the referenced dockets. The Commission found that it had “sufficiently resolved the ongoing litigation involving SFPP's 2008 rate case in Docket No. IS08-390 to proceed with these complaints.” The Commission lifted the abeyance and directed SFPP to provide the segmented cost, revenue and throughput data for each of its systems.

On June 13, 2018, SFPP submitted its cost, revenue, and throughput data for calendar years 2009 and 2010 and moved to hold the proceedings in abeyance on the grounds that a rehearing request of Order 511-C was pending. On August 10, 2018, Tesoro filed two Amended Complaints: one challenging SFPP’s West Line rates and the other challenging the carrier’s North and Oregon Line rates. On August 13, 2018, Philipps 66 and Chevron filed Amended Complaints which withdrew that portion of their original complaints challenging SFPP’s East Line, Sepulveda Line, and Watson Station rates, but continued to challenge the carrier’s West, Oregon, and North Line rates. Both filings also responded to SFPP’s motion to hold the proceeding in abeyance.

Based on SFPP’s compliance filing data and by making certain cost-of-service adjustments they believed appropriate, the Philipps 66 and Chevron Amended Complaints alleged an 8.8 percent over-recovery of costs for the West Line, a 15.5 percent over-recovery for the North Line, and a 22.6 percent over-recovery for the Oregon Line. These Amended Complaints also alleged that their preliminary analyses demonstrated that the change in the achieved real rate of return on equity for the Oregon and North Lines, when compared to the achieved real rates of return in prior periods, raised serious questions as to the grandfathered status of the Oregon and North Line rates pursuant to the Energy Policy Act of 1992 (“EPAct 1992”). Tesoro’s Amended Complaint made similar assertions, estimating a 2010 over-recovery of 15 percent for the North Line and 22 percent for the Oregon Line, and not making a numerical estimate regarding the West Line absent discovery. Tesoro also asserted that its preliminary analysis of the achieved real rates of return on equity for the North and Oregon Lines for the relevant time periods placed in question the grandfathered status of the carrier’s North and Oregon Line rates.

On September 10, 2018, SFPP filed its Answers to the Amended Complaints in all three unconsolidated but related dockets. Regarding the West Line, SFPP’s Answer claimed none of the complainants had made a prima facie showing that the rates were unreasonable. SFPP asserts the adjustments were unwarranted and that, even with adjustments, the estimated over-recovery of 8.8 percent fell within a reasonable range of divergence between costs and revenues. Regarding the North and Oregon Lines, the Answer emphasized that the burden to examine grandfathered rates lies with complainants and argued that they had failed to meet this burden here. SFPP also asserted that the interstate status of the Oregon Line is doubtful, and claimed the burden lies with complainants to establish jurisdiction. SFPP also contended that the complaints’ request for reparations are directly impacted by previous global settlements resulting in a claimed overstatement of potential damages.

On September 24, 2018, Tesoro filed an Answer to SFPP’s Answer, arguing the Answer amounted to a motion to dismiss. And on October 9, 2018, Chevron and Phillips 66 filed a similar Motion for Leave to Respond and Response to SFPP’s Answer. The complaining shippers all argued that there is no 10% threshold divergence of cost and revenues to set a complaint for hearing, that SFPP’s 10% threshold is a novel standard unsupported by law or precedent, and that the complainants had met their prima facie burden of alleging reasonable grounds that the rates are unjust and unreasonable. The complaining shippers also took issue with SFPP’s characterization of Accumulated Deferred Income Taxes (“ADIT”) for similar reasons raised by shipper parties in other SFPP dockets discussed herein. Complaining shippers defended the use of a pipeline’s actual capital structure model and contended that, contrary to SFPP’s claims, recovery is not barred by any previous settlements because those settlements contain exclusions which cover the time period at issue in this case. Complaining shippers defended their estimates and assertions regarding costs resulting from a right of way settlement, pipeline relocation, and environmental remediation. Chevron and Phillips 66 also took issue with SFPP’s characterization of its Oregon Line shipments as intrastate and non-jurisdictional, since the location of a line in one state is not dispositive of its jurisdictional status. These issues, shippers contend, preclude dismissal and require a hearing.

On October 9, 2018, SFPP filed an Answer to Tesoro’s answer and on October 24, 2018 filed an Answer to the Answer of Chevron and Phillips 66. SFPP stressed that the “substantially over-recovering” language came directly from the Commission’s October 2011 Order. SFPP also defended the 10% threshold and distinguished Epsilon Trading cited by the complainants because the over-recovery alleged was higher than 10% although the carrier’s Page 700 in that case showed less. SFPP supported its treatment of ADIT and argued the amount in this case is too small to help complainants meet their prima facie burden. SFPP also asserted, once again, the recovery sought is barred by settlement, as the exclusion in the Global Settlement cited by the shippers was limited to particular other dockets.

As of the publication of this report, the Commission has not yet acted on the shippers’ Amended Complaints and the carrier’s response thereto described above.

h. 2012 and 2013 Indexing Complaints (Docket Nos. OR14-35 and OR14-36)

As noted in prior reports, on June 27 and 30, 2014, HollyFrontier Refining & Marketing LLC, Southwest Airlines Co., Tesoro Refining and Marketing Company, US Airways, Inc., Valero Marketing and Supply Company, Chevron Products Company, and Western Refining Company, L.P. (collectively, “Joint Complainants”) filed complaints challenging the justness and reasonableness of SFPP, L.P.’s (“SFPP”) West and East Line 2012 index rate increases and the justness and reasonableness of SFPP’s West, East, Oregon , North, and Sepulveda Line 2013 index rate increases. SFPP filed its answer on July 28, 2014, arguing that the Joint Complainants failed to show a reasonable basis for the Commission to reject the 2012 and 2013 index rate changes. On October 31, 2014, the Commission held the complaint proceedings in abeyance pending the resolution of other ongoing proceedings affecting SFPP’s rates, including Docket Nos. IS08-390, IS09-437, and IS11-444. On November 26, 2014, Joint Complainants filed a request for rehearing, asserting that FERC’s decision to hold the complaint in abeyance was in direct contradiction to its policy of streamlining index rate challenges and basing such decisions solely on the pipeline’s Form No. 6 Page 700 data.

On December 8, 2016, the Commission issued its Order on Rehearing and Dismissing Complaints. The Order stated that the Joint Complainants failed to satisfy the second part of the “substantially exacerbate” test: showing reasonable grounds that the pipeline’s index increase substantially exacerbates the carrier’s existing over-recovery. The Commission stated that the difference between SFPP’s costs and revenues (i.e., over-recovery) declined from 2011 to 2013, based on end-of-year cost and revenue data from the carrier’s 2013 Form 6 post-dating the index rate increases at issue. As a result, the Commission concluded that the Joint Complainants did not show that the 2012 and 2013 index rate increases substantially exacerbated the pipeline’s existing over-recovery.

On January 9, 2017, Joint Complainants filed a request for rehearing concerning the Commission’s December 8 Rehearing Order. The Joint Complainants claimed that the December 8 Rehearing Order’s failure to rely on specifically the cost and revenue data from the two years prior to the subject index rate change unreasonably alters FERC’s established test for determining whether an index rate increase “substantially exacerbates” the over-recovery of a pipeline’s cost of service without reasoned basis and contrary to precedent. SFPP filed, on January 24, 2017, a Motion for Leave to Answer and Answer to Joint Complainants rehearing request disputing the arguments made in opposition to the December 8 Rehearing Order.

On March 15, 2018, the Commission issued its order denying rehearing. The Commission found that, contrary to Joint Complainants contentions, it had not altered the “substantially exacerbate” test since different situations call for different analysis. The Commission determined that notwithstanding its prior orders indicating that index-based rate increases should be evaluated based on the change in costs between the previous two years, given the timing of the complaint (i.e., near the end of the ICA’s two-year statute of limitations), the carrier’s Form No. 6 Page 700s showed a declining over-recovery from 2011 to 2013 and this “continuing decline is inconsistent with the claim that the index increase substantially increased any pre-existing over-recovery.” In this connection, the Commission, for the first time, identified that when an index complaint is filed can dictate what cost and revenue information can be relied on to evaluate the reasonableness of the challenged index rate increases.

The Joint Complainants filed Petitions for Review with the Court of Appeals for the D.C. Circuit on May 14, 2018. And SFPP moved to intervene in the consolidated dockets on June 7, 2018.

The Joint Complainants (now “Petitioners”) filed their Initial Brief on October 26, 2018, requesting the Court to vacate FERC’s orders with instructions to reconsider the complaints. Petitioners argued that FERC policy is clear that an index rate increase is intended to compensate a pipeline for the cost changes occurring between the two preceding years. And that therefore, when evaluating an index rate increase, FERC has consistently held that only the pipeline’s cost and revenue data between the two preceding years is relevant. Petitioners thus argue that FERC’s dispositive reliance on data after the effective date of the increase constitutes an unjustified departure from the agency’s established methodology and past precedent without any explanation, rendering the Order arbitrary and capricious.

Petitioners also argued that applying different standards based on when complaints are filed within the applicable statute of limitations is arbitrary and invites gamesmanship and undermines the policy goal of simplified ratemaking for indexed rates. Petitioners further claimed the Rehearing Order relied on data FERC knew to be incorrect by relying on SFPP’s Form No. 6, Page 700 data that included an income tax allowance (“ITA”) despite a Commission policy no longer allowing that allowance in a cost of service for entities such as SFPP. Petitioners point to orders issued by the Commission the same day, including in another SFPP index dispute, which inconsistently took account of and directed the removal of any ITA from the carrier’ s cost of service before evaluating the reasonableness of the index-based rate change.

Respondent FERC filed its Brief on December 21, 2018 and SFPP filed its Intervenor Brief in Support of Respondents on January 10, 2019. FERC defends its reliance on data significantly post-dating the increase on the grounds that the shippers filed their complaints more than a year later and the Commission had not necessarily committed itself to reviewing only the data from the prior two years. Respondent FERC argued it had not yet clarified whether its indexing policy was forward-looking or backwards-looking, leaving it with the purported discretion to decide in specific cases. FERC argued the Rehearing Order did acknowledge the departure from “generally” using data and adequately justified the broader approach as yielding a sounder and more equitable result. Respondent also claimed Petitioners should not be allowed to cite prior FERC orders where the Commission had refused to consider new data when available on the grounds that Petitioners did not specifically cite those cases to the agency. SFPP argued that the substantially exacerbate test is inherently forward-looking because exacerbation occurs in the future. FERC asserts there is little concern of gamesmanship because complainants choose the timing of their complaints. Respondent FERC also argued that applying the Commission’s ITA policy here would contravene the goal of simplicity inherent in index proceedings.

Regarding the reliance on incorrect data, FERC argued that Petitioners cannot raise that argument before the Court because they had not raised it before the agency. FERC further argued that under simplified indexing procedures, the Commission does not examine assumptions underlying the annual cost data included in the Form No. 6, Page 700. SFPP also argued that Petitioners had not exhausted their administrative remedies. SFPP further argued that Petitioners invited the alleged income tax allowance-related error because by filing their Request for Rehearing of FERC’s order originally holding the case in abeyance, they urged the Commission not to wait to consider the outcome of the proceedings which ultimately required SFPP to remove its income tax allowance. Therefore, SFPP argues, the Petitioners should not now have the benefit of those rulings because it allegedly induced the Commission to ignore them.

Petitioners filed their Reply Brief on February 11, 2019. Petitioners asserted Respondents had not rebutted arguments that past Commission precedent considered post-index rate increase data entirely irrelevant. They took issue with FERC’s claims that its own precedent was unclear as to whether its indexing mechanism is retrospective or prospective. Petitioners contend the agency’s precedent is clear that it is retrospective and FERC could not cite to any authority supporting its contrary theory. Petitioners claim they are not precluded from citing FERC precedent not cited before the agency because they had fully raised the issue of inconsistency there and were not required to cite each and every case FERC has issued finding that index-based rate increases are only retrospective especially where FERC has never before permitted cost and revenue data post-dating the index-based increase to influence an evaluation of the reasonableness of index-based rate increase. Petitioners also assert they were not required to request rehearing regarding FERC’s reliance on incorrect data because they could not have raised that issue prior to issuance of the final order. Petitioners assert that applying the ITA policy will not impair the simplicity of the proceedings as the issue is resolved and the application would be straightforward. Petitioners also dispute that they invited FERC’s error.

Oral argument was held on April 12, 2019. On June 14, 2019, the D.C. Circuit vacated and remanded the orders in an opinion written by Judge Tatel. The Court ruled, consistent with Petitioner shippers’ arguments, that the Commission had departed from its prior policy without an adequate explanation. The Commission’s proffered explanation—that the new data was now available—assumed without explanation that the information is relevant, which, according to the Court, “calls into question the purpose of indexing itself.” The Court also questioned whether the Commission could allow the question of “the purpose of indexing . . . to go unanswered” and still engage in reasoned decisionmaking. The Court directed the Commission to “explain its actions in a way that coheres with the rest of its indexing scheme” on remand.

As of publication of this Report, the Commission has not yet acted on the D.C. Circuit’s remand.

i. Aircraft Service International Group, Inc., et al. v. Central Florida Pipeline LLC, et al. (Docket No. OR16-26)

As noted in prior reports, Aircraft Service International Group, Inc. (“ASIG”), American Airlines, Inc., Delta Air Lines, Inc., Hookers Point Fuel Facilities LLC, Southwest Airlines Co., United Aviation Fuels Corporation, and United Parcel Service, Inc. (collectively, “Joint Complainants”) filed a joint complaint against Central Florida Pipeline LLC (“CFPL”) and Kinder Morgan Liquid Terminals LLC (“KMLT”) on September 20, 2016. The complaint alleged that CFPL has unlawfully provided for physical transportation of jet fuel in interstate commerce on its pipeline from a KMLT terminal in Tampa, Florida (“KMLT Terminal”) to CFPL delivery points at a liquids terminal in Taft, Florida and the ASIG terminal at Orlando International Airport without filing a tariff with the Commission. The joint complaint also alleged that KMLT has unlawfully provided un-tariffed FERC-jurisdictional break-out tankage service at its liquids terminal in Tampa, Florida. Finally, based on public filings related to CFPL costs, the joint complaint alleged that the rates charged by CFPL for the transportation of jet fuel are not just and reasonable. Joint Complainants requested that the Commission order an evidentiary hearing to determine just and reasonable rates for jet fuel transportation on CFPL’s pipeline, as well as direct CFPL to file an appropriate FERC-related tariff in recognition that CFPL is providing interstate transportation of jet fuel.

CFPL and KMLT filed a joint answer on October 17, 2016. CFPL and KMLT argued that there is a “break” between the waterborne movement of jet fuel to the KMLT Terminal and the subsequent transportation of jet fuel to Orlando and other Florida airports. As a result of this alleged break in the chain of commerce, CFPL and KMLT argued that CFPL does not provide interstate transportation of jet fuel and, therefore, the Commission does not have jurisdiction over the pipeline. CFPL and KMLT also argued that KMLT does not provide un-tariffed FERC-jurisdictional break-out tankage service at its liquids terminal in Tampa, Florida because the tanks at the Tampa terminal are not necessary for the operation of the pipeline (i.e., there are other points at which product may originate). Finally, the defendants argued that the Joint Complainants’ over-recovery analysis is incorrect and should be disregarded.

The Commission issued an order on December 15, 2016 setting this matter for hearing, stating: “because of the need for an intensely factual inquiry and the need to examine closely the complex nature of the transactions and relationships between various entities on both sides of the complaint, it would not be appropriate to make a jurisdictional determination based upon the pleadings alone.” The Commission noted that the threshold question in this matter is whether the CFPL pipeline and the KMLT terminal facilities are providing interstate transportation service and therefore directed the ALJ “to establish appropriate hearing procedures, including whether a phased hearing is required.”

On January 5, 2017, the Presiding Judge requested briefs from the parties on whether a phased hearing is “required.” The Joint Complainants submitted comments arguing that a two-phase proceeding would be inefficient and result in a longer time frame for CFPL and KMLT to provide un-tariffed transportation and break-out storage services. CFPL and KMLT submitted joint comments stating that a two-phase proceeding was appropriate and most efficient. On January 25, 2017, the Presiding Judge issued an Order Phasing Case and Establishing Procedural Schedule. The Presiding Judge stated that the factors enumerated by the Commission in Trans-Alaska Pipeline System, 16 FERC ¶ 61,245 (1981), dictate that a two phase proceeding is appropriate in this matter. Phase 1 of the hearing would address whether the CFPL pipeline and the KMLT terminal facilities are providing interstate oil pipeline transportation service that is subject to the Commission’s jurisdiction under the ICA. Phase 2, if necessary, would address the remaining issues including the justness and reasonableness of CFPL’s rates. The Phase 1 hearing commenced on August 31, 2017 and concluded on September 21, 2017.

The Presiding Judge issued an Initial Decision on January 30, 2018, finding generally that KMLT/CFPL’s pipeline was providing intrastate service not subject to FERC’s jurisdiction. First, with respect to the issue of whether KMLT should be dismissed from the proceeding, the Presiding Judge denied KMLT/CFPL’s motion for summary disposition because material facts remained in dispute at the time of the filing of the motion regarding KMLT’s control over certain facilities and the intent/purpose of certain agreements.

Second, the Presiding Judge indicated that she gave significant weight to the jurisdictional test and related line of cases utilized in Guttman Energy, Inc. v. Buckeye Pipe Line Company, L.P., 161 FERC ¶ 61,180 (2017) (“Guttman”), to determine that transportation on CFPL is not jurisdictional (i.e. intrastate). The Presiding Judge stated that the appropriate test to determine the nature of transportation on CFPL is (i) whether the product comes to rest at a point of interruption and (ii) whether the point of interruption constitutes a “‘sufficient break’ in the continuity of the transportation, such that the foreign or interstate journey comes to an end and subsequent movements beyond the point of interruption constitute independent, intrastate transportation.” After determining that transported jet fuel comes to rest at the KMLT Terminal, the bulk of the Initial Decision weighed the multiple factors relevant to the inquiry regarding whether a sufficient break in the continuity of transportation had occurred at that point. The Presiding Judge determined that these factors weighed in favor of finding a sufficient break at the KMLT Terminal, such that subsequent transportation on the CFPL should be considered intrastate transportation.

Notably, in recognition of the Joint Complainants’ arguments and related precedent relied on, the Presiding Judge observed that “there is another line of cases that has revised” the jurisdictional test used in the Initial Decision – namely, cases related to the Interstate Commerce Commission’s (“ICC”) Policy Statement – Motor Carrier Interstate Transportation – From Out-of-State Through Warehouses to Points in Same State, 8 I.C.C. 2d 470 (1992) (“1992 Policy Statement”) and related case law. The Presiding Judge concluded the Initial Decision by stating that “[t]he Commission may want to review the 1992 Policy Statement” and subsequent case law and noting that application of this precedent “to the present proceeding might alter the outcome.”

The Presiding Judge determined that her decision regarding the intrastate nature of transportation on CFPL mooted the issue of whether the break-out tankage service at the KMLT Terminal is jurisdictional.

On March 1, 2018, opposing briefs on exception were filed by Joint Complainants and KMLT and CFPL. Complainants raised several exceptions. Chief among them was that the Initial Decision viewed the factors in an overly restricted and isolated manner, rather than in a broader or holistic context. Joint Complainants alleged this was a legal error which led to various factual errors on most key points in dispute. Joint Complainants also argued that the question of whether the KMLT Terminal was jurisdictional was not moot and that the Initial Decision erred by declining to adopt the methodology and analysis espoused in the ICC’s 1992 Policy Statement.

The two parties also took exception to the Initial Decision’s characterization of a product’s coming to rest as a “threshold” to be met before applying certain evaluation factors. On exceptions, KMPLT and CFPL argued that such a determination is the conclusion of the factor-driven inquiry, not a condition precedent to it.

On March 22, 2018, briefs opposing exception were filed by Joint Complainants, KMLT and CFPL, and Commission Trial Staff. Joint Complainants agreed with Respondents that the Initial Decision misapplied the law by treating the factual inquiry concerning the issue of whether a product has come to rest as a threshold question but differed from KMLT and CFPL by arguing that the Northville Dock factors are not a conclusive test.

In their Brief Opposing Exceptions, KMLT and CFPL argued that Joint Complainant’s analysis would be disruptive of the Commission’s jurisdictional treatment of oil pipelines and have negative policy ramifications. They also supported the conclusions reached by the Initial Decision and argued that Joint Complainant’s factual evidence and legal arguments had been adequately addressed. Commission Trial Staff agreed with KMLT and CFPL on all relevant points and took issue with Joint Complainants argument that Supreme Court precedent, as well as the Commission’s recent decision in Guttman, which applied the cases cited by Joint Complainants, required a different result.

On April 10, 2019, Joint Shipper filed a motion requesting that the Commission expeditiously issue an order in this proceeding and clarify the scope of the Commission’s jurisdiction. Joint Shippers argued that this treatment was necessary as CFPL recently added terms to its “Transportation Policy” which require that shippers warrant the product has “come to rest,” thereby precluding them from making arguments to the contrary before the Commission. On April 24, 2019 CFPL and KMLT submitted an Answer arguing that the Motion was really an attempt to submit new evidence after the close of the record.

As of publication of this Report the Commission has not yet acted on the Initial Decision and exceptions raised in relation thereto.

j. American Aviation Supply LLC, et. al v. Buckeye Pipe Line Company, L.P. (OR19-26)

On June 5, 2019, American Aviation Supply LLC, Delta Air Lines, Inc., JetBlue Airways Corporation, and United Airlines, Inc. (“Complainants” or “Airlines”) filed a complaint against Buckeye Pipeline Company, L.P. (“Buckeye”) challenging the lawfulness of rates charged by the pipeline for the transportation of jet and aviation turbine fuel from Linden, New Jersey, to the New York City market. The Airlines alleged Buckeye is substantially overrecovering its cost of service, rendering its rates not just and reasonable. The Airlines rely on Page 700 data from Buckeye’s Form No. 6 report for 2018 as well as cost-of-service data for 2017, provided pursuant to a settlement, which segments Buckeye’s Eastern Products System (“EPS”) from its Long Island System (“LIS”). The Complaint argues that Buckeye’s two systems should be treated as one (i.e., treated on a “company-wide basis”) in evaluating cost of service, since they share an origin point and many assets. The Complaint argued that Buckeye’s rates are not grandfathered, and even if they were, that recovery is not barred. The Airlines sought reparations for past payments and the establishment of just and reasonable rates going forward.

On July 5, 2019, Buckeye filed an Answer arguing that a hearing was not warranted. Buckeye argued that the LIS and EPS should be evaluated separately as they use different assets and serve different markets. But Buckeye claimed that its rates are just and reasonable when evaluated under either method and disputed the adjustments made in the Complaint. Buckeye also claimed that its rates were grandfathered and asserted that the Airlines had failed to make a showing that there had been a “substantial change” in economic circumstances, which is required to challenge grandfathered rates.

On July 22, 2019, the Airlines concurrently filed a Response to Buckeye’s Answer and an Amended Complaint. The Amended Complaint included a new section detailing the Airlines’ substantial change of economic circumstances analysis regarding Buckeye’s rates. The Amended Complaint otherwise restated the arguments from the original Complaint without any substantial changes. In their concurrently filed Response, the Airlines stated that the issues in the Complaint are largely those left unresolved from a previous dispute in Docket No. OR12-28. The Airlines disputed Buckeye’s assertion that they had not met their prima facie burden to set the matter for a hearing. The Airlines also asserted that the issue of whether or not Buckeye’s rates should be evaluated on a company-wide basis is a factual question that must be resolved through a hearing. The Airlines also reiterated that Buckeye’s rates were not grandfathered and that even if they were, the Airlines should be given an opportunity to demonstrate that there has been a substantial change in economic circumstances.

On August 13, 2019, Buckeye filed its Answer to the Airlines’ Amended Complaint and to the Response in one pleading. The Answer to the Amended Complaint incorporated by reference Buckeye’s previous answer to the original Complaint. Buckeye claimed that it was denied fair process to address the new claims because they were filed in an Amended Complaint. Buckeye claimed the Airlines violated Rule 206 in filing their original Complaint by not presenting all the information that the Airlines possessed and that the filing of the Amended Complaint wasted Commission resources. Buckeye requested that the Amended Complaint be rejected or in the alternative that the prospective relief date be tied to the filing of the Amended Complaint. On the merits, Buckeye criticized the changed circumstances analysis for incorporating adjustments to its cost of service. The Answer also criticized the changed circumstances for analysis including market-based rates as those rates were per se just and reasonable, according to Buckeye. Buckeye also criticized the analysis for relying on company-wide data.

On August 28, 2019, the Airlines filed a Response to Buckeye’s Answer to the Amended Complaint. The Airlines disputed that the Amended Complaint prejudiced Buckeye, stating that amending complaints is common, is allowed by the Rules, and does not require the discovery of new information. The Airlines defended the use of company-wide data as proper for the reasons stated in their Complaint and Amended Complaint and also because Buckeye files its cost-of-service data on a company-wide basis. The Response defended the use of market-based rates in the analysis of changed circumstances since those rates are not per se just and reasonable, rather they are only presumed to be just and reasonable. The Response also alleged that the portion of Buckeye’s August 28, 2019 filing that was in Answer to the Airlines’ July 22 Response was procedurally improper.

As of the publication of this Report, the Commission has not acted on the Airlines’ Complaint or Amended Complaint.

k. Enbridge Energy, Limited Partnership (Docket No. IS19-231)

On March 1, 2019, Enbridge Energy, Limited Partnership (Enbridge) filed FERC Tariff No. 43.29.0 in Docket No. IS19-231-000, to implement the annual change to its Facilities Surcharge. On March 18, 2019, the Canadian Association of Petroleum Producers (CAPP) filed a protest and motion to intervene in the facilities surcharge filing, chiefly objecting to Enbridge’s elimination of the Accumulated Deferred Income Tax (ADIT) balance. CAPP argued that the Commission policy guidance on which Enbridge based its elimination does not apply to Enbridge given several factors, including other tax allowances available to Enbridge during the 2018 annual period. CAPP also questioned the validity of the guidance itself, proposing two alternative treatments of ADIT balances for the Commission. On March 22, 2019, Enbridge filed a response to the March 18 protest, arguing that CAPP’s protest was directly contrary to Commission policy and precedent with respect to ADIT and should be dismissed.

On March 29, 2019, the Commission issued an order accepting and suspending Enbridge’s March 1 tariff filing, to become effective April 1, 2019, subject to refund and subject to conditions and further review. In particular, the Commission requested supplemental information from Enbridge regarding its treatment of the income tax allowance and ADIT within 15 days of the order, and allowed CAPP to respond within 30 days of the order. On April 5, 2019, Enbridge filed its response to the Commission request for additional information. On April 25, 2019, CAPP filed a timely reply to the Enbridge response. Further Commission action is pending.

E. Tariff Rules Issues

1. CHS Inc., et al. v. Enterprise TE Products Pipeline Company, LLC (Docket Nos. OR13-25 and OR13-26)

As noted in prior reports, in 2013 several parties filed complaints against Enterprise TE Products Pipeline Co., LLC (“Enterprise TE”) challenging the lawfulness of a tariff that abandoned service for jet fuel and distillates. According to the complainants, Enterprise TE violated a settlement agreement that required Enterprise TE to continue offering transportation for jet fuel and distillates. The complainants requested that the Commission prevent Enterprise TE from abandoning service and award damages. On October 17, 2013, the Commission granted the complaints in part. The Commission interpreted the settlement agreement as requiring Enterprise TE to maintain service for the duration of the settlement. However, because it lacked jurisdiction over oil pipeline abandonments, the Commission could not require Enterprise TE to continue jet fuel and distillate service. Instead, the Commission set a hearing to determine any damages from the termination of service. On November 18, 2013, the complainants filed a request for a limited rehearing of the Commission’s order, claiming that the Commission erred in determining that it lacked the authority to direct Enterprise TE to continue to transport distillates and jet fuel and failing to enforce the terms of the settlement. Ultimately, Enterprise TE reached a settlement with all parties regarding the issue of damages and the hearing proceedings were terminated. However, two of the complainants, United Airlines, Inc. (“United”) and UPS Fuel Services, Inc. (“UPS”), remained parties to the proceedings to pursue the request for rehearing.

On May 19, 2016, the Commission denied the request for rehearing. In the Order on Rehearing, the Commission held that Enterprise TE’s decision to discontinue transportation service for distillate and jet fuel did not violate the pipeline’s common carrier obligations or the requirements set forth in the ICA. Further, the Commission explained that its decision to establish a proceeding to determine monetary damages was the proper remedy for Enterprise TE’s violation of the settlement agreement. The Commission concluded once again that an equitable remedy of specific performance was not appropriate

The Commission analyzed five main issues in the Rehearing Order. First, the Commission affirmed its prior holding that the decision by a common carrier oil pipeline to no longer provide transportation of a distinct product is an abandonment and not merely a refusal to provide service. The Commission explained that the best analogy to the definition of an abandonment concerning an oil pipeline is found in the Commission’s definition for abandonment for gas pipelines, and not in the definition used by the Surface Transportation Board in the context of railroads. Second, the Commission emphasized that nothing in the ICA changed the common law rule that common carriers were only required to provide the services that they held themselves out as being willing and able to provide. In its analysis, the Commission reviewed various case law addressing the development of the common carriers’ ability to limit the type of service that it provides, both before and after the adoption of the ICA. The Commission pointed to the tariff as the definition of the types of service that a common carrier oil pipeline holds itself out as providing. The Commission held that Enterprise TE was involved in an abandonment of service that was beyond the Commission’s jurisdiction to regulate. Third, the Commission rejected the argument that Enterprise TE’s discontinuation of transportation service for distillate and jet fuel involved a classification, regulation, or practice. The Commission clarified that the rates at issue were not based on a classification, which would require similar rates for similar groupings of commodities, but instead were commodity rates, which removes the rates from the scope of section 1(6) of the ICA. Fourth, the Commission reiterated that where service is abandoned entirely, and all shippers receiving the service are subject to the abandonment, there is no issue of discrimination under the ICA. Fifth, the Commission held that there is no ICA provision that would grant the Commission equitable authority to obstruct the decision of an oil pipeline to abandon a particular service.

On July 18, 2016, United and UPS, filed a petition for review of the Commission’s October 13, 2013 and May 19, 2016 orders with the D.C. Circuit in case No. 16-1245. That case was consolidated with Enterprise TE’s petition for review of the Commission’s October 13, 2013 order in case No. 13-1305. On December 13, 2016, the court granted an unopposed motion to voluntarily dismiss Case No. 13-1305, leaving only Case No. 16-1245 pending before the court. In Case No. 16-1245, the Joint Petitioner Brief was filed on February 14, 2017. Respondents’ brief was filed on May 1, 2017. Intervenor for Respondents’ brief was filed on May 16, 2017. Petitioners’ reply brief was filed on June 15, 2017. Final briefs were filed on July 6, 2017. Oral arguments were held on February 13, 2018.

On July 17, 2018, the D.C. Circuit issued an unpublished Per Curiam order in Case No. 16-1245 dismissing the petition for review for lack of standing. The court rejected Petitioner’s challenge to the Commission’s policy that it lacks the authority to prevent the abandonment of services, reasoning that the possibility of future abandonment without Commission intervention does not satisfy the present injury requirement for standing.

2. BP Products North America v. Sunoco Pipeline, L.P. (Docket No. OR15-25)

As noted in past reports, BP Products North America Inc. (“BP”) filed, on April 30, 2015, a complaint against Sunoco Pipeline, L.P. (“Sunoco”) concerning throughput and deficiency (“T&D”) agreements Sunoco entered into with other shippers on its Marysville to Toledo pipeline segment and a revision of the carrier’s proration policy. BP contended that Sunoco’s actions and conduct resulted in an undue preference for certain shippers and unduly discriminated against BP contrary to the ICA. Sunoco answered the complaint on June 1, 2015 disputing BP’s complaint allegations. The Commission, on July 31, 2015, set the complaint for hearing.

BP, Sunoco, FERC Trial Staff, and Intervenors, Marathon Petroleum Company LP (“Marathon”), PBF Holding Company LLC and Toledo Refining Company LLC (together “PBF”), filed their respective testimonies throughout 2016 with the hearing being held November 17-22, 2016. Of note, on November 1, 2016, PBF and Marathon filed motions to strike certain portions of BP’s witness testimony. Administrative Law Judge Patricia E. Hurt denied these motions on November 14, 2016, finding that PBF and Marathon failed to carry their burden of proof in demonstrating that the challenged testimony provisions were “irrelevant, immaterial, or unduly repetitious” under 18 C.F.R. § 385.509(a).

On November 11, 2016, PBF filed a motion requesting that the Commission treat certain materials in the exhibits filed by the parties as protected from public disclosure. The ALJ denied this motion at a prehearing conference on November 15, 2016, and simultaneously denied PBF’s motion for permission to file an interlocutory appeal. PBF subsequently filed an interlocutory appeal to the Commission on November 18, 2016, arguing that the ALJ had applied an overly stringent standard for PBF to prevent public disclosure of the contested materials. On December 8, 2016, the Commission issued an order stating that the appropriate standard for protection of confidential materials is whether disclosure is “likely to cause substantial harm to the competitive position of the person from whom the information was obtained.” The Commission determined that the ALJ may have applied too strict of a standard (i.e., requiring PBF to show that disclosure would in fact cause competitive harm) and remanded the matter for further consideration in accordance with the appropriate standard. On December 16, 2016, after holding oral argument on the issue, the ALJ issued an order confirming her prior ruling on releasing the contested information based on her finding that PBF had failed to show that public release was likely to cause competitive harm.

The Presiding Judge issued her Initial Decision on May 26, 2017, finding that “Sunoco unduly discriminated against BP by its process of awarding [T&Ds], by granting an undue preference via the terms and treatment of a particular shipper’s [T&Ds], and by revising its proration policy to favor certain shippers over BP.” Relying primarily on Colonial Pipeline Co., 146 FERC ¶ 61,206 (2014) and White Cliffs Pipeline, L.L.C., 148 FERC ¶ 61,037 (2014), the Presiding Judge held that Sunoco’s T&Ds with PBF and Marathon should be voided.

Additionally, the Presiding Judge held that the capacity allocation of the Marysville pipeline should be re-calculated according to the three shippers’ actual shipment data for the 12-month period preceding the effective date of the first unlawful T&D at issue in the proceeding (i.e., September 30, 2010). The Presiding Judge also recommended that the Sunoco proration policy be investigated by the Commission. In response to the issue of whether BP’s claim was time barred, the Presiding Judge found that the complaint was timely filed within the requirements of the ICA. Finally, with regard to damages, the Presiding Judge adopted an alternative damage calculation of FERC Trial Staff amounting to approximately $13.1 million for BP, without interest and related updating. The parties filed briefs on exception on July 26, 2017 and briefs opposing exceptions on September 18, 2017.

On October 15, 2018, the parties filed a Joint Unopposed Motion to Defer Ruling on the Initial Decision Pending Completion of Settlement Discussion. In the motion, the parties represented that they were close to reaching an agreement and requested the Commission strike the matter from the Commissions upcoming October 18, 2018 meeting agenda. On November 8, 2018, the parties filed a Notice of Settlement Agreement in Principle. On December 11, 2018 the parties jointly submitted the Offer of Settlement to the Commission. The Settlement resolves all issues in the proceeding. Under the Settlement, Sunoco will revise its proration policy, as well as revise the parties’ Initial Base Period Histories and Initial Heavy Ratios. Further, Sunoco’s T&D agreements with Marathon and PBF are null and void under the Settlement and an Alternative Allocation Charge (allowing shippers to pay to maintain their shipping history on the Marysville Pipeline) will expire four years following the effective date of the Settlement Agreement. Sunoco will also make a settlement payment to BP, which will withdraw its Complaint. On December 20, 2018, Commission Trial Staff filed Initial Comments supporting Commission certification of the Settlement Agreement. On March 21, 2019, the Commission issued a Letter Order Approving the Settlement.

3. Colonial Pipeline Company (Docket Nos. OR18-7, OR18-12, OR18‑17, and OR18-21)

On November 22, 2017, Epsilon Trading, LLC (“Epsilon”), Chevron Products Company (“Chevron”), and Valero Marketing and Supply Company (“Valero”) (collectively, “Complainants”) filed a Complaint in Docket No. OR18-7 challenging the lawfulness of the rates charged by Colonial Pipeline Company (“Colonial”) for transportation of petroleum products from all origins to all destinations under FERC Tariff No. 99.30.0. The complaint alleged that Colonial’s rates are unjust and unreasonable and that Colonial is over recovering its cost of service. The complaint also challenged the pipeline’s market-based and grandfathered rates. In addition, it argued that Colonial’s transmix and product loss allocation accounting are not properly stated in the tariff. Complainants seek prospective relief and reparations. On December 22, 2017, Colonial answered the complaint and argued that it lacked merit and should be dismissed. On January 8, 2018, the Complainants filed an answer to Colonial’s answer.

On February 2, 2017, BP Products North America, Inc., Trafigura Trading LLC, and TCPU, Inc. (“Joint Complainants”) filed a complaint in Docket No. OR18-12 challenging the lawfulness of the rates charged by Colonial for transportation of petroleum products, including aviation kerosene, motor gasoline, diesel, and jet fuel, from all origins to all destinations in the FERC Tariff No. 99.30.0 and FERC Tariff No. 98.34.0, and predecessor tariffs to both tariffs, alleging that pipeline’s interstate revenue in 2016 exceeded the pipeline’s interstate cost of service by an estimated level of $339.3 million based on reasonable and conservative adjustments to account for the impact of non-recurring pipeline integrity incidents, including related impacts therefrom, and other appropriate adjustments to Colonial’s reported cost-of-service and revenue data. The complaint challenged colonial’s cost-based tariffs, its market-based and grandfathered rates, as well as its transmix allocation policy. The complaint also requested consolidation with the complaint filed in Docket No. OR18-7. On March 5, 2018, Colonial answered the complaint and argued that it lacked merit and should be dismissed, or if not dismissed, that any proceeding be conducted in two phases, where the first phase would address Colonial’s market power and its market-based rates and the second phase would address Colonial’s indexed rates and any outstanding issues. On March 20, 2018, the Joint Complainants filed an answer to Colonial’s answer.

On March 1, 2018, TransMontaigne Product Services LLC (“TransMontaigne”) filed a complaint in Docket No. OR18-17 challenging the justness and reasonableness of Colonial’s cost and market-based rates from all origins to all destinations on similar grounds to the complaints filed in Docket Nos. OR18-7 and OR18-12, including challenges to Colonial’s cost-based tariffs, its market-based and grandfathered rates, as well as its transmix allocation policy. The complaint also requested consolidation with the complaint filed in Docket No. OR18-7 and OR18-12. On April 2, 2018, Colonial answered the complaint and argued that it lacked merit and should be dismissed, or if not dismissed, that any proceeding be conducted in two phases, where the first phase would address Colonial’s market power and its market-based rates and the second phase would address Colonial’s indexed rates and any outstanding issues. On April 17, 2018, TransMontaigne filed an answer to Colonial’s answer.

On April 20, 2018, CITGO Petroleum Corporation (“CITGO”) filed a complaint in Docket No. OR18-21 challenging the justness and reasonableness of Colonial’s cost and market-based rates from all origins to all destinations on similar grounds to the complaints filed in Docket Nos. OR18-7, OR18-12, and OR18-17, including challenges to Colonial’s cost-based tariffs, its market-based and grandfathered rates, as well as its transmix allocation policy. The complaint also requested consolidation with the complaint filed in Docket No. OR18-7, OR18-12, and OR18-17. On April 20, 2018, Colonial answered the complaint and argued that it lacked merit and should be dismissed, or if not dismissed, that any proceeding be conducted in two phases, where the first phase would address Colonial’s market power and its market-based rates and the second phase would address Colonial’s indexed rates and any outstanding issues. On April 17, 2018, CITGO filed an answer to Colonial’s answer.

On September 20, 2018, the Commission established hearing and settlement judge procedures consolidated Docket Nos. OR18-7, OR18-12, OR18-17, and OR18-21. The Commission set dual-track, but contemporaneous proceedings, one regarding indexed rates, grandfathered rate, and transmix and product loss allocation practices and charges, and another to address market-based rates. The Commission rejected the argument that market-based rates which diverge from a pipeline’s cost of service are per se unjust and unreasonable. However, the Commission set for hearing the issue of whether there have been significant changes in the relevant markets since Colonial was granted market-based rate authority that resulted in Colonial possessing significant market power.

In addition, on October 9, 2018, Southwest Airlines Co. and United Aviation Fuels Corp. filed a complaint against Colonial in Docket No. OR19-1. On October 16, 2018, Phillips 66 Company filed a similar Complaint in Docket No. OR19-4. Colonial answered both of the complaints, and complainants in both dockets filed additional answers thereto. On February 5, 2019, the Commission issued an order consolidating Docket Nos. OR19-1 and OR19-4 with Docket Nos. OR18-7-000, et al. for purposes of hearing and settlement judge procedures. On March 25, 2019, the Commission issued an order consolidating the complaint filed by American Airlines, Inc. in Docket No. OR19-16 with Docket Nos. OR18-7-000, et al. On May 22, 2019, the Commission issued an order consolidating the complaint filed by Metroplex Energy Inc. in Docket No. OR19-20 with Docket Nos. OR18-7-000, et al. On August 19, 2019, the Commission issued an order consolidating the complaint filed by Gunvor USA LLC in Docket No. OR19-27 with Docket Nos. OR18-7-000, et al.

The Complainants’ direct cost-based rate testimony was filed on September 9, 2019. The Complainants’ direct market-based rate testimony was filed on October 1, 2019. Ultimately, a hearing on cost-based rates issues is scheduled to begin on June 16, 2020 and another hearing on market-based rates issues is scheduled to begin on July 16, 2020. An Initial Decision is due on February 26, 2021.

In addition, the ongoing proceedings in Docket Nos. OR18-7, et al., additional similar complaints were filed by BP Products North American, et al. (OR19-10), TransMontaigne Product Services, LLC (OR19-8), and CITGO Petroleum Corporation (OR19-7) (together, the “PLA Complaints”). However, on June 26, 2019, the Commission found that the issues raised by the PLA Complaints were already set for hearing in the consolidated complaint proceeding in Docket Nos. OR18-7, et al. and dismissed the PLA Complaints accordingly.

On September 25, 2019, Pilot Travel Centers, LLC also filed a complaint, which was docketed in Docket No. OR19-36, challenging Colonial’s cost-based and market-based rates, as well as charges related to product loss allocation and transmix. That complaint sought consolidation with the consolidated complaint proceeding in Docket Nos. OR18-7, et al. Answers to this complaint are due October 25, 2019.

4. Colonial Pipeline Company (Docket No. OR16-17)

On May 9, 2016, Tricon Energy Ltd. and Rockbriar Partners Inc. filed a complaint alleging that it is unlawful for Colonial Pipeline Company (“Colonial”) to enforce the tariff modifications filed in Docket No. IS16-259-000 (discussed in our Spring 2017 and Fall 2017 reports) prior to Commission review and acceptance of that modification. On September 13, 2016, the Commission issued an Order on Complaint in Docket No. OR16-17. The Commission explained that it “requires additional information before rendering a decision on the Complaint.” The Commission then directed Colonial and the three other parties to respond to data request and requests for production of documents within 30 days of the order. The Commission explained that it would “defer action on the complaint until it receives and reviews the responses to the data request and requests for production of documents.”

On September 29, 2016, Colonial submitted a motion for expedited clarification, protective order, and extension of time for submission of discovery responses concerning the data requests and requests for production of documents in the Commission’s September 13 Order (“Motion”). The Motion explained, among other things, that the due process protections to be afforded to Colonial must be clarified because the Commission’s September 13 Order expands the scope of the proceeding without specifying the issues the Commission ultimately intends to rule on. Colonial requested that the Commission clarify the issues and provide Colonial with a timely opportunity to address those issues substantively. Colonial also requested that the Commission enter a protective order to safeguard certain information to be submitted as part of the discovery responses. Additionally, Colonial requested additional time to respond to the discovery requests.

On October 5, 2016, the Commission issued a Notice of Extension of Time providing Colonial until November 14 to respond to the data requests and requests for production of documents in the Commission’s September 13 Order.

On October 13, 2016, Tricon Energy Ltd. and Rockbriar Partners Inc. responded to the Commission’s data request. On the same date, Flint Hills Resources LP also responded to the Commission’s data request. On November 14, 2016, Concept Petroleum Marketing, LLC filed comments in the docket, and Colonial later filed a motion to reject those comments. On December 5, 2016, Emert Enterprises, LLC filed comments, and Colonial filed a motion to reject those comments as well.

On November 14, 2016, the Commission issued an order entering the proposed protective order sought by Colonial. In that order, the Commission noted that Colonial did not allege that any due process violations have occurred, and therefore the issue was not ripe for review. However, the Commission stated that the proceeding will comport with any and all due process requirements, Colonial will have an opportunity to address the substance of issues that warrant further examination by the Commission, and any alleged violations of due process may be raised during the course of the proceeding.

On November 16, 2016, Colonial responded to the Commission’s data request. On January 23, 2017, Costco Wholesale Corporation (“Costco”) submitted an answer to Colonial’s response to the Commission’s data request. On February 13, 2017, Colonial submitted a reply to Costco’s answer. More recently, on September 23, 2019, the Commission issued further information requests to update the record in the proceeding. Answers to these are due on October 23, 2019.

5. Colonial Pipeline Company (Docket No. OR19-23)

On May 1, 2019, TransMontaigne Partners L.P. and Metroplex Energy, Inc. filed a complaint against Colonial Pipeline Company in Docket No. OR19-23 challenging the lawfulness of the rate structures associated with “in-transit storage” and alleging that they unreasonably advantage and provide an undue preference to Colonial’s proprietary and affiliated storage operations. On May 31, 2019, Colonial answered the complaint, rebutting the allegation that storage and blending services at issue are subject to the jurisdiction of the Commission, among other points. Further answers were submitted by TransMontaigne Partners L.P. on June 17, 2019 and by Colonial on July 5, 2019. Commission action is pending.

6. Challenge to Leveret Pipeline Co. LLC/Mid-America Pipeline Co., LLC Tariffs (Docket Nos. IS17-498, et al.)

As noted in prior reports, on June 12 and 16, 2017, Leveret Pipeline Company LLC (“LPC”) and Mid-America Pipeline Company, LLC (“MAPL”) filed various tariff amendments to (i) reflect the transfer of certain assets and facilities from MAPL to LPC (effective immediately) and (ii) increase general commodity and incentive rates on their respective pipelines (effective July 1, 2017).

INEOS USA LLC (“INEOS”), a chemical manufacturer with a fractionator connected to the MAPL system, filed a protest and motion to intervene on June 26, 2017, arguing that the proposed LPC and MAPL tariff amendments would improperly deny INEOS the ability to utilize portions of the MAPL system and are unreasonably designed to favor affiliates of LPC and MAPL. INEOS requested that the Commission reject the proposed tariff amendments or, in the alternative, set the matter for hearing. LPC and MAPL submitted a joint response to INEOS’ protest on July 3, 2017 and INEOS filed an answer on July 10, 2017.

On July 12, 2017, subject to the authority delegated in absence of a Commission quorum, the Acting Director of the Division of Pipeline Regulation issued a letter order stating that the tariff amendments “may be unjust, unreasonable, unduly discriminatory, or preferential or otherwise unlawful” and, therefore, stated that the tariff amendments were “accepted for filing, and suspended, to become effective as proposed in their individual filings, subject to refund, and further Commission order.”

INEOS filed a request for rehearing on August 4, 2017 stating that FERC Staff erred by failing to set the tariff amendments for hearing and settlement judge procedures (despite finding that the tariff amendments may be unjust, unreasonable, or otherwise unlawful) and for failing to suspend the tariff amendments for the maximum period allowed by statute (seven months). On September 5, 2017, the Commission granted the rehearing request solely for the purpose of affording additional time for consideration of the matters raised.

The Commission issued an order on January 18, 2018, accepting LPC’s and MAPL’s tariffs to be effective on the dates requested and denying INEOS’ request for rehearing. First, the Commission stated that rejection or further hearing on the filed tariffs was unwarranted because the filings dealt mainly with administrative aspects of the transfer of assets between LPC and MAPL. Second, the Commission rejected INEOS’ rehearing request because the request related to cancellations of service contained in the tariff filings. The Commission stated that cancellations of service amount to an “abandonment” under the Interstate Commerce Act and the Commission has no jurisdiction over oil pipeline “abandonments.” Accordingly, the Commission concluded that no hearing or further investigation was warranted.

On February 20, 2018, INEOS filed a Request for Rehearing arguing that the January 2018 Order erred in three ways. First, by finding no jurisdiction over the transfer at issue or the cancellation filing. Second, by not rejecting the tariffs or setting them for hearing and/or settlement judge procedures. And third, by not consolidating the cases. INEOS characterized a communication it made with MAPL before the tariff filing as a “Connection Request” and the subsequent tariff revisions as a de facto denial of that request.

On March 7, 2018, MAPL and LPC filed a Request for Leave to Answer and Joint Answer to the INEOS Rehearing Request. The answer asserted that the corporate form of MAPL and LPC should not be ignored and that no connection request had been denied so arguments that the denial was unreasonable are premature.

On March 19, 2018, INEOS submitted a Petition for Review in the Court of Appeals for the D.C. Circuit associated with the July 2017 Order and the January 2018 Order. On March 20, 2018, the Commission granted INEOS February 20, 2018 rehearing request for the limited purpose of further consideration.

On June 1, 2018, the Commission issued an Order Denying Rehearing. The Commission found that “rehearing does not lie” because the January 2018 Order did not modify the result of the July 2017 Order. To the extent the rehearing request concerns the January 2018 Order’s acceptance or the tariffs contemplated in the July 2017 Order, the Commission rejected those arguments on the grounds they had already been argued by INEOS twice before and rejected. The Commission also rejected the request on the merits, restating its position on jurisdiction over abandonments and connections, and distinguishing the cases cited by INEOS.

On July 30, 2018, INEOS submitted another Petition for Review to the Court of Appeals for the D.C. Circuit concerning the July 2017 Order, January 2018 Order, and June 2018 Orders.

On September 6, 2018, the D.C. Circuit issued a Per Curiam order consolidating INEOS’s two petitions for review and rejecting motions to hold in abeyance as moot. On September 11, 2018, a 60-day briefing schedule was established with Petitioners’ initial brief due October 22, 2018. Subsequent to the briefing schedule being established, the Commission filed motions to dismiss the appeal and suspend the briefing schedule. As a result, the Court issued an order, on September 18, 2018, suspending the briefing schedule.

In its motion to dismiss, the Commission argues that its rejection of a protest is a refusal to initiate an investigation, and therefore unreviewable. The Commission claimed that INEOS was not left without a remedy because it could file a complaint under section 13 of the ICA. On September 27, 2018, INEOS responded to FERC’s motion to dismiss. INEOS argues that it is not simply challenging the Commission’s decision not to investigate. Rather, it is challenging FERC’s disclaimer of jurisdiction over the tariff revisions at issue, so review is proper. On October 2, 2018, the Commission filed a reply in support of its motion, arguing that the precedent cited by INEOS was distinguishable. The Commission asserts that only a decision to investigate may be challenged on jurisdictional grounds and that decisions not to investigate are still not reviewable even when they are based on disclaimers of jurisdiction. On November 14, 2018, the Court issued a Per Curiam Order referring the motion to dismiss to the merits panel.

On January 29, 2019, INEOS filed its Initial Brief of Petitioner, which was updated on February 6, 2019 to comply with Court rules regarding the overuse of acronyms. In its brief, INEOS asserts that the Court has jurisdiction over the tariff revisions, and therefore dismissal is inappropriate. INEOS also claims the ambiguous nature of FERC’s January order required INEOS to file both a rehearing request and a petition for review to preserve its rights. INEOS urged the Court to direct FERC to exercise jurisdiction over the Enterprise tariff revisions. INEOS argues that FERC should have pierced the corporate veil of the two affiliated companies if it had properly applied Commission policy and based its decision on the substantial evidence. INEOS also argues that the transfers at issue here are not complete abandonments according to FERC precedent because the transportation service, facilities, and direction will all remain the same after the cancellation. According to INEOS this amounts to an unexplained departure from precedent.

Respondent FERC filed its Brief on March 29, 2019. The Commission argued that the Court lacked jurisdiction because the decision not to investigate a tariff is unreviewable, because INEOS had not established injury-in-fact, and because the initial petition was prematurely filed pending rehearing by the Commission. On the merits, Respondent argued that the Commission reasonably explained how the tariffs would not impact the services used by INEOS and reasonably concluded that it lacked jurisdiction over the dispute as it concerned an abandonment. The Commission also argued that the dispute at issue is not actually premised on the tariff filings, but rather they revolve around INEOS’s interconnection request. On April 5, 2019, LPC and MAPL filed a Joint Intervenor Brief in Support of Respondent. This Brief raised the additional arguments that INEOS did not suffer any harm by the tariffs because nothing changed substantively before and after their filing.

On April 18, 2019, INEOS filed its Reply Brief. INEOS stressed that its claims were limited to a request that the Commission exercise jurisdiction over the tariff revisions for purposes of determining whether the pipelines violated section 3(1) of the ICA by discriminating against INEOS. INEOS also asserted that it suffered injury in the form of affiliate abuse. In response to the argument that nothing changed before and after the filings, INEOS argued that the filings delayed INEOS’ receipt of interconnection, and that delay of service is a sufficient injury to establish standing.

Oral argument was held on September 10, 2019.

7. BridgeTex Pipeline Company, LLC (Docket Nos. IS18-102, OR18-6, and OR18-3)

On October 30, 2017, BridgeTex Pipeline Company, LLC (“BridgeTex”) filed a petition for declaratory order (“PDO”) in Docket No. OR18-3 related to the proposed BridgeTex II Expansion Capacity project. The PDO sought approval of: (1) a proposed version of a tariff (subsequently filed in IS18-102), and (2) an overall rate structure and terms of service for a proposed expansion of the existing BridgeTex pipeline system, including an earlier addition of a new origin in Midland, Texas for service to Houston, Texas, referred to as the BridgeTex Expansion Capacity project. In the PDO, BridgeTex also sought a ruling that the regulatory assurance provided by the Commission in two earlier declaratory orders approving the original BridgeTex pipeline system and the initial expansion are not be affected by the BridgeTex II Expansion Capacity project.

On November 21, 2017, Occidental Energy Marketing, Inc. (“Occidental”) filed a protest regarding the PDO. Occidental argued that it underwrote the construction of the BridgeTex system and the terms and rates in the PDO are unduly discriminatory as compared to those available in the original open season. Occidental also alleged that the prorationing policy in the PDO was unduly discriminatory. Occidental contended that its original Transportation Service Agreement (“TSA”) should continue to govern its transportation on “Carrier Facilities,” which were defined to include “associated facilities and improvements.” The original TSA, according to Occidental, did not contemplate different tranches of capacity on the BridgeTex System. Also on November 21, 2017, Occidental filed a complaint against BridgeTex. The complaint alleged that BridgeTex unlawfully refused to provide service to Occidental under two existing tariffs and also discriminated against it in violation of the ICA.

On December 21, 2017, BridgeTex filed a response to the protest and complaint. BridgeTex asserted that the Commission has held that committed shippers from different open seasons are differently situated and may be treated differently. BridgeTex argues that because Occidental had the opportunity but declined to participate in the BridgeTex II Expansion Capacity project, it cannot now deny other shippers that participated and signed TSAs the benefit of rates and terms of service offered. BridgeTex disputed that Occidental underwrote the system and argued that the term “improvement” in Occidental’s TSA is not the same as “expansion.” Also on December 21, 2017, BridgeTex filed FERC Tariff Nos. 6.0.0 and 7.0.0 in Docket No. IS18-102 setting forth rules and regulations, and uncommitted and committed rates for the BridgeTex II Expansion Capacity Project to be effective on January 1, 2018. On December 22, 2017, Occidental protested the tariff filing and argued that BridgeTex has attempted to carve up capacity on its system into tranches of capacity with different rates and terms and conditions of service.

On January 19, 2018, the Commission issued an order that accepted and suspended the tariffs filed in Docket No. IS18-102 subject to refund and established hearing and settlement judge procedures for the tariff and the complaint in Docket No. OR18-6. In the same order, the Commission held in abeyance the PDO filed in Docket No. OR18-3. The Commission found that there were material issues of fact related to the fundamental issue of contract interpretation concerning the existing BridgeTex tariff and the TSA signed by Occidental, and particularly whether the definition of “Carrier Facilities” applies to BridgeTex II Expansion Capacity project or only contemplates the facilities installed at the time of the initial construction of the BridgeTex system. The Commission explained that the language “associated facilities and improvements” contained in the definition of “Carrier Facilities” is not clear on its face and therefore, to resolve the conflict, extrinsic evidence needs to be examined to ascertain the intentions of the parties. The Commission stated that it will address the merits of the regulatory rulings sought in the PDO after the contractual rights of the respective parties are resolved at hearing.

On January 30, 2018, BridgeTex filed a tariff pertaining to a supplemental open season on expansion capacity from the Permian Basin to East Houston, Texas, which resulted in additional volume commitments pursuant to a supplemental TSA. On March 1, 2018, the Commission accepted and suspended the tariff, subject to refund, set the tariff for hearing, and consolidated the proceeding with the ongoing proceedings in Docket Nos. IS18-102 and OR18-6. The PDO in Docket No. OR18-3 remains held in abeyance subject to the outcome of the consolidated proceedings. BridgeTex filed requests for rehearing to both the Commission’s January Order and its March Order. On August 16, 2018, the Commission dismissed both requests for rehearing because they did not seek rehearing of final Commission action.

On February 13, 2018, the Chief Administrative Law Judge recognized that the Settlement Judge declared an impasse following the first settlement conference, terminated settlement judge procedures, designated a Presiding Judge for the hearing, and set the hearing on a Track III schedule, with an Initial Decision due by April 30, 2019.

On February 19, 2019, however, Occidental notified the Commission that it had reached a settlement with BridgeTex resolving the claims set forth in its complaint and protests, and it withdrew its complaint and protests. The Chief Administrative Law Judge accepted the withdrawal and ordered the hearing proceeding terminated on March 14, 2019.

On June 19, 2019, the Commission issued an order granting BridgeTex’s October 30, 2017 PDO and the specific rulings requested concerning previous regulatory assurances.

8. Andeavor Field Services, LLC v. Mid-America Pipeline Company, LLC (Docket No. OR18-15)

On February 27, 2018, Andeavor Field Services, LLC (“Andeavor”) filed a complaint against Mid-America Pipeline Company, LLC (“MAPL”) and Enterprise Products Operating LLC (“Enterprise”) (together “Joint Respondents”). The Complaint alleged that MAPL was improperly imposing a ship-or-pay obligation on uncommitted shippers for existing capacity in violation of the ICA. These alleged ship-or-pay obligations were said to come from a Transportation Service Agreement (“TSA”) which the Commission approved in August 2011 pursuant to a declaratory order request. Andeavor contended that MAPL had misrepresented that portion of the TSA and requested the Commission either rescind or modify the August 2011 Declaratory Order to prohibit the imposition of ship-or-pay obligations on uncommitted shippers for existing capacity. Andeavor also alleged that the penalty for failure to ship-or-pay—seizure of product—allowed Joint Respondents to take advantage of the volatile market by strategically choosing the time to seize the line fill to the benefit of MAPL’s affiliate Enterprise. Andeavor also alleged this maneuver raised the possibility that MAPL was sharing shipper information in violation of Section 15(13) of the ICA.

On March 29, 2018, MAPL and Enterprise filed a Joint Answer to the Complaint. Joint Respondents claim that the obligations in the TSA are clear. Joint Respondents also claimed that the central issue was the terms of the TSA, and that the proper forum was a state court. Joint Respondents applied the Commission’s Arkla factors used to determine when the Commission should assume jurisdiction over a matter of contract interpretation. Joint Respondents also contended that Andeavor had not provided any evidence to justify its accusation that seizure of the line fill had been timed strategically or information had been shared improperly.

On April 12, 2018, Andeavor filed an Answer to Joint Respondents’ Joint Answer. Andeavor argued that the Complaint does not involve a “contract dispute,” asserting the wrongs alleged would violate the ICA regardless of the terms of the contract. Andeavor further contended that the Commission should exercise jurisdiction because the seizure of line fill is governed by the tariff, not the TSA. Andeavor also claimed the facts would justify exercising jurisdiction under the Arkla test.

On June 21, 2018, the Commission issued its Order on Complaint. The Commission found that “the dispute in this case turns on the intent of Mid-America and Andeavor’s predecessor, QEP-FS, in the formation of the contract at issue.” It therefore considered the Complaint a contract dispute and applied the Arkla factors. Applying these factors, the Commission declined to exercise jurisdiction stating: (i) the Commission has no special expertise to interpret contracts beyond a state court, (ii) there was no need for uniformity of interpretation, and (iii) resolution did not implicate the Commission’s regulatory responsibilities. The Commission did not believe the use of the line fill seizure terms of the tariff warranted jurisdiction because “the application of the tariff provision in question is a result of the contract dispute at issue here,” i.e., if the dispute had not arisen, those terms would not be invoked. The Commission also found no evidence MAPL was improperly disclosing shipper information. The Commission therefore dismissed the Complaint in its entirety.

On July 17, 2018, Andeavor filed a Request for Rehearing of the June 21 Order. The request claims the Complaint never requested the Commission actually interpret the contract, it only requested that the Commission find MAPL’s practices illegal under the ICA. Andeavor claimed it was only the Commission’s intent in issuing the August 2011 Declaratory Order, not the parties intent in signing the TSA, which was relevant to the Complaint. Andeavor also disputed the Commission’s application of the Arkla factors. On August 16, 2018, the Commission granted the rehearing request for the limited purpose of further consideration.

On April 18, 2019 the Commission denied Andeavor’s Request for Rehearing. The Commission found again that “this matter turns on an interpretation of the Agreement, and an ongoing state court proceeding is currently addressing that issue.” The Commission addressed Andeavor’s arguments that the ship-or-pay obligation violates the ICA, stating that “this argument only may become relevant after the contract has been interpreted. This issue will not become ripe until the ongoing state court proceeding is completed, and may never become ripe at all.” FERC stressed that it had discretion whether or not to exercise jurisdiction over contracts on file with the Commission. The Commission also stated that it “did not rely on Mid-America’s factual assertions” regarding the diversion of product to an affiliate. Rather, the Commission found that the “threshold contractual issues should be resolved first in the pending state court matter.”

9. Mid-America Pipeline Company, LLC and Seminole Pipeline Company LLC (Docket Nos. IS18-766 and IS18-767)

On September 28, 2018, Mid-America Pipeline Company, LLC (“MAPL”) filed FERC Tariff No. 74.7.0 to cancel and replace FERC Tariff No. 74.6.0 (Docket No. IS18-766) and Seminole Pipeline Company LLC (“Seminole”) filed FERC Tariff No. 2.14.0 to cancel and replace FERC Tariff No. 2.13.0 (Docket No. IS18-767). The two tariffs (together, “Revised Tariffs”), proposed three changes to the current tariffs. First, the Revised Tariffs proposed to give the carriers a lien on the shippers’ product as collateral. Second, the Revised Tariffs required financial assurances as a condition of receiving transportation services under certain circumstances. And third, new shippers who are affiliates of existing shippers would no longer be allocated capacity during periods of prorationing. MAPL and Seminole contended these changes were needed in light of companies creating affiliates to secure capacity and an increased credit risk among their shippers.

Andeavor Field Services, LLC (“Andeavor”) filed a Protest and Motion to Intervene in Docket No. IS18-766 on October 12, 2018, and in Docket No. IS18-767 on October 15, 2018. In its protests, Andeavor claimed all three tariff provisions were unduly discriminatory in violation of the Interstate Commerce Act (“ICA”). Andeavor also asserted that the burden of proof to justify a tariff change is on a carrier and neither MAPL nor Seminole had met this burden in their tariff filings. Andeavor also discussed its ongoing dispute with MAPL (OR18-15, discussed infra). Andeavor claims that the proposed lien provisions are too broad and allow the carriers too much discretion and that they could refuse service to captive shippers based on payment disputes the shippers undertook in good faith. And Andeavor claims the financial assurance provisions are too broad and grant too much discretion to the carriers which could result in discrimination against similarly situated shippers. Andeavor argues that the Revised Tariffs did not sufficiently justify the limit on allocating capacity to new shippers (i.e., those without historical volumes) who are affiliates of existing shippers who have established historical capacity interests. Andeavor also asserts those terms are impermissibly discriminatory.

On October 17, 2018, MAPL filed a Response to Andeavor’s Protest and Seminole filed a similar Response on October 22, 2018. The carriers argued that the terms proposed in the Revised Tariffs were commercially needed, were common in the industry, and that Andeavor’s concerns were hypothetical and overblown. Regarding the lien provisions, the carriers argued that Andeavor’s grievances were directed at existing tariff provisions, beyond the scope of the protest proceeding. The carriers assert that other pipelines include financial assurances provisions similar to the ones proposed, including affiliates of Andeavor. The carriers further asserted that pipelines are typically allowed significant discretion in conducting their business and it is improper to automatically assume they will abuse it. The carriers claimed the terms which disallow capacity allocations to affiliates of existing shippers are common in the industry and justified in light of recent shipper practices.

On October 23, 2018, Andeavor filed a Motion for Leave to Answer and Answer to MAPL’s response and on October 24, 2018 Andeavor filed a Motion for Leave to Answer and Answer to Seminole’s response. In the Answers, Andeavor sought to distinguish the existing tariff provisions from those in the Revised Tariff and stressed that the burden of proof is on a carrier in proposing new tariff terms. On October 24, 2018 and October 25, 2018 similar Answers were filed by MAPL and Seminole respectively. These Answers claimed Andeavor repeated arguments, changed past arguments, and made hyperbolic inaccuracies in relation to its previous Answers.

On October 25, 2018, the Commission issued an Order Accepting and Suspending Tariffs Subject to a Technical Conference and Consolidating Proceedings. The Commission found there to be “a number of issues requir[ing] additional clarification that can best be addressed at a technical conference, after which a resolution may be reached or further process ordered if necessary.” The Commission therefore accepted the Revised Tariffs and suspended them for the full seven-month period allowed under the ICA.

A technical conference was held on March 26, 2019. On April 15, 2019, the parties submitted their Initial Post-Technical Conference Comments. On April 29, 2019, MAPL and Seminole withdrew the disputed tariffs.

F. TAPS Issues

1. TAPS Quality Bank Litigation

The Trans Alaska Pipeline System (TAPS) Quality Bank (QB) makes monetary adjustments among TAPS shippers to account for the pipeline’s commingling of multiple crude oils that have different qualities and, therefore, different market values. As discussed in prior reports, the QB’s valuation of the TAPS crude streams has been the subject of extensive litigation at FERC, the Regulatory Commission of Alaska (and predecessor agencies), and the U. S. Court of Appeals for the D.C. Circuit since the late 1980s.

The current chapter of that litigation (still in progress) began in August 2013, when Flint Hills Resources Alaska, LLC (FHR), a TAPS shipper, supported by Petro Star Inc.(PSI), challenged the Quality Bank’s valuation of the Resid cut, the heaviest of the nine cuts used in valuing each shipper’s crude stream. After a hearing and an Administrative Law Judge’s Initial Decision rejecting FHR/PSI’s challenge, the Commission affirmed the Initial Decision in an order issued in November 2014. PSI then filed a petition for review to the D.C. Circuit, which the court granted in an opinion issued in August 2016 and remanded the case back to FERC. On remand, the Commission again rejected PSI’s arguments and reaffirmed the lawfulness of the QB methodology used to value the Resid cut.

On April 20, 2018, PSI filed a petition for review of FERC’s order on remand. After PSI filed its initial brief with the court, and shortly before FERC’s brief was due, FERC requested that the court remand the case to the Commission. The D.C. Circuit granted the Voluntary Remand Motion on March 7, 2019. In the Voluntary Remand Motion, FERC invited the parties to provide their respective positions on two questions: (1) the scope of issues properly before the agency on voluntary remand; and (2) the procedures to be employed by the agency in addressing those issues. Initial comments were filed on May 6, 2019, by Petro Star, Joint Parties (comprised of Anadarko Petroleum Corp., BP Exploration (Alaska) Inc., ConocoPhillips Alaska, Inc., Exxon Mobil Corp. and Tesoro Alaska Co. LLC), the Indicated TAPS Carriers (BP Pipelines (Alaska) Inc., ConocoPhillips Transportation Alaska, Inc., and ExxonMobil Pipeline Company), and the State of Alaska. Reply comments were filed on June 5, 2019. The matter is currently pending before the FERC.

2. PTE Pipeline LLC, FERC Docket No. IS18-686/RCA Docket P-18-018

The Point Thomson Unit (“PTU”), which holds both natural gas and condensate (light liquid hydrocarbons), lies on the Alaska North Slope 60 miles east of Prudhoe Bay and the Trans Alaska Pipeline System (“TAPS”) and west of the Arctic National Wildlife Refuge. PTE Pipeline LLC (“PTE Pipeline”) owns and operates a liquids pipeline – the Point Thomson Export Pipeline (“PTEP”) – that transports PTU-produced condensate through 22 miles of 12-inch pipeline to an interconnection with the Badami Pipeline. The Badami Pipeline connects to Endicott Pipeline that connects to TAPS at Pump Station No. 1.

On July 30, 2018, PTE Pipeline filed proposed rate increases for interstate and intrastate service on PTEP at the FERC and the Regulatory Commission of Alaska (RCA), respectively. The State of Alaska protested the filings. Both agencies issued orders allowing the proposed rate increases to become effective, subject to refund, on September 1, 2018. Settlement conferences and a technical conference were held between December 2018 and June 2019. An uncontested settlement agreement was filed with both the FERC and the RCA on August 1, 2019. By order issued August 27, 2019, the RCA accepted the settlement agreement and closed the docket. The agreement is pending approval before the FERC.

G. Petitions for Declaratory Orders

During 2018 and 2019, pipelines filed petitions for declaratory orders (“PDO”) requesting approval of various committed rate structures under Transportation Service Agreements (“TSA”) that support new pipeline projects and expansions. Many PDOs asked the Commission to waive its initial rate regulations at 18 C.F.R. § 342.2 (which require a pipeline to submit cost and revenue data, or a supporting affidavit, when filing to implement their rates for the first time) for the committed rates. In 2019, the Commission granted certain PDOs when the open season process was fair and transparent and the terms were consistent with prior Commission precedent and the Interstate Commerce Act. The Commission generally rejected the requests for waiver of the initial rate regulations, and made its orders contingent on the subject pipeline complying with 18 C.F.R. § 342.2 when filing its tariffs to implement the committed rates.

1. Buckeye Pipe Line Company, L.P. and Laurel Pipe Line Company, L.P. (Docket Nos. OR18-22, IS19-277, and IS19-278)

On April 30, 2018, Buckeye Pipe Line Company, L.P. (“Buckeye”) and Laurel Pipe Line Company, L.P. (“Laurel”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service under a joint tariff for a new petroleum products service from origin points in Michigan, Ohio, and Pennsylvania to destination points in Ohio and Pennsylvania.

Specifically, Buckeye and Laurel asked the Commission to approve: (1) a rate structure where the committed shippers pay a premium, relative to the uncommitted rate, in exchange for firm service; (2) committed rates that vary, based on the committed volumes; (3) a prorationing policy that reserves 90 percent of the new capacity for committed shippers, and 10 percent for uncommitted shippers; (4) a prorationing policy that uses historical volumes data to allocate volumes to uncommitted shippers; (5) committed shippers’ right to ship incremental barrels (i.e., barrels that exceed their committed volumes) on a firm basis, provided that there is no reduction in the capacity available for uncommitted shippers; (6) a proposal to place the committed rates into service in phases; and (7) additional rights for committed shippers, including the right to take committed service at new origin points that may be added to the system in the future.

On May 30, 2018, the Pennsylvania Public Utility Commission (“PaPUC”) filed a limited protest in Docket No. OR18-22, in light of the fact that the PDO would impact intrastate service (and thus, the PaPUC’s jurisdiction) on Laurel’s system. On June 12, 2018, Giant Eagle, Inc., Guttman Energy, Inc., Lucknow-Highspire Terminals LLC, Monroe Energy, LLC, Philadelphia Energy Solutions Refining & Marketing LLC, and Sheetz, Inc. (collectively, the “Indicated Parties”) filed a protest challenging Buckeye and Laurel’s PDO. The Indicated Parties argued that the proposed committed service would negatively impact shippers on Laurel’s existing intrastate system, and unreasonably interfere with an ongoing, related proceeding before the PaPUC. On July 12, 2018, the PaPUC rejected an application wherein Laurel proposed to reverse its intrastate pipeline system and begin providing the joint service at issue in the PDO.

On April 8, 2019, Laurel and Buckeye filed tariffs in Docket Nos. IS19-277 and IS19-278, respectively, to implement the committed rates that were the subject of their PDO (“Committed Rate Filings”). On April 23, 2019, the Indicated Parties filed a protest and argued that the Committed Rate Filings, if approved, would unreasonably circumvent the PaPUC’s order finding that Laurel was not authorized to reverse its intrastate pipeline system, and interfere with ongoing cases regarding bi-directional service on Laurel’s system. On May 1, 2019, the PaPUC filed a letter asking the Commission to allow the PaPUC to resolve the outstanding issues related to Laurel’s intrastate system before issuing a substantive ruling on the Committed Rate Filings.

On June 6, 2019, the Commission rejected Buckeye and Laurel’s Committed Rate Filings without prejudice. The Commission found that it was unclear whether Buckeye and Laurel could legally provide the services at issue in the Committed Rate Filings, given the ongoing disputes before the PaPUC and related court proceedings. The Commission also determined that the facts were not sufficiently clear to support a conclusion that the TSAs would be lawful under the Commission’s committed rate policies and the Interstate Commerce Act. Accordingly, the Commission rejected the Committed Rate Filings without prejudice to Buckeye and Laurel submitting new filings that addressed the Commission’s concerns.

On July 11, 2019, Buckeye, Laurel, and the Indicated Parties filed a Joint Offer of Settlement to resolve their disputes in Docket Nos. OR18-22, IS19-277, and IS19-278, as well as the related proceedings before the PaPUC. On September 26, 2019, the Commission approved the Joint Offer of Settlement as fair and reasonable and in the public interest.

2. Enterprise Crude Pipeline LLC (Docket No. OR18-27)

On June 27, 2018, Enterprise Crude Pipeline LLC (“Enterprise Crude”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on a new crude oil pipeline system from points in New Mexico to Midland, Texas.

Specifically, Enterprise Crude asked the Commission to approve: (1) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service during prorationing; (2) TSA provisions establishing a minimum volume commitment of 100,000 barrels per day for a ten year term; (3) a prorationing policy that reserves 90 percent of the new capacity for committed shippers, and 10 percent for uncommitted shippers; (4) a prorationing policy that uses historical volumes data to allocate capacity to historical uncommitted shippers, and a pro rata or lottery mechanism to allocate capacity to uncommitted shippers that are not historical shippers; and (5) contract extension rights for committed shippers. On July 16, 2018, Enterprise Crude filed tariffs in Docket Nos. IS18-634 and IS18-646 to implement the committed rates that were the subject of its PDO.

On March 27, 2019, the Commission denied the PDO, finding that Enterprise Crude failed to demonstrate that its proposed 100,000 barrel per day minimum volume commitment was lawful. The Commission reasoned that an excessive minimum volume commitment (i.e., one that is not required for operational reasons) essentially reserves a pipeline system for large shippers, which is unduly discriminatory and inconsistent with the Interstate Commerce Act’s common carriage requirements. The order also noted that the committed rates took effect by operation of law when Enterprise Crude’s July 16, 2018 tariff filing implementing those rates was not protested or set for an investigation.

3. Targa NGL Pipeline Company LLC (Docket No. OR18-30)

On July 27, 2018, Targa NGL Pipeline Company LLC (“Targa NGL”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on a new natural gas liquids pipeline system from Oklahoma to Texas.

Specifically, Targa NGL asked the Commission to approve: (1) a committed rate structure where committed shippers can elect to either pay a premium rate for firm service, or a discounted rate for non-firm service, during prorationing; (2) a prorationing policy that reserves 90 percent of the capacity for firm committed shippers, and 10 percent for uncommitted shippers; and (3) a prorationing policy that uses committed volumes to allocate capacity to non-firm committed shippers, and historical volumes data to allocate capacity to uncommitted shippers.

Targa NGL also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSA, and requested a waiver of 18 C.F.R. § 342.2, which requires pipelines to support their initial rate filings with either cost and revenue data, or an affidavit stating that the proposed rates have been agreed to by an unaffiliated shipper who intends to take the new service.

On March 11, 2019, the Commission conditionally granted Targa NGL’s PDO, finding that Targa NGL’s TSA was consistent with the Interstate Commerce Act. The Commission denied Targa NGL’s request for waiver of 18 C.F.R. § 342.2, and held that committed rates are subject to the Commission’s initial rate regulations. The Commission made its order contingent on Targa NGL complying with the initial rate regulations when submitting its tariff filing to implement the committed rates. Because Targa NGL’s only committed shipper was an affiliate, the Commission explained that Targa NGL would need to file cost-of-service data to support its committed rates, or to secure the agreement of a non-affiliated shipper before filing to implement the new rates.

On April 10, 2019, Targa NGL filed a Request for Rehearing, and argued that the Commission’s March 11, 2019 order was inconsistent with its earlier orders finding that oil pipelines did not need to support their committed rates with cost-of-service data. The Commission has not taken further action in this proceeding.

4. Magellan Pipeline Company, L.P. (Docket No. OR18-31)

On August 8, 2018, Magellan Pipeline Company, L.P. (“Magellan”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on a refined products pipeline system in Texas.

Specifically, Magellan asked the Commission to approve: (1) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service during prorationing; (2) committed rates that vary, based on the contract term and committed volumes; (3) a prorationing policy that reserves 90 percent of the capacity for committed shippers, and 10 percent for uncommitted shippers; (4) TSA provisions allowing Magellan to increase the committed rates or establish a surcharge to recover increased regulatory compliance costs; (5) a proposal to use new capacity and underutilized capacity to provide firm committed service; (6) committed shippers’ rights to increase their committed volumes over a specified time period; and (7) additional rights for committed shippers, including contract assignment rights, extension rights, and a right to take firm service at new origin and destination points that may be added to the system in the future. Magellan also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSAs, and to waive its regulations requiring a pipeline to submit a supporting affidavit or cost data to establish initial committed rates under 18 C.F.R. § 342.2.

On March 11, 2019, the Commission conditionally granted Magellan’s PDO, finding that Magellan’s TSAs were consistent with the Interstate Commerce Act. The Commission also granted Magellan’s request to treat the committed rates as settlement rates during the term of the TSA, but denied the request for waiver of 18 C.F.R. § 342.2, and conditioned its order on Magellan complying with the initial rate regulations when submitting its tariff filing to implement the committed rates.

5. Cactus II Pipeline LLC (Docket No. OR18-32)

On August 9, 2018, Cactus II Pipeline, LLC (“Cactus II”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on a new crude oil pipeline system in Texas.

Specifically, Cactus II asked the Commission to approve: (1) a proposal to lease new capacity to provide the committed service; (2) a contract term that is tied to the aggregate volumes shipped, rather than a specific time period; (3) committed rates and in-kind deductions that vary, based on the open season, the type and level of volume commitment, and the actual volumes shipped; (4) a committed rate structure where the committed shippers pay a discount, relative to the uncommitted rate, in exchange for a volume commitment; (5) TSA provisions allowing Cactus II to establish a surcharge to recover increased regulatory compliance costs; (6) a most-favored nations clause that would require Cactus II to decrease the committed rate if it offers a lower rate to another shipper in the future; (7) a prorationing policy that allocates 90 percent of the capacity to committed shippers and historical uncommitted shippers, and allocates 10 percent of the capacity to new uncommitted shippers; (8) a proposal to hold a new open season for committed service on up to 90 percent of the available capacity, when the TSAs expire; and (9) additional rights for committed shippers, including the right to take committed service at origin and destination points that may be added to the system in the future, a limited right to convert an acreage dedication into additional committed volumes, and the right to assume committed volumes from expired or terminated TSAs. Cactus II also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSAs, and to waive its regulations requiring a pipeline to submit a supporting affidavit or cost data to establish initial committed rates under 18 C.F.R. § 342.2.

On June 3, 2019, the Commission conditionally granted part of Cactus II’s PDO, finding that Cactus II’s TSAs were consistent with the Interstate Commerce Act. The Commission granted Cactus II’s request to treat the committed rates as settlement rates during the term of the TSA, but denied the request for waiver of 18 C.F.R. § 342.2, and conditioned its order on Cactus II complying with the initial rate regulations when submitting its tariff filing to implement the committed rates. The Commission also declined to approve Cactus II’s proposal to hold a new open season for up to 90 percent of the system capacity when the TSAs expire, reasoning that the proposal was premature, and not ripe for Commission review.

6. Enterprise TE Products Pipeline Company LLC (Docket No. OR18-34)

On August 18, 2019, Enterprise TE Products Pipeline Company LLC (“TEPPCO”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on an expansion of its refined products and liquefied petroleum gas pipeline system.

Specifically, TEPPCO asked the Commission to approve: (1) a committed rate structure where committed shippers can elect to either pay a premium rate for firm service, or a discounted rate for non-firm service, during prorationing; (2) a prorationing policy that reserves 90 percent of the capacity for committed shippers, and 10 percent for uncommitted shippers; and (3) a prorationing policy that uses committed volumes to allocate capacity to non-firm committed shippers, and historical volumes data to allocate capacity to uncommitted shippers. TEPPCO also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSA, and to waive its regulations requiring a pipeline to submit a supporting affidavit or cost data to establish initial committed rates under 18 C.F.R. § 342.2.

On March 11, 2019, the Commission issued an order granting TEPPCO’s PDO, finding that the TSAs were consistent with the Interstate Commerce Act. The Commission also found that TEPPCO’s request for waiver of the initial rate regulations in the PDO was moot, because TEPPCO subsequently submitted an initial rate filing that complied with 18 C.F.R. § 342.2.

7. White Cliffs Pipeline, L.L.C. (Docket No. OR18-35)

On August 16, 2018, White Cliffs Pipeline, L.L.C. (“White Cliffs”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service under a joint tariff for a new natural gas liquids service from Colorado to Texas.

Specifically, White Cliffs asked the Commission to approve: (1) a committed rate structure where the committed rates and certain terms of service vary, depending on the volume commitment; (2) a committed rate structure where the committed shippers pay a discount, relative to the uncommitted rate, in exchange for a volume commitment; (3) a proration policy that uses a pro rata method to allocate 5 percent of the capacity to uncommitted shippers who are not historical shippers; (4) a proration policy that allocates 95 percent of the capacity to historical uncommitted shippers and committed shippers, based on historical volumes and committed volumes, respectively; (5) TSA provisions allowing White Cliffs to increase the committed rates to recover increased regulatory compliance costs; and (6) additional rights for committed shippers, including rollover rights, and the right to take committed service on new capacity that may be added to the system in the future. White Cliffs also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSAs, and to waive its regulations requiring a pipeline to submit a supporting affidavit or cost data to establish initial committed rates under 18 C.F.R. § 342.2.

On August 13, 2019, the Commission conditionally granted part of White Cliffs’ PDO, finding that the majority of the TSA was consistent with the Interstate Commerce Act. However, the Commission found that White Cliffs’ proration policy failed to allocate at least 10 percent of the system capacity to uncommitted shippers, and was therefore inconsistent with the Commission’s committed rate policies. The Commission clarified that White Cliffs’ right to recover compliance costs pursuant to the TSA provisions extends only to committed shippers. The Commission also granted White Cliffs’ request to treat the committed rates as settlement rates during the term of the TSA, but denied the request for waiver of 18 C.F.R. § 342.2, and conditioned its order on White Cliffs complying with the initial rate regulations when submitting its tariff filing to implement the committed rates.

8. Medallion Pipeline Company, LLC (Docket No. OR18-37)

On September 10, 2018, Medallion Pipeline Company, LLC (“Medallion”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on an expansion of its crude oil pipeline system in Texas.

Specifically, Medallion asked the Commission to approve: (1) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service during prorationing; (2) a prorationing policy that reserves 90 percent of the capacity for committed shippers, and 10 percent for uncommitted shippers; (3) committed rates that vary, depending on the contract term; (4) TSA provisions that allow committed shippers to increase their committed volumes over a specified time period; (5) a proposal to offer existing committed shippers a lower rate, in exchange for extending their initial TSAs; and (6) additional rights for committed shippers, including contract extension rights and assignment rights. Medallion also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSAs, and to waive its regulations requiring a pipeline to submit a supporting affidavit or cost data to establish initial committed rates under 18 C.F.R. § 342.2.

On June 26, 2019, the Commission conditionally granted Medallion’s PDO, finding that the TSA was consistent with the Interstate Commerce Act. The Commission granted Medallion’s request to treat the committed rates as settlement rates during the term of the TSA, but denied the request for waiver of 18 C.F.R. § 342.2, and conditioned its order on Medallion complying with the initial rate regulations when submitting its tariff filing to implement the committed rates.

9. EnLink Crude Pipeline, LLC (Docket No. OR18-38)

On September 12, 2018, EnLink Crude Pipeline, LLC (“EnLink”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on an expansion of its crude oil pipeline system in Texas.

Specifically, EnLink asked the Commission to approve: (1) a prorationing policy that reserves 90 percent of the capacity for committed shippers, and 10 percent for uncommitted shippers; (2) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service during prorationing; (3) TSA provisions allowing EnLink to recover increased regulatory compliance costs; and (4) additional rights for committed shippers, including contract extension rights, expansion capacity rights, and assignment rights. EnLink’s TSAs also state that the committed rates would be treated as settlement rates during the term of the TSAs, and would not be subject to the Commission’s initial rate regulations under 18 C.F.R. § 342.2.

On March 27, 2019, the Commission conditionally granted EnLink’s PDO, finding that the TSA was consistent with the Interstate Commerce Act. The Commission clarified that EnLink’s right to recover compliance costs pursuant to the TSA extends only to committed shippers. The Commission granted EnLink’s request to treat the committed rates as settlement rates, but denied the request for waiver of 18 C.F.R. § 342.2, and conditioned its order on EnLink complying with the initial rate regulations when submitting its tariff filing to implement the committed rates.

10. EPIC Crude Pipeline, LP (Docket No. OR19-2)

On October 10, 2018, EPIC Crude Pipeline, LP (“EPIC Crude”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on a new crude oil pipeline system in Texas.

Specifically, EPIC Crude asked the Commission to approve: (1) a prorationing policy that reserves 90 percent of the capacity for committed shippers, and 10 percent for uncommitted shippers; (2) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service during prorationing; (3) EPIC Crude’s right to recall and re-offer unutilized capacity from an acreage dedication committed shipper; and (4) additional rights for committed shippers, including contract extension rights. EPIC Crude also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSA, and to waive its regulations requiring a pipeline to submit a supporting affidavit or cost data to establish initial committed rates under 18 C.F.R. § 342.2.

On April 11, 2019, the Commission conditionally granted EPIC Crude’s PDO, finding that the TSA was consistent with the Interstate Commerce Act. The Commission clarified that any open season re-offering acreage dedication capacity should be limited to the period of time remaining in the initial term and rates of the original TSA. The Commission granted EPIC Crude’s request to treat the committed rates as settlement rates, but denied the request for waiver of 18 C.F.R. § 342.2, and conditioned its order on EPIC Crude complying with the initial rate regulations when submitting its tariff filing to implement the committed rates.

11. EnLink Delaware Crude Pipeline, LLC (Docket No. OR19-3)

On October 11, 2018, EnLink Delaware Crude Pipeline, LLC (“EnLink Delaware”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on a new crude oil pipeline system in Texas and New Mexico.

Specifically, EnLink Delaware asked the Commission to approve: (1) a prorationing policy that reserves 90 percent of the capacity for committed shippers, and 10 percent for uncommitted shippers; (2) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service during prorationing; (3) TSA provisions allowing EnLink Delaware to recover increased regulatory compliance costs; (4) EnLink Delaware’s ability to hold a supplemental open season; and (5) additional rights for committed shippers, including contract extension rights, expansion capacity rights, and assignment rights. EnLink Delaware’s TSAs also state that the committed rates would be treated as settlement rates during the term of the TSAs, and would not be subject to the Commission’s initial rate regulations under 18 C.F.R. § 342.2.

On March 27, 2019 the Commission conditionally granted EnLink Delaware’s PDO, finding that the TSA was consistent with the Interstate Commerce Act. The Commission clarified that EnLink Delaware’s right to recover compliance costs pursuant to the TSA provisions extends only to committed shippers. The Commission granted EnLink Delaware’s request to treat the committed rates as settlement rates, but denied the request for waiver of 18 C.F.R. § 342.2, and conditioned its order on EnLink Delaware complying with the initial rate regulations when submitting its tariff filing to implement the committed rates.

12. Iron Horse Pipeline, LLC (Docket No. OR19-9)

On November 16, 2018, Iron Horse Pipeline, LLC (“Iron Horse”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on a new crude oil pipeline system in Wyoming.

Specifically, Iron Horse asked the Commission to approve: (1) a prorationing policy that reserves 90 percent of the capacity for committed shippers, and 10 percent for uncommitted shippers; and (2) a proration policy that allocates uses historical volumes data and committed volumes to allocate capacity to uncommitted shippers and committed shippers, respectively. Iron Horse also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSA. On April 11, 2019, the Commission granted Iron Horse’s PDO in its entirety.

13. EnLink NGL Pipeline, LP (Docket No. OR19-11)

On December 11, 2018, EnLink NGL Pipeline, LP (“EnLink NGL”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on an expansion of its natural gas liquids system in Texas and Louisiana.

Specifically, EnLink NGL asked the Commission to approve: (1) a prorationing policy that reserves 90 percent of the capacity for committed shippers, and 10 percent for uncommitted shippers; (2) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service on the expansion; and (3) additional rights for committed shippers, including extension rights, expansion capacity rights, and a right to take committed service at new origin and destination points that may be added to the system in the future.

On April 11, 2019, the Commission conditionally granted EnLink NGL’s PDO, finding that the TSA was consistent with the Interstate Commerce Act. The Commission also found that the expansion capacity constituted a new service, and conditioned its order on EnLink NGL complying with the initial rate regulations when submitting its tariff filing to implement the committed rates.

14. Plantation Pipe Line Company (Docket No. OR19-12)

On December 20, 2018, Plantation Pipe Line Company (“Plantation”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on an expansion of its refined petroleum products pipeline system.

Specifically, Plantation asked the Commission to approve: (1) a proration policy that allocated 20,000 barrels per day of the expansion capacity to committed shippers, and seventy percent of the total pipeline capacity to uncommitted shippers; (2) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service on the expansion; (3) the provision of interim service prior to the in-service date of the expansion; and (4) committed shippers’ ability to ship incremental barrels (i.e., barrels that exceed their committed volumes) on a non-firm basis. Plantation also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSA, and to waive its regulations requiring a pipeline to submit a supporting affidavit or cost data to establish initial committed rates under 18 C.F.R. § 342.2.

On April 11, 2019, the Commission conditionally granted Plantation’s PDO, finding that the TSA was consistent with the Interstate Commerce Act. The Commission granted Plantation’s request to treat the committed rates as settlement rates, but denied the request for waiver of 18 C.F.R. § 342.2, and conditioned its order on Plantation complying with the initial rate regulations when submitting its tariff filing to implement the committed rates.

15. ONEOK Elk Creek Pipeline, L.L.C. (Docket Nos. OR19-13, IS19-303, IS19-689)

On December 20, 2018, ONEOK Elk Creek Pipeline, L.L.C. (“Elk Creek”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on a natural gas liquids pipeline from Wyoming to Kansas.

Specifically, Elk Creek asked the Commission to approve: (1) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service during prorationing; (2) a proration policy that reserves 90 percent of the capacity for committed shippers, and 10 percent for uncommitted shippers; (3) a proration policy that uses historical volumes data to allocate capacity to uncommitted shippers; and (4) additional rights for committed shippers, including a right of first refusal on expansion capacity that may be added in the future, and contract extension rights. The Commission has not issued an order on Elk Creek’s PDO.

On April 30, 2019, Elk Creek submitted its tariff filing in Docket No. IS19-303 (“April Initial Rate Filing”) to establish its $2.0789 per barrel committed rate for natural gas liquids service from Wyoming to Kansas. Elk Creek also filed the cost and revenue data required under 18 C.F.R. § 342.2 to support its initial uncommitted rate of $2.0689 per barrel. On May 30, 2019, Elk Creek submitted a supplemental filing in Docket No. IS19-303 that: (1) set the committed rate at the cost-of-service rate of $2.0689 per barrel; (2) decreased the uncommitted rate to $2.0589 per barrel; and (3) clarified the shippers that only took service on one segment of Elk Creek’s system would pay a lower rate than shippers who took service on the entire system.

On June 28, 2019, the Commission rejected Elk Creek’s April Initial Rate Filing without prejudice. The Commission stated that while Elk Creek’s initial committed rate was supported by cost-of-service data, it appeared that the committed rate would not be subject to the Commission’s indexing or cost-of-service regulations for the duration of the TSA. The Commission therefore rejected Elk Creek’s committed rate as inconsistent with its cost-of-service ratemaking regulations.

On July 2, 2019, Elk Creek submitted a new tariff filing in Docket No. IS19-689 (“July Initial Rate Filing”) to establish the $2.0689 per barrel committed rate that the Commission previously rejected. Elk Creek explained that under the TSA, the committed rate will be $0.01 higher than the uncommitted rate for the same movement. Further, because the uncommitted rate would be subject to indexing and cost-of-service challenges, the committed rate (which would increase or decrease along with the uncommitted rate) would be subject to the same. Therefore, Elk Creek argued that the Commission’s June 28, 2019 order erred in concluding that its committed rates would not be subject to the Commission’s cost-of-service ratemaking regulations.

On August 1, 2019, Elk Creek’s July Initial Rate Filing took effect by operation of law when the Commission declined to issue an order rejecting the filing, or setting it for an investigation. On August 2, 2019, Commissioner Glick and Commissioner LaFleur issued a Joint Statement explaining that they would have rejected Elk Creek’s July Initial Rate Filing for failing to comply with the Commission’s cost-of-service ratemaking regulations. Conversely, Commissioner McNamee issued a statement concluding that Elk Creek’s July Initial Rate Filing satisfied the Commission’s committed rate policies. Chairman Chatterjee—the only other sitting Commissioner on August 2, 2019—did not provide a statement or otherwise address Elk Creek’s July Initial Rate Filing.

16. Sunoco Pipeline L.P. (Docket No. OR19-15)

On December 28, 2018, Sunoco Pipeline L.P. (“Sunoco”) filed a PDO requesting the Commission to approve the rate structure and terms for committed service on a natural gas liquids pipeline from Pennsylvania to Delaware.

Specifically, Sunoco asked the Commission to approve: (1) a committed rate structure where committed shippers pay a premium, relative to the uncommitted rate, for firm service during prorationing; (2) a proposal to offer firm service on capacity that was subject to an earlier TSA, which was cancelled before the pipeline began providing service; (3) TSA provisions allowing Sunoco to increase the committed rates to recover increased regulatory compliance costs; and (4) committed shippers’ rights to take committed service at origin and destination points that may be added to the system in the future. Sunoco also asked the Commission to find that the committed rates would be treated as settlement rates during the term of the TSAs, and to waive its regulations requiring a pipeline to submit a supporting affidavit or cost data to establish initial committed rates under 18 C.F.R. § 342.2.

On May 20, 2019, the Commission conditionally granted Sunoco’s PDO, finding that the TSA was consistent with the Interstate Commerce Act. The Commission granted Sunoco’s request to treat the committed rates as settlement rates during the term of the TSA, but denied the request for waiver of 18 C.F.R. § 342.2, and conditioned its order on Sunoco complying with the initial rate regulations when submitting its tariff filing to implement the committed rates.

The Committee acknowledges with great appreciation the primary contribution to the preparation of this report by Thomas C. Kirby of Steptoe & Johnson LLP; Keith Coyle, and Ashleigh Krick of Babst, Calland, Clements and Zomnir, P.C.; and Christopher M. Randall of Latham & Watkins LLP.

    Authors